NORTH AYRSHIRE COUNCIL 
23 September 2026 
Planning Committee 
Title:    Development Plan Scheme 
Purpose:  To update Members on the preparation of the Council’s next
Local Development Plan (LDP3) and seek approval of a revised
Development Plan Scheme. 
Recommendation:  It is recommended that the Planning Committee adopts the
Development Plan Scheme. 
1. Executive Summary 
1.1 On 9 December 2025, the Local Development Plan Committee approved an Evidence
Report, the first stage in the preparation of North Ayrshire’s third Local Development
Plan (LDP3). A 'gate check' of the Evidence Report was undertaken by a Reporter
appointed by Scottish Ministers. On 1 July 2026, the Reporter gave notice of their
assessment that the Evidence Report is sufficient. This allows us to progress with the
preparation of LDP3. 
1.2 Following the gate check, a new Development Plan Scheme has been prepared in
accordance with planning legislation. A Development Plan Scheme is a document
setting out a planning authority's programme for preparing and reviewing its local
development plan (LDP). The Development Plan Scheme also includes a Participation
Strategy, setting out when, how and with whom consultation on the plan will take place. 
1.3 The proposed timetable outlined in the new Development Plan Scheme sets a target
date of May 2028 for the adoption of LDP3.   
2. Background 
2.1 North Ayrshire Council adopted the current Local Development Plan (LDP2) on 28
November 2019. The Plan has a vision, aligned with the North Ayrshire Community
Planning Partnership, that looks forward 20 years and plans for a 10-year period to
2029. The policies and proposals, including sites allocated for development, within
LDP2 – alongside the National Planning Framework (NPF4) – are the basis for
determining planning applications, with decisions made in accordance with the
development plan (LD2 and NPF4), unless material considerations indicate otherwise. 
2.2 As the planning authority we are required by Section 20B of the Town and Country
Planning (Scotland) Act 1997, as amended, to prepare a Development Plan Scheme
(DPS) annually. The Development Plan Scheme sets out the programme for preparing

Page 2

and reviewing the local development plan; what is likely to be involved at each stage
and when, how and with whom consultation on the plan will take place (a Participation
Statement). Our last Development Plan Scheme was approved by the Planning
Committee in November 2023. 
2.3 The Planning (Scotland) Act 2019 makes significant changes to the development
planning system and the way local development plans are to be prepared, which are
still in their infancy. The changes aim to make development plans more effective, with
greater community involvement and more focus on delivery. The new legislative
provisions and regulations relating to the development planning system came into
force in May 2023 with local development planning guidance, setting out the Scottish
Ministers’ expectations for implementing this new system, published at the same time.
The Scottish Government expects that every planning authority in Scotland will have a
new style LDP in place within around 5 years of the Regulations coming into force i.e.
by May 2028. 
2.4 The table below sets out the proposed timetable for preparing LDP3. The timetable
has been adjusted to reflect the additional time taken to pass the gate check stage.
The 2024 Development Plan Scheme envisaged publication of the Evidence Report
between January and March 2025 and a three-month gate check. It was published in
December 2025, with the gate check concluding after 5 months and one week. The
target date for adoption of LDP3 is now May 2028, in line with the Government’s
expectation. 
Key Stage
2024
Development Plan
Scheme
Revised Target Date
Publication of Proposed
Plan
October to December
2025
(Q3 2025/26)
July to September 2027
(Q2 2027/28)
Submission of Proposed
Plan to Scottish Ministers
April to June 2026
(Q1 2026/27)
October to December
2027
(Q3 2025/26)
Expected Adoption of
LDP3
January to March 2027
(Q4 2026/27)
April to June 2028
(Q1 2028/29) 
2.5 The Development Plan Scheme sets out the reasons for the changes to the timetable,
as required by the Regulations. As noted above, there was a delay in publishing the
Evidence Report and passing the gate check. Since the publication of the previous
DPS, the evidence reports of 10 planning authorities were found to be insufficient at
gate check. Additional time was taken in the preparation of our Evidence Report to
learn lessons from completed gate checks; engage with key agencies and the Scottish
Government Planning and Environmental Appeals Division (DPEA); adopt emerging
best practice and to refine the Evidence Report prior to publication. It is considered
this delay of nine months to our LDP programme was invaluable in ensuring the
Evidence Report was found to be sufficient. 
2.6 Work has commenced on the next stage in the process, to prepare the Proposed
Plan. The Proposed Plan must be approved by the full Council before it is published
for consultation. We expect to seek approval from the Local Development Planning
Committee to publish the Proposed Plan after next year’s local government elections.
The revised timetable provides for an extended period for preparing the Proposed

