NORTH AYRSHIRE COUNCIL 
29th October 2025                                                                                                                                                            
Planning Committee 
Locality  
Reference 25/00399/PP
Application Registered 4th September 2025
Decision Due 4th November 2025
Ward Garnock Valley 
Recommendation  Approved subject to condition 
__________________________________________________________________ 
Location  Wardlaw Wood Windfarm, Dalry 
Applicant  CWP Energy Ltd 
Proposal  Application under Section 42 of the Town and Country
Planning (Scotland) Act 1997 to amend condition 1 of
planning permission N/02/00906/PP to extend the
operational life of Dalry Community Wind Farm until
October 2038
___________________________________________________________________ 
1. Description 
A Section 42 application has been submitted in relation to a condition attached to a planning
permission for a wind farm development at Wardlaw Wood near Dalry. The development
was granted planning permission in June 2005 (ref. 02/00906/PP) and has been operational
since June 2006. The wind farm has an installed capacity of 18MW, consisting of 6 no. 3MW
Vestas turbines with blade tips of 125m above ground level.  Condition 1 requires the
development to cease, and the site restored by 6th October 2028. 
At the time of the application in 2002, the nominal lifespan of the wind farm was anticipated
by the developer to be 25 years. The condition was set at 25 years and one week from the
date of the Planning Committee date meeting held on 29th September 2003 when the
development was authorised. A Section 75 obligation was entered into which took until June
2005 to conclude. The planning permission was then formally granted on 14th June 2005,
with development operational by June 2006.

Page 2

Consequently, condition 1 as currently worded would not provide 25 years of operational life 
(25 years from June 2006 would be June 2031). Moreover, there is no distinction made in
the condition between the operational phase of the development and the restoration phase. 
For the avoidance of doubt, the application relates to the original 6 turbine wind farm located
on a former coniferous forestry plantation known as Wardlaw Wood, which is located
immediately to the west of Baidland Hill and Cockrobin Hill some 3.6km to the northwest of
Dalry. There are another 22 wind turbines in the vicinity, 8 of which are owned and operated
by the applicant at Millour Hill and 14 at Kelburn by Green Hill Energy Ltd (a subsidiary of
RES). 
The area of the site is 75.4 hectares. It comprises upland plateau moorland where 6 wind
turbines have been operating since 2006. The ground level varies from approximately 300m
- 330m above sea level. It is located at the southwestern area of the cluster of 28 turbines
which comprise Dalry Community Windfarm, Millour Hill Windfarm (to the east) and the
Kelburn Windfarm (to the north). 
The moorland site was afforested during the 1980s with a large conifer plantation. This was
largely clear felled prior to the construction of the Wardlaw Wood windfarm during 2005. 
There are small remnants of sitka spruce remaining as well as some self-seeded trees
which have grown since the wind farm was developed. There are stone access tracks which
lead into the site, terminating at each turbine. 
The operator of the wind farm now seeks to amend condition 1 which relates to the duration
of the planning permission and the decommissioning and restoration of the site. They are
seeking a further 10 years of operational time and an associated revision to the
decommissioning/site restoration. 
The current wording of condition 1 requires that the wind turbines and associated buildings
and equipment shall be removed and the land restored to its former condition on or before
6th October 2028.  The applicant states that the windfarm is still operating and that the
turbines are capable of producing electricity during the coming decade. 
An application under Section 42 of the Act, if granted, creates a new planning permission
without altering the conditions on the previously granted permission. The planning authority
must consider "only the question of the conditions to which planning permission should be
granted." 
In this case, as the planning permission to develop the windfarm has been implemented,
this report will consider only the issue of the proposed amendment to condition 1 and shall
have no bearing on the other conditions relating to the planning permission for the
development, some of which related to the construction phase and some the operational
phase. The application does not relate to the other wind farm developments in the vicinity of
the application site. 
2. Consultations and Representations 
Neighbour notification was undertaken in accordance with statutory requirements, and the
application was advertised in a local newspaper. A total of four comments were received

