Democracy Spraffa

24-00327- Sannox Sand Quarry Sannox Brodick Isle Of Arran KA27 8JD

North Ayrshire Council · 19 March 2025
Back to Planning Committee — 19 March 2025 and its agenda

Text extracted from the council's PDF. Layout and reading order may differ from the original.

Original council PDF · Download plain text

Page 1

NORTH AYRSHIRE COUNCIL 
19th March 2025                                                                                                                                                            
Planning Committee 
Locality  Isle of Arran
Reference 24/00327/ALO
Application Registered 17th April 2024
Decision Due 17th June 2024
Ward Arran 
Recommendation  Approved with no Conditions 
__________________________________________________________________ 
Location  Sannox Sand Quarry Sannox Brodick Isle Of Arran
North Ayrshire
KA27 8JD 
Applicant  John Thomson Construction Ltd F.a.o Mr Benjamin
Cook 
Proposal  Discharge of S.75 agreement which was initially put in
place in 1999 in connection with planning permission
97/00653/PP and subsequently varied in 2012 in
connection with planning permission 10/00212/PP 
___________________________________________________________________ 
1. Description 
This can be ascertained by reference to the attached plans and photographs. 
The application seeks permission to discharge a legal obligation which was entered into
under Section 75 of the Town and Country Planning (Scotland) Act 1997 in relation to the
operation of a sand and gravel quarry at Sannox, Isle of Arran and to refund the associated
sum of money deposited with the Council by the applicant at the time as a bond for the
future restoration of the quarry area. 
The legal agreement was originally in relation to the conditional planning permission
97/00653/PP (N/01/97/0207) which was granted by the planning committee on 3rd March
1999, subject to a legal agreement being made to cover potential future restoration costs for
the site.  The planning permission was subsequently issued following legal agreement.

Page 2

Legal Services has previously confirmed the background timeline of the bond amount as
being: 
July 1999 - S75 legal agreement between John Thomson Construction Ltd (JTC) as
operator, Sannox Estates as landowner and North Ayrshire Council in relation to planning
permission 97/00653/PP; 
January 2002 - confirmation by JTC of a £10,000 supporting restoration bond from Bank of
Scotland being in place; 
2010 - Planning permission 10/00212/PP granted for continuation of quarrying operations
until 2021; 
2012 - A Minute of Variation of the existing Section 75 Agreement was concluded which
required JTC to lodge a cash sum of £10,000 with the Council, which was lodged with
Finance Services at the time; 
Legal Services have confirmed that, in accordance with Clause Two of the 2012 Variation,
the cash was submitted and was to be held by the Council until the subjects are restored to
(the Council's) reasonable satisfaction. 
The planning permission for the site has since been subsequently extended for further
periods, most recently in planning permission 20/00710/PP for continuation of the existing
quarrying operations and future westward extension of the quarry, which was granted at
planning committee on 25th February 2021. 
20/00710/PP was granted subject to twelve conditions, which largely replicated previous
planning conditions on the operation of the quarry.  A new Condition 1 required the
agreement and provision of documentary evidence of a sufficient bond amount for
restoration of the future extended quarry area being in place prior to the commencement of
the westward expansion.   
Following advice provided to the Council by its engaged advisors, Alan Doak Consulting, a
new Condition 2 was also applied which introduced the requirement for regular (four yearly)
reporting of the extent of ongoing works and projected works for the following four year
period.  This was to allow an audit of existing operations and thus ensure that sufficient
financial protection arrangements will always be in place for any required site restoration. 
The advice given by the consultants had been that this is now common industry practice in
such matters, rather than the deposit of a lump sum of cash secured by legal agreement and
it is noted that this approach is also consistent with the Scottish Government Chief Planner's
advice to planning authorities that legal agreements should not be used as justification for
planning approvals.   
Since 20/00710/PP was issued, ownership and operation of the quarry has changed from
John Thomson Construction to Arran Aggregates Ltd, an established quarrying business on

Page 3

the island operated by Murchie Sand and Gravel Ltd, and the first four yearly report under
Condition 2 has not yet been submitted.  Arran Aggregates have confirmed that they are
working up the audit of operations for submission to the council in line with the condition 2 of
20/00710/PP. 
Given the above change in ownership, this planning application has been submitted as JTC
now seek the final discharge of their Section 75 legal agreement and the return of the
£10,000 sum which was lodged with the Council, given that financial responsibility for the
quarry has now passed to the new operators Arran Aggregates.  Arran Aggregates have
separately confirmed to Planning Officers that they are to continue with the existing
operations and also intend to implement the previously approved planning permission for
westward expansion in due course.     
The quarry site is approximately 250m to the north of the settlement of Sannox, on the
northeast coast of the Isle of Arran.  It is adjoined on three sides by the Sannox Burn with
Sannox Golf Course further to the north and north-west; a residential property (Sonaburn)
adjoins at the north-east corner, and to the south are agricultural fields and a cricket field.
The whole site is within the North Arran National Scenic Area (NSA) and approximately 1km
east of the North Arran Wild Land Area (WLA).  At its closest point the extension would be
100m east of the Arran Moors Special Protection Area (SPA) which is classified for its
breeding population of hen harriers.   
The site is located within the countryside area, as identified within the adopted 2019 North
Ayrshire Local Development Plan ("the LDP").  The development was assessed and found
to accord with the LDP in 20/00710/PP.  The same LDP remains in place and circumstances
'on the ground' have not changed significantly in the interim. 
This application proposal relates to the discharge of a legal agreement only and does not
propose any alteration of operations or site boundaries.  It does not therefore raise any
strategic planning policy issues requiring assessment against the Development Plan
policies. 
This application was initially registered in April 2024.  Its determination has been delayed by
subsequent site meetings and discussions between JTC, Arran Aggregates and Planning
Officers.  Arran Aggregates (AA) finally confirmed in February 2025 that they have sufficient
bonds in place for the three existing quarries which they now operate on Arran (Sannox,
Bogary and Derenenach) and are currently updating the existing agreements with the
landowner, Arran Estates in this regard. 
AA confirmed their ongoing work with regard to agreeing an appropriate revised bond
amount with the Council for the previously approved westward expansion of Sannox
Quarry, which details are to be addressed as part of their first four yearly report on
operations required by the conditions of 20/00710/PP.