Page 3

Plan, from five months to 13 months. This is considered a more realistic target for
undertaking the required engagement and assessments required. 
2.7 The Development Plan Scheme also includes a Participation Statement setting out
when, how and with whom consultation on the plan will take place. The statement
reiterates our approach, followed throughout the preparation of LDP2, to encourage
everyone with an interest in North Ayrshire to get involved in the update of the Local
Development Plan. Our proposed approach to engagement on the Proposed Plan
(stage 4) consists of four distinct engagements: consultation on proposed
development sites, which will commence in September 2026; vision and priorities;
spatial strategies and on a background housing paper. 
2.8 We want to make it as easy as possible for everyone with an interest to engage in the
preparation of LDP3 and to ensure that underrepresented groups are involved; public
participation is inclusive and that wider public engagement directly feeds into the
development of the LDP. Responses to an Engagement Survey and the Draft DPS
have expressed support for a range of engagement methods and we will develop
detailed plans that consider the best approach, taking account of the resources
available and opportunities to align consultation activities with other workstreams to
reduce risks of consultation fatigue, at each stage.   
Next Steps 
2.9   If approved for adoption by Members, the Development Plan Scheme will be sent to
Scottish Ministers, published online and placed in all libraries in accordance with the
planning legislation. An update will be provided to all stakeholders.   
3. Proposals 
3.1 It is recommended that the Planning Committee adopts the Development Plan Scheme
attached to this report.

Page 4

4. Implications/Socio-economic Duty 
Financial 
4.1 The programme for preparing and reviewing North Ayrshire’s local development plan
(LDP) can be delivered within existing staff resources and budgetary provision. 
Human Resources 
4.2 As above. 
Legal 
4.3 The Development Plan Scheme has been prepared in accordance with the Planning
(Scotland) Act 2019, as amended, and The Town and Country Planning (Development
Planning) (Scotland) Regulations 2023.   
Equality/Socio-economic 
4.4 The preparation of a new Local Development Plan for North Ayrshire will be required to
be subject of an equalities impact assessment and assessment on the impact of the
plan on children. 
Climate Change and Carbon 
4.5 The preparation of a new Local Development Plan for North Ayrshire will be required to
be subject of a Strategic Environmental Assessment and Habitat Regulations Appraisal. 
Key Priorities 
4.6 LDP3 will align with wider national priorities, programmes and strategies, most directly
via National Planning Framework 4. This links with the Council’s key priorities of
wellbeing, communities and local democracy and climate change. The LDP is a key
mechanism for supporting Placemaking within North Ayrshire. 
Community Wealth Building 
4.7 There is significant scope within the plan making process to explore how the Local
Development Plan can support Community Wealth Building, for example around its
approach to land owned by ‘anchor’ organisations within the local economy. 
Islands Communities Impact Assessment (ICIA) 
4.8 The preparation of a new Local Development Plan for North Ayrshire will be required to
be subject of an Island Communities Impact Assessment. 
United Nations Rights of the Child (UNCRC) 
4.9 Legislation requires us to make appropriate arrangements to promote and facilitate
participation by children and young people in the preparation of the local development
plan. This will requirement will inform our detailed proposals for engagement.

Page 5

Consumer Duty 
4.10 None. 
5. Consultation 
5.1 A Participation Statement forms part of the Development Plan Scheme and outlines
how, when and with who we will engage with throughout the process of preparing the
next Local Development Plan, further detailed proposals to be developed. An
Engagement Survey and consultation on the Draft DPS will informed our approach,
which will evolve in response to guidance, best practice and further feedback. 
DAVID W. HAMMOND
Executive Director (Communities and Housing) 
For further information please contact Alistair Gemmell, Strategic Planning Manager, on
01294 324021. 
Background Papers
0