Page 3

from members of the public, all objecting to the proposed change to the lifetime of the wind
farm.  In addition, comments have been received from the Ayrshire & Arran Bat Group. 
1. There is no need to have the extension. The owners benefit greatly whilst the local
community gets very little benefit. High energy prices are paid by consumers who have to
put up with the "eyesores" dominating the skyline.  All the lifetime extension will do is make
more money for the owners. 
Response: The circumstances and policy context for determining the application are
discussed in the Analysis section below. 
2. Just because the applicant states that they have not received any noise complaints does
not mean that people living locally are not affected by turbine noise. The constant rumble of
the aggregate number of turbines in this area prevents use of outdoor garden areas at
certain times due to adverse noise impacts. 
Response: The wind turbines are required to operate within noise certain limits, as set by
planning permission 02/00906/PP. Although the wind farm has operated for over 19 years
without any noise complaints, such concerns can be reported to the Council for investigation
at any time. The Council's Environmental Health service has raised no objections in their
consultation response (below). 
3. The community benefit fund pays less than the required amount. There  is little evidence
of any sums being used for the benefit of Dalry. 
Response: This is not a material planning consideration. 
4. Property values are already affected and would be affected for longer by the proposed
lifetime extension. 
Response: This is not a material planning consideration. 
5.The proposed change to the decommissioning plan is merely to suit the applicant. A
ring-fenced levy should be put in place to ensure there is money available for
decommissioning. 
Response: The current condition is not fit for purpose and requires to be reviewed. It should
be noted that there is an existing Section 75 obligation in place which secures a financial
bond for site restoration in the event of failure by the developer. 
6. The relevant community council was not directly notified of the application as is required
under Section 35A of the Town and Country Planning (Scotland) Act 1997. 
Response: Section 35A relates to pre-application consultation, which was not applicable in
this case since the proposal is to amend a condition on an existing planning permission
under Section 42 (and is not an application for a new major development). Dalry Community
Council are sent a weekly list of planning applications each week and is entitled to comment
on any planning application in their area as they see fit. 
7. Individual objections do not appear fully on the planning portal and are not reflected in
comment totals, reducing transparency and public confidence.

Page 4

Response: There is no statutory requirement to publish representations online. Comments
made by members of the public are considered and addressed in the Committee Report. 
8. Proposed changes or extensions must be screened under the Town and Country
Planning (Environmental Impact Assessment) (Scotland) Regulations 2017. The Council
appears to have accepted the developer's claim that no new impacts exist based solely on
the absence of physical changes. Since the original 2003 EIA, multiple renewable projects
have been built or consented, fundamentally changing the baseline. 
Response: This is not relevant to the application, since there is no change proposed to the
development itself, nor any proposed extension to its scale. Consideration of the application
is limited to planning condition 1 attached to planning permission ref. 02/00906/PP for
Wardlaw Wood wind farm as granted by the Council in 2005. The proposed changes to
condition 1 would not in themselves result in any significant new environmental effects. 
9. A consented solar farm and battery storage within the site will be operated by the same
company and reliant on the wind farm's infrastructure cannot operate if the wind farm is
decommissioned. This interdependency demonstrates that cumulative impacts exist and
must be reassessed. 
Response: The applicant has requested a review of condition 1 of planning permission
02/00906/PP. The consented battery energy storage development would be linked to the
other wind turbines operated by the applicant in addition to those within the current
application site. The implications of the current condition in relation to the consented solar
farm development are discussed in the Analysis below. 
10. The lifetime extension, the solar and BESS projects, and the proposed Crosbie Wind
Farm are interlinked. Continued operation affects Crosbie's and Wardlaw Wood's technical
and financial viability, as shown by the developer's objection to Crosbie. Determining this
application in isolation risks prejudicing the Scottish Ministers' decision on Crosbie and
failing to assess cumulative effects, contrary to NPF4 Policy 32 and the EIA Regulations.
Approving dependent projects before determining whether the wind farm continues raises
questions about deliverability and proper cumulative assessment. 
Response: The current application relates to a very specific issue and must be determined
on its own merits. Given its very limited scope, that of the lifespan and decommissioning of
an existing wind farm, it is not considered necessary to await the outcome of other unrelated
applications. 
11. The environmental and cumulative context has changed significantly since 2003.
Prolonging the project delays site restoration and extends industrialisation of Muirshiel
Regional Park. No cumulative impact assessment appears to have been undertaken,
contrary to Regulation 4 of  the EIA Regulations and NPF4 Policy 32. 
Response: See Analysis with respect to the national and local policy framework for
renewable energy and specifically the handling of wind farm developments. Policy 32 of
NPF4 addresses aquaculture and is not considered relevant to the current application. 
12. Absence of community benefit and socio-economic considerations. NPF4 Policy 11
requires renewable developments to "maximise net economic impact, including local and