Page 4

The amount indicated in planning permission 20/00710/PP was £50,000 but Arran
Aggregates are of the opinion that the actual restoration, if required, could be achieved for a
lower amount, which would require to be agreed prior to commencement of the extension of
the quarry, as per the planning condition. 
Relevant Planning History 
97/00653/PP for Continuation and extension of operations for the winning and working of
minerals Approved subject to Conditions on 27.04.1999. 
04/00353/PP for Continuation of sand extraction from existing quarry (modification of
condition no 2 on previous consent - N/01/97/0207) Approved subject to Conditions on
17.05.2005 
10/00212/PP for Modification of condition 2 on planning approval N/04/00353/PP to allow
continuation of sand extraction for existing quarry for a further 10 years Approved subject to
Conditions on 05.04.2012. 
20/00710/PP for Continuation and extension of existing quarry for extraction of sand and
gravel Approved subject to Conditions on 25.02.2021. 
Relevant Development Plan Policies 
The LDP can be viewed at the link below. 
LDP November 2019 
NPF4 can be viewed at the link below 
National Planning Framework 4 
2. Consultations and Representations 
There is no requirement for neighbour notification nor other forms of publicity for this
category of application. No consultations were carried out. 
The landowner Sannox Estates was notified of the application as an original signatory of the
Agreement but has not responded or submitted comments. 
Publicity:- Not Advertised   
Site Notices:-  No Site Notice 
3. Analysis 
As already covered above, this application does not propose any alterations to the
previously approved working methods or site boundaries.  The quarry operation would

Page 5

therefore continue to accord with the Development Plan, as assessed and confirmed in
20/00710/PP. 
The determining considerations in the application are therefore only: 
(i) whether the clauses of the previously agreed Section 75 agreement have been
satisfactorily discharged meaning it could therefore be discharged; 
and  
(ii) whether sufficient financial arrangements remain in place on behalf of the new
operators for restoration of the quarry site by the Council should operations ever cease and
such responsibilities then fall to the Council , meaning that the previously lodged monies
can be returned to the applicant. 
The updated and varied Agreement signed in 2012 concerned the remaining matters not
already discharged by that point from the Section 75 Agreement signed by the Council,
landowner and John Thomson Construction on 19th May 1999. 
Variation (1) of the updated 2012 agreement was: "That, the Second Party (JTC) shall, prior
to effecting further work on Phases 5, 6 and 7 (of the quarry):- 
(a) restore Phases 2, 3 and 4 by placing top soil and seed on Phases 2, 3 and 4 to the
same specification as provided by clauses (SECOND) (c) and (d) of the (1999) Section 75
Agreement, and   
(b) erect a fence on the southern boundary of Phase 4." 
A site inspection was carried out by the Planning Officer, accompanied by the Council's
advisor Alan Doak and Donald Murchie of the new operators Arran Aggregates on 16th July
2024 and it was found that the Phases 2, 3 and 4 (the areas shaded green on the
accompanying 20/00710 Site Plan (San 02 RevA) had been satisfactorily restored as
required by Variation 1(a) of the updated 2012 Agreement. 
It was found that the boundary fence required by Variation 1(b) had not yet been installed
and that matter was brought to the attention of the applicants, JTC, who subsequently
advised that the fence had been installed as required. 
A further unaccompanied site visit by the Planning Officer on 4th October 2024 confirmed
that the fence had been installed. 
CONCLUSIONS 
The operational requirements detailed in the Section 75 Agreement have therefore been
fulfilled.  The ongoing operation and future expansion of the quarry is subject to the
conditions of 20/00710/PP and so remains under Planning control.  The existing Section 75

Page 6

Agreement has therefore served its purpose and there are no material planning reasons
remaining for its retention. 
Written confirmation has been received from the new operators Arran Aggregates that
sufficient financial arrangements are in place to cover the amount of the existing restoration
bond which was lodged with the Council in 2012, if responsibility for restoration of the quarry
ever passed to the Council for any reason.  The deposited £10,000 funds can therefore be
returned to the applicant, John Thomson Construction. 
The new operators (or their successors) are to submit details of sufficient available
restoration finances as part of the ongoing reviews and audits of ongoing operations and
future expansion of the site as required by conditions 1 and 2 of planning permission
20/00710/PP.  The ongoing restoration requirements of the quarry site therefore remain
within planning control should that requirement ever fall to the Council for any reason. 
RECOMMENDATION 
On that basis, it is recommended that committee approve the discharge of the Section 75
legal agreement and the refund of the lodged £10,000 bond to the applicant, who is no
longer involved in the operation or any required future restoration of Sannox Quarry. 
The applicant would then be advised to contact Legal Services to make the necessary legal
arrangements. 
4. Full Recommendation 
Approved with no Conditions 
Allan Finlayson 
Chief Planning Officer           
For further information please contact Mr Neil McAteer Planning Officer on 01294 324316.

Page 7

Appendix 1 – Location Plan           
DO NOT SCALE Reproduced from the Ordnance Survey mapping with the permission of the Controller of His Majesty’s Stationery
Office © Crown Copyright.  Unauthorised reproduction infringes Crown copyright and may lead to prosecution or civil proceedings.
North Ayrshire Council Licence Number AC0000825715.