Page 6

Development Plan Scheme
September 2026

Page 7

2 
Introduction
The development plan for North Ayrshire comprises the adopted Local Development
Plan (LDP2) and National Planning Framework 4 (NPF4). North Ayrshire Council
adopted LDP2 on 28 November 2019. Scottish Ministers adopted NPF4 on 13
February 2023. 
This 2026 Development Plan Scheme sets out North Ayrshire Council’s latest
programme for reviewing LDP2 and preparing North Ayrshire’s third local
development plan, LDP3. It updates the previous Development Plan Scheme which
was adopted by the planning committee and published in November 2024.
We are preparing LDP3 under the provisions of the Town and Country Planning
(Scotland) Act 1997, as amended by the Planning (Scotland) Act 2019. The current
legislative provisions and regulations relating to the development planning system
came into force on 19 May 2023. Local development planning guidance, setting out
the Scottish Ministers’ expectations for implementing this new system, was also
published in May 2023. 
The local development planning guidance states that every planning authority in
Scotland should have a new style LDP in place within around five years of the
regulations coming into force, in other words by May 2028. The revised timetable
proposed envisages adoption of LDP3 by this date.
The 2019 Act, Town and Country Planning (Development Planning) (Scotland)
Regulations 2023 and guidance are at the centre of reforms to the Scottish planning
system, including to the way local development plans are prepared. They are aimed
at making LDPs more effective, more place-based with greater community
involvement in their preparation and more focus on delivery. This means putting
people and communities at the heart of a collaborative process to prepare LDP3 in a
way that meets people’s needs and aspirations and tackles inequalities. 
This Development Plan Scheme includes a Participation Statement which sets out
our intentions around ensuring engagement on LDP3 is early, collaborative,
meaningful and proportionate; including when consultation is likely to take place,
how and with whom. 
Any individual or organisation interested in the preparation of the development plan
for North Ayrshire, including the details of future consultation events, is encouraged
to sign up to our mailing list to receive updates direct to their mailbox.

Page 8

3 
Proposed Timetable
The proposed timetable for preparing North Ayrshire’s third Local Development Plan
(LDP3) is set out below: 
Key Stage
2024
Development Plan
Scheme
Revised Target Date
Publication of Proposed
Plan
October to December
2025 July to September 2027
Submission of Proposed
Plan to Scottish Ministers April to June 2026 October to December
2027
Expected Adoption of LDP3 January to March 2027 April to June 2028 
The 2024 Development Plan Scheme envisaged publication of the Evidence Report
between January and March 2025. It was published in December 2025. 
A key reason for the delay in publishing the Evidence Report was the desire to
ensure it passed the Gate Check first time. It was noted in the 2024 Development
Plan Scheme that the Evidence Report is a new stage in the preparation of a local
development plan, and the Regulations do not specify minimum evidence
requirements. This has created some uncertainty around what constitutes
‘sufficiency’ which is assessed at the Gate Check stage. 
The evidence reports of 10 planning authorities were found to be insufficient at Gate
Check over the course of 2025 and, accordingly, the delay of nine months to our
LDP programme was invaluable in ensuring that it was found to be sufficient. The
additional time enabled discussions with other planning authorities and key
agencies; to learn lessons from completed Gate Checks; to adopt emerging best
practice and to refine the Evidence Report prior to publication. 
The delay in submission of the Evidence Report and its progress through the Gate
Check stage have had a knock-on effect on the indicative timetable for preparing
LDP3. We now anticipate publishing the Proposed Plan in August 2027 and adoption
in May 2028. 
These revised dates are a consequence of the additional time required to pass the
Gate Check and provide for an extended period for preparing the Proposed Plan,
from five months to 13 months. This is considered a more realistic target for
undertaking the required engagement and assessments required to prepare the
Proposed Plan.

Page 9

4 
Key Stages
The following section of the Development Plan Scheme details what is involved in
each stage of preparation of North Ayrshire’s third Local Development Plan. 
Early Engagement & Data Collection 
 Complete
In late 2022, the Planning Service commenced early engagement, including with
other Council services, Elected Members, key agencies and community councils in
advance of commencing work on North Ayrshire’s third Local Development Plan. 
In March 2023 we launched an online hub to support the preparation of LDP3,
including the launch of the ‘Your Place’ survey, based on the Place Standard. 
Scoping was undertaken to consider the matters to be addressed in the Evidence
Report; the relevant baseline information needed for each issue; the need for
primary data collection; the stakeholders to be involved in collating and reviewing
data and a timetable for this work. A programme of data collection was undertaken
with several audits and studies also completed to inform the Evidence Report. 
To support the preparation of the Evidence Report, Place Profiles for all six localities
in North Ayrshire were published in October 2024. These set out key baseline
information and data, summarise early engagement to date and reflect on the
outcomes of other community engagement initiatives such as Charrettes, Local
Place Frameworks, Local Place Plans and Island Plans. 
Evidence Report 
 Complete
The purpose of the Evidence Report is to support the quality and effectiveness of the
LDP. A robust evidence base will inform the process of plan making, justify the
content of the plan and provide a baseline for future monitoring
To support the preparation of the Evidence Report, in addition to the Place Profiles,
we prepared topic papers on housing, transport and the environment. These papers
formed the basis of our engagement with key agencies and the corresponding
Evidence Report sections. The housing and environment papers were also published
in March 2025 for wider stakeholder comment. 
The final Evidence Report was approved by the Local Development Plan Committee
on 9 December 2025. Supporting documents include a Record of Engagement which
sets out a detailed account of the engagement carried out in the preparation of the
report.
Gate Check 
 Complete
The Evidence Report was submitted to Scottish Ministers on 20 January 2026.
Scottish Ministers appointed a Reporter on 24 February 2026 to carry out a 'Gate