Page 5

community socio-economic benefits." This proposal offers none. It creates no new
employment or investment and extends restrictions on public access and recreation,
contrary to NPF4 Policy 14 and the Council's duties under the Equality Act 2010 and the
Fairer Scotland Duty. 
Response: There is no new development proposed. Public access to the site is already
available and this is not proposed to change. 
13. A Section 75 planning obligation could secure mitigation, but none has been proposed. 
Response: As noted above, there is an existing Section 75 obligation in place which secures
a financial bond for site restoration in the event of failure by the developer. 
14. The proposed Crosbie Wind Farm offers approximately £396,000 per year in community
benefit for 30 years (about £11.8m total). Approving this application without conditions risks
blocking Crosbie and denying significant local benefit. This is a material consideration in
assessing the public interest 
Response: This is not a material planning consideration and is of no relevance to the
application under consideration. 
Ayrshire & Arran Bat Group - In general terms, older wind farms, such as this one, are
less likely to have been designed and sited with a full consideration of bat conservation in
mind. This, therefore, may result in large numbers of bat casualties over the course of the
wind farms lifespan. This is as a result of the combination of lack of, or incomplete
preconstruction bat survey work, and the siting and operation of turbines without adequate
reference to the mitigation hierarchy. As we do not know the exact circumstances of the bat
evaluation carried out, relevant to this particular wind farm and its subsequent lifespan
request, we request that the following precautionary and proportionate requirements are
made part of any S42 consent in order to mitigate for any significant effects on bats arising
from this proposal. 
Response: Bat conservation was considered as part of the environmental impact
assessment carried out for the original planning application between 2002 and 2005. The
only matter under consideration is condition 1 of planning permission 02/00906/PP. 
Consultations 
Dalry Community Council (DCC) – does not object to the application but raise concerns
about the consultation process. DCC considers that they should have been consulted at the
start of the application process. However, in their response, DCC advise that they support
renewable energy in principle and are not opposed in principle to extending the life of the
existing site. DCC want a fair, lawful, transparent process, acts in the public interest, and not
for any individual. They state that Wardlaw Wood Wind Farm and Dalry Community Wind
Farm are the same site. The site pays community benefit to the Dalry Parish Boundary
Trust. The current application seeks a 10-year extension to October 2038 with no new
turbines. They note that the original Environmental Impact Assessment is from 2003 and
that a solar farm and a battery storage facility have since been consented within the site
boundary. These projects rely on the wind farm’s infrastructure. They have requested that
the Council issue a fresh EIA screening for this Section 42 application and publish the
reasons. If screening identifies gaps, please seek updated environmental information on

Page 6

cumulative effects. They also request that the application is requested against NPF4 Policy
11 on maximising local socio-economic benefit, Policy 14 on health and access to green
space, and Policy 3 on biodiversity. Extended operation delays restoration and prolongs
impacts within the regional park. If the Council is minded to grant planning permission, DCC
requests proportionate mitigation secured by conditions or a Section 75 agreement tied to
impacts, including:
• Safe public access measures and path improvements where appropriate.
• Habitat and peatland enhancement during the extended term.
• An updated decommissioning and restoration bond sized to the 2038 end date. 
Response: Noted. Taking each of the points raised in turn: 
All community councils in North Ayrshire are sent a weekly list of planning applications that
have been validated by the Council. This is the trigger for planning consultations thus
enabling community councils to put forward their views on any application either in their
area or elsewhere. Nonetheless, Dalry Community Council contacted the Planning Service
on 2nd October requesting that they be consulted. In response, they were provided with 14
days in which to submit any comments and duly responded on 15th October 2025. 
Dalry Community Council’s request for a fresh screening opinion is noted but not supported.
The application seeks to amend a planning condition in relation to the duration of the
planning permission for the six-turbine wind farm at Wardlaw Wood, known as Dalry
Community Wind Farm. It is not considered that the proposed extension of time would
directly result in any additional significant environmental effects. 
The application requires to be assessed only in relation to condition 1 of the planning
permission: the development is operational and only the duration of the planning permission
is under consideration at this time. 
The relevant provisions of NPF4 and the North Ayrshire LDP are discussed in the Analysis
section below. 
There is no requirement for “additional” mitigation arising from the proposed extension of
time. The scope of the application relates to the wording of condition 1 and nothing more: if
the Council do not consider that the proposed extension of time is appropriate, it has the
power to refuse the application. 
As noted elsewhere in this report, it is not proposed to alter any physical characteristics of
the development. Public access to the site is, and would remain, available. No ground
disturbance is proposed in the application. Habitat and peatland enhancement is outside
the scope of the proposal and has not been applied for. It would be unreasonable, and
contrary to the parameters for section 42 applications, for the planning authority to require
works outside the scope of the proposed amendment to condition 1. 
If approved, the revised text of condition 1 would provide for an updated decommissioning
plan. 
Finally, regardless of the outcome of the application, there is a restoration bond in place
under the existing Section 75 obligation in the event that the applicant (or any successor in
title) is unable to fulfil its obligations in this respect.