Page 10

5 
Check' of the Evidence Report to assess whether it contains sufficient information to
enable the planning authority to prepare a Local Development Plan.
On 1 July 2026, the Reporter gave notice of their assessment that the Evidence
Report contains sufficient information to enable the planning authority to prepare a
Local Development Plan. The Reporter’s assessment and decision can be viewed at
the case page on the Scottish Government’s Planning and Environmental Appeals
(DPEA) online portal.
Call for Ideas 
 Complete
Acknowledging the delay to the publication of the Evidence Report, we went ahead
with a ‘Call for Ideas’ during 2025, having initially intended to undertake this after the
Gate Check. In April 2025, individuals, community bodies, organisations, landowners
and developers were invited to submit their ideas for what should be included in
North Ayrshire's third Local Development Plan, LDP3. Ideas relating to any aspect of
the new local development plan, not limited specifically to suggestions for
development sites or types of development, for example housing, were sought. 
The deadline for the submission of ideas was Monday 30 June 2025 however late
submissions have also been accepted. Around 110 ideas have been submitted to
date, with 100 of these relating to the development or use of land.
Proposed Plan
 In progress
Following successful completion of the Gate Check, we are now preparing the
Proposed Plan. 
The Proposed Plan will be our settled view on the policies and proposals that will
make up LDP3, including where new development should take place and where it
should not. In preparing the Proposed Plan, we will consider the Evidence Report;
submissions made at the Call for Ideas stage; registered Local Place Plans and any
other place-based community-led plans; and undertake further engagement with
stakeholders to test proposals to be included within the Plan. 
The Proposed Plan requires the approval of the full Council. Once Council has had
the opportunity to consider and approves the Proposed Plan, it will be published to
allow any representations from stakeholders, including the general public, which
seek to make changes to the plan, for a period of at least 12 weeks. 
Following the close of the period for representations on the Proposed Plan, we may
make modifications to the plan to take account of representations, consultation
responses or correct minor drafting and technical matters. A Modification Report, if
necessary, will set out any modifications made and explain the reasons for making
them and for not making changes where matters have been raised in significant
numbers.

Page 11

6 
We will then republish the Proposed Plan and submit it to Scottish Ministers, who will
examine any unresolved representations via an Examination. 
We will aim to publish the Proposed Plan for consultation by August 2027 and
submit to Scottish Ministers in December 2027.
Examination 
The examination is the opportunity for independent consideration of any issues
raised during the formal consultation on the Proposed Plan that have not been
resolved through modifications. Scottish Ministers will appoint a person, known as a
Reporter, to examine the Proposed Plan, starting with whether the consultation and
involvement of the public in the preparation of the plan meets or exceeds the
requirements of the Participation Statement.
The scope of the examination is limited only to issues raised in unresolved
representations. These issues will be set out in the summary of issues prepared by
the planning authority and it is the Reporter who will determine the form the
Examination will take. Only where the Reporter feels they do not have all the
information they need to make a proper assessment of an issue will they request
further information from any person.
The Reporter will provide conclusions and recommendations for each of the
unresolved issues identified at the start of the Examination process. 
Adoption 
Following receipt of the examination report from the Reporter – and subject to the
recommendations of the Reporter on the unresolved representations – we will
progress to adopt LDP3, further modified as required. 
As with the Gate Check, it is difficult to be certain how long the examination of the
Proposed Plan will take. This will be determined by the number of issues being
examined, the requirement for further information to be submitted; the need for any
hearing sessions; resources available to DPEA, among other factors. Our
programme allows for five months for the examination and adoption of the plan. 
Notwithstanding the potential for the examination to take longer, we anticipate
adopting LDP3 on or before May 2028. 
Monitoring & Delivery
Whilst the adoption of a plan is a significant milestone, it is not the end point.
Monitoring will form a feedback loop, providing data that will be needed for the
evidence gathering for amendment of the plan, or the next LDP and – in line with the
aspiration to achieve a delivery focussed system – focus will turn to facilitating
development that supports the spatial strategy, in particular developments that are
proposals of the plan. 
A key component of this is the Delivery Programme, which we are required to adopt
and publish a within three months of the LDP being constituted. A draft Delivery
Programme will be published alongside the Proposed Plan in August 2027.

Page 12

7 
Participation Statement
The Participation Statement forms an important part of the Development Plan
Scheme and sets out when consultation is likely to take place, with whom and its
likely form, including the steps to be taken to involve the public in the preparation of
the local development plan. 
To inform this Participation Statement we published an Engagement Survey seeking
views on how we should publicise LDP3 and its engagement opportunities; how
people would like to be involved in LDP3 and how we could reach more people to
involve them in the local development plan process. Comment were also sought on a
draft of this Development Plan Scheme. 
Throughout the preparation of LDP3 we will develop and tailor our approach to
engagement and seek to ensure it is effective and update our Participation
Statement as part of the Development Plan Scheme. 
When engagement will take place: 
We will engage and consult with stakeholders throughout the preparation of LDP3. In
line with our proposed timetable and the key stages, there are five distinct
opportunities for engagement, three of which are complete (early engagement; Place
Profiles and Evidence Report; and Call for Ideas). The Record of Engagement sets
out a detailed account of the engagement carried out in the preparation of the
Evidence Report. The following two stages remain: 
4) Proposed Plan engagement 
We will engage with all stakeholders to seek their views on proposals, including
those submitted at the ‘Call for Ideas’ stage, to inform the preparation of the
Proposed Plan. Four distinct engagements are proposed:
a) Development sites – September to October 2026
We will seek the views of local communities on the sites submitted via the Call
for Ideas, and other sites identified as potentially suitable for development and
allocation within LDP3. This consultation will inform our site assessments. It is
envisaged this will primarily be undertaken using our online engagement hub,
with in-person or video call appointments also offered to any individual or
group seeking further information or assistance to submit comments. 
b) Vision and Priorities – October to December 2026
LDP3 will share its vision and priorities with the North Ayrshire Local
Outcomes Improvement Plan (LOIP). The current Local Outcomes
Improvement Plan is reaching its halfway point in 2027. To ensure it remains
reflective of the needs and aspirations of our communities, especially in the
context of improving long term outcomes and tackling inequalities, a range of
engagement methods are anticipated to be employed, with a particular focus
on seeking the views of a wide range of groups. 
c) Spatial strategies – January to June 2027

Page 13

8 
Taking account of the site assessment process and agreed vision and
priorities, we will engage with all stakeholders on the development of spatial
strategies for North Ayrshire’s localities and settlements, prior to their
inclusion within the Proposed Plan. These spatial strategies will set out how
we anticipate places in North Ayrshire evolving over the plan period, including
where development should and should not take place. 
d) Background Housing Paper – April to June 2027
Noting the publication of updated household projections in December 2025,
after the approval of the Evidence Report, and the Council’s intention to
prepare a new Housing Needs and Demand Assessment (HNDA), we will
compile a background housing paper to support the preparation of the
Proposed Plan. 
The paper will consider the implications of the up-to-date household
projections; HNDA outputs and other new evidence for the Local Housing
Land Requirement figure and the location and types of new housing to be
delivered by LDP3. We will work with relevant stakeholders, including Homes
for Scotland and housing developers, to prepare a joint statement detailing
areas of agreement and disagreement with the intention that is leads to a
shorter and more focussed discussion on housing at an Examination. 
5) Proposed Plan consultation – September to November 2027
After the Council has approved the Proposed Plan it will be published to allow any
representations from stakeholders, including the general public, which seek to make
changes to the plan for a period of at least 12 weeks.
Who engagement will take place with: 
We want to ensure that everyone – either as an individual or on behalf of a group,
organisation, body or company – with an interest in North Ayrshire as a place to live,
work or visit is involved in the preparation of LDP3. Identified stakeholders include: 
• North Ayrshire residents
• Elected Members, MPs & MSPs
• Children and young peoplec
• Community Bodies, including Community Councils
• Locality Planning Partnerships
• Other Community and Interest Groups, including the Third Sector
• Landowners and Developers
• Business and Industry
• Key Agencies (Nature Scot, SEPA, Scottish Water, Scottish Enterprise,
Historic Environment Scotland, SPT, Scottish Forestry, the Crofting
Commission, NHS Ayrshire & Arran, and Transport Scotland) 
• Infrastructure providers
• North Ayrshire Council Departments