Page 7

NAC Environmental Health - No objections. 
NATS (En route) plc - No objections. 
Ministry of Defence - No objections. 
Glasgow Airport - No objections. 
Prestwick Airport - No objections. 
Response: Noted. 
3. Analysis 
Section 42 of the Town and Country Planning (Scotland) Act 1997 is a statutory mechanism
which allows for the submission of a planning application without complying with
condition(s) subject to which a previous permission was granted. As noted above, Section
42 of the Act stipulates that in this type of application the "planning authority shall consider
only the question of the conditions subject to which permission should be granted." 
The main determining issue in this case is whether the proposed amendments to condition 1
would accord with the relevant development plan policies for the site and in respect of any
other material planning considerations. 
National and local government policy supports all forms of renewable energy developments,
including the life extension of existing wind farms. NPF4 Policy 11 a) states that
"development proposals for all forms of renewable, low-carbon and zero emissions
technologies will be supported. These include: i. wind farms including repowering,
extending, expanding and extending the life of existing wind farms;"  Part of of Policy 11
states that, whilst "consents for development proposals may be time-limited... areas
identified for wind farms are, however, expected to be suitable for use in perpetuity." 
Similarly, Policy 29 of the adopted North Ayrshire LDP supports wind farm developments,
subject to meeting a range of criteria, including establishing the use of the site for energy
infrastructure development. In this case, no new development is proposed and the only
matter for consideration is the duration of the planning permission and its subsequent
decommissioning. Extending the lifespan of a wind farm development is supported once a
site has been established. Policy 29 states that "proposals should include redundancy plans
which will demonstrate how apparatus will be timeously removed as reasonably soon as the
approved scheme ceases operation." The site operator advises that the current wind
turbines on the site are fully operational and will continue to operate during the coming
decade. The turbines are maintained by a specialist contractor, Vestas, who have a local
depot based in Dalry. 
The applicant states that the windfarm is still operating and that the turbines are capable of
producing electricity during the coming decade. There are no community, safety or
environmental reasons to indicate otherwise. As such, the proposals to extend the life of the
wind farm accord with the development plan. The eventual decommissioning of the wind
farm would be addressed in the proposed variation to condition 1.   
There is no evidence available to indicate whether or not there was a technical reason as to
why 6th October 2028 was chosen as the expiry date for the planning permission, other than

Page 8

being 25 years and one week from the date the application was considered by the Council's
Planning Committee.  The turbines started operating in June 2006. As stated above, 25
years of operational life would take until June 2031, yet condition 1 requires
decommissioning and restoration by 6th October 2028. In effect, the lifetime extension would
amount to just over 7 years more than the "nominal" 25 years identified by the applicant
when they originally applied during 2002. 
The applicant has proposed the following text as an amendment to condition 1: 
Condition 1a. Permission for the development shall apply from the date of approval and the
development will cease to generate electricity by no later than the 6th of October 2038. 
Reason: To reflect the lifetime of the development 
Condition 1b. That, unless otherwise agreed in writing by North Ayrshire Council as
Planning Authority, the site shall be decommissioned after 35 years of becoming
operational. A decommissioning plan shall be submitted for the written approval of North
Ayrshire Council as Planning Authority during the 34th year of operation, which shall include
details of restoration and aftercare for the site. Thereafter, the decommissioning plan shall
be implemented to the satisfaction of North Ayrshire Council as Planning Authority. 
Reason: To safeguard the amenity of the site and its surroundings. 
Scottish Government Planning Circular 4/1998 sets out the tests for planning conditions, as
follows: 
- Need for a condition 
- Relevance to planning 
- Relevance to the development to be permitted 
- Ability to enforce 
- Precision 
- Reasonableness 
The two parts of the proposed amendment could be combined into a single condition in
accordance with the Council’s standard procedures for drafting conditions. Amendments to
the applicant's proposed wording would bring the text into compliance with the tests of
Circular 4/1998. 
It is recognised that the text of the existing condition, with regards to the restoration of the
site "to its former condition" is imprecise and unlikely to be achievable. In order to restore
the land to its "former condition" would require the planting of a coniferous forestry
plantation (this being the former use of the site before the development took place). This
would not be readily achievable and may not be desirable for other reasons, including
habitat impacts and the need for permission from Scottish Forestry. Furthermore, planning
permission was granted for the development of a solar array on the land during 2024 (ref.
24/00773/PP). The solar array would utilise the ground on which the wind farm has been
developed, without interfering with the turbines, and has an expected lifetime of 40 years
from its commissioning. Replanting a coniferous woodland would not be compatible with the
consented solar array development, assuming its implementation. Thus, the current text is
incompatible with national policy on addressing the nature and climate crises as well as the
more recent planning permission on the land.

Page 9

The date set by the existing condition is also arbitrary, in that it takes no account of the time
it took to negotiate and conclude a Section 75 obligation and does not distinguish between
the operational and restoration phases of the development. Rather than providing the
'nominal' 25 years of electricity envisaged by the applicant, the existing condition, in effect,
provides just over 22 years between commissioning and site restoration. Given the lengthy
timescale required for decommissioning and site restoration, there would be less than 22
years available for electricity generation. 
Consideration must also be taken of the national planning policy which states that areas
identified for wind farms are "expected to be suitable for use in perpetuity." The fundamental
test, that of the need for a condition, must therefore be satisfied. Whilst national planning
policy establishes that areas identified for wind farms are "expected to be suitable for use in
perpetuity" it is reasonable to expect that large items of mechanical plant such as wind
turbines will require to be replaced at some point simply due to their age and deteriorating
condition. Wind turbine technology continues to evolve, thus, the turbine specifications of
the early 2000s are likely to be superseded by the 2030s. Accordingly, the need for a time
limit condition is met. However, it must be sufficiently clear and precise as to the duration of
the planning permission and what is then expected of the site operator upon the end of the
operational phase. Taking these factors into account, it is proposed to amend the text of
condition 1 as follows: 
1. Condition 1 of planning permission N/02/00906/PP shall cease to have effect and shall be
replaced as follows: 
(a) the wind farm development on the land (as granted planning permission on 14th June
2005 and commissioned during June 2006) will cease to generate electricity not later than
midnight on 6th October 2038; 
(b) within the year prior to 6th October 2038, an updated decommissioning plan for the wind
farm development shall be submitted by the site operator for the written approval of North
Ayrshire Council as Planning Authority. The decommissioning plan shall include details of
restoration and aftercare for the wind farm development together with a detailed timetable
for its implementation; 
(c) the decommissioning plan as may be approved under part (b) shall be implemented by
the site operator to the satisfaction of North Ayrshire Council as Planning Authority. 
Reason: To extend the lifetime of the wind farm development whilst ensuring that the
redundant plant and equipment is removed and the land restored to a satisfactory condition
upon the end of its operational life. 
In summary, the current wording of condition 1 would provide far less than the anticipated
25 years operational time, since the condition was drafted in such a way as to prevent even
the "nominal" lifespan from being achievable, since no account was taken of the lead-in time
between authorising the development, concluding the consent and
constructing/commissioning the turbines. In addition, the turbines are estimated to have
more than a decade of serviceable use ahead, exceeding the original expectations of the
developer. The proposed change to condition 1 would extend the operational life of
Wardlaw Wood wind farm until 6th October 2038, giving a total operational lifetime of 32
years and 4 months. Although ten years later than the limits set by the current condition, this
represents an additional seven years and four months of operational time, after which the

Page 10

development would require to be decommissioned, and the affected land restored. If any of
the turbines becomes redundant before then, condition 2 of the original planning permission
requires their removal (and this condition would not change). Controls over noise impacts
(conditions 15 and 16) would also remain extant. 
In conclusion, the application to amend condition 1 of planning permission N/02/00906/PP
accords with the development plan and there are no material considerations to indicate
otherwise. Approval of the application is therefore recommended, subject to the condition
set out below. 
4. Full Recommendation 
Approved subject to condition 
Condition 
1. Condition 1 of planning permission N/02/00906/PP shall cease to have effect and
shall be replaced as follows: 
(a) the wind farm development on the land (as granted planning permission on 14th June
2005 and commissioned during June 2006) will cease to generate electricity not later than
midnight on 6th October 2038; 
(b) within the year prior to 6th October 2038, an updated decommissioning plan for the wind
farm development shall be submitted by the site operator for the written approval of North
Ayrshire Council as Planning Authority. The decommissioning plan shall include details of
restoration and aftercare for the wind farm development together with a detailed timetable
for its implementation; 
(c) the decommissioning plan as may be approved under part (b) shall be implemented by
the site operator to the satisfaction of North Ayrshire Council as Planning Authority. 
Reason 
To extend the lifetime of the wind farm development whilst ensuring that the
redundant plant and equipment is removed and the land restored to a satisfactory condition
upon the end of its operational life. 
Allan Finlayson 
Chief Planning Officer           
For further information please contact Mr A Hume Planning Officer on 01294 324318.