Page 14

9 
How engagement will take place:
We want to make it as easy as possible for everyone with an interest to engage in
the preparation of LDP3. Responses to the Engagement Survey have expressed
support for: 
• In-person exhibitions: drop-in events at convenient times and in convenient
locations for communities
• Online exhibitions: material hosted online to provide information 
• Workshops: interactive session to facilitate community (both in-person and
online) 
• Online resources: using social media and an online hub to gather views and
enable the submission of comments. 
• Tailored resources: bespoke resources tailored to particular groups which
make it easier to participate. 
In the first instance, we welcome the opportunity to speak to both individuals and
groups to understand the method of engagement that works best for them. 
Finally, in accordance with Planning Circular 2/2021, we will consider opportunities
to use mediation as a means of exploring, resolving or reducing disagreement in the
preparation of LDP3. Mediation is one of a range of techniques sometimes labelled
as ‘alternative dispute resolution (ADR)’ which can include facilitation, conciliation
and arbitration as well as mediation. These techniques can be used to help to
resolve issues of dispute. 
Whether facilitated by an independent third-party or not, there may be scope to use
mediation to resolve differences and build support for proposals through discussion
and negotiation prior to the publication of the Proposed Plan. Mediation is a
voluntary process; no stakeholders in the process of preparing LDP3 will be required
to enter into mediation.

Page 15

10 
Local Place Plans
The Planning (Scotland) Act 2019 introduces a new right for communities to produce
Local Place Plans (LPPs). The aim of LPPs is to enhance engagement in
development planning by empowering communities to play a proactive role in
defining the future of their places by setting out their proposals for the use and
development of land. 
Secondary legislation to govern the implementation of LPPs came into force in
January 2022 and Planning circular 1/2022 provides further guidance on their
preparation.
On 19 May 2023, in accordance with Section 15A of the Town and Country Planning
(Scotland) Act 1997 as amended by the Planning (Scotland) Act 2019 we published
an invitation to community bodies in North Ayrshire to prepare a local place plan. 
Community bodies that intend to prepare a local place plan were encouraged to
submit a ‘notice of intention to prepare a local place plan’ by completing the notice of
intention online form. To date, six Local Place Plans have been registered and can
be viewed on the Local Place Plan Register.
We have supported and worked with community bodies developing Local Place
Plans to ensure they can be registered and maximise their potential to inform LDP3.
A Handbook setting out local guidance and the support available to local
communities to prepare local place plans was shared with bodies expressing their
intention to prepare a local place plan in April 2024.
To date, the following Local Place Plans have been registered. In preparing LDP3
must take account of these plans:
• West Kilbride, Seamill and Portencross
• Stevenston
• Largs
• Cumbrae
• Fairlie
• Garnock Valley
We have been flexible with the deadline for submitting Local Place Plans, reflecting
changes to the timetable for LDP3. Now we are at the stage of preparing the
Proposed Plan, the scope for newly registered Local Place Plan to shape the new
LDP is decreasing, however, we would still welcome discussions with any
community body interesting in preparing a Local Place Plan.

Page 16

11 
Impact Assessments
A number of different assessments must be undertaken to support the preparation of
LDP3. These assessments are an integral part of the plan making process and
should inform and be informed by the plan as it is prepared. They are:
• Equalities Impact Assessment;
• Public Sector Equality Duty Assessment;
• Fairer Scotland Duty Assessment;
• Island Communities Impact Assessment, 
• Strategic Environmental Assessment; and
• Habitats Regulations Appraisal
• Transport Assessment
Further detail on these assessments is included at Annex C of the Local
Development Planning Guidance. 
Preparation of the Evidence Report provided the opportunity to align with the
Scoping stage of the Strategic Environmental Assessment through the establishment
of the environmental baseline and engagement with the Consultation Authorities. In
this regard, the Environmental Evidence Paper published in April 2025 incorporates
Strategic Environmental Assessment (SEA) Scoping Report. 
All assessments will be published in draft alongside the Proposed Plan and revised
and updated as required.