NORTH AYRSHIRE COUNCIL 
15 May 2024 
North Ayrshire Council 
Title:    Seagate Castle 
Purpose:  To seek Council approval for an allocation of £263,420 from the
Irvine Common Good to carry-out stabilisation and conservation
works at Seagate Castle, Irvine. 
Recommendation:  That Council approves an allocation of £263,420 from the 
Irvine Common Good to carry-out stabilisation and conservation
works at Seagate Castle, Irvine. 
1. Executive Summary 
1.1 On 5th March 2020, Council approved the allocation of £250,000 from Irvine Common
Good to carry out essential stabilisation and conservation works at Seagate Castle.
Unfortunately the progression of these works was delayed as a result of the Covid
Pandemic. 
1.2 In the interim, design, investigation and preparatory works have been undertaken and
pre -consents have been approved for a revised project scope which includes the
following: 
• Full conservation works as detailed by Conservation architects.
• Structural protections and supporting works required to protect the structure’s
stability and integrity.
• Additional and new underground drainage works, imposed by Historic Environment
Scotland (HES) as a condition to Scheduled Monument Consent (SMC).
• A watching and monitoring role during these phases for the protection and
preservation of any archaeological aspects with the Scheduled area of the
monument. 
1.3 The Council must comply with HES requirements and Statutory obligations as
custodian of this listed, ancient monument. 
1.4 The total remaining project cost is now estimated to be £452,420 and further allocation
of £263,420 is therefore required from the Irvine Common Good. 
2. Background

Page 2

2.1 At Full Council on 5th March 2020, a request for £250,000 to the Irvine Common Good
was approved by Council for required stabilisation and conservation works at Seagate
Castle, Irvine.  This was immediately prior to the first Covid lockdown coming into
effect. 
2.2 At that time, Property Management and Investment had begun working with HES,
external conservation architects and conservation engineers with regards to the
condition and stability of Irvine’s Seagate Castle.
2.3 Their reports concluded that a number of urgent and essential works required to be
carried out to preserve fabric integrity, conserve specific features of importance to our
heritage and render the structure safe and stable.
2.4 These works were costed at a sum of approximately £250k and were anticipated then
to commence later in 2020, subject to full consent from HES.
2.5 The impact of the Covid-19 pandemic meant that the works did not progress as
planned and subsequently, reassessment of the project was required as a result. 
2.6 When it was possible, work recommenced and some elements have progressed,
which have included:
• Archaeological surveys, investigations and reports.
• Meetings and discussions with HES, including on site and investigative works.
• Controlled archaeological digs, topographical reports and soil percolation tests.
• Scheduled Monument Consent applications.
• Vegetation clearance and permitted tree removal.
• Design changes and amendments to suit HES and achieve consent.
• Phase 1 site construction works to immediately preserve Heraldic emblems forming
part of the structure’s detailing.
2.7 The scope of the works now required includes:
• Full conservation works to the structure, general fabric and features of the castle.
• Structural protection, supporting and stabilisation works required as a result of
Conservation Engineer’s reports and HES approvals.
• New underground drainage and storm water diversion works imposed by HES as a
condition of SMC.
• Full archaeological monitoring and reporting in line with HES guidance and
statutory aspects of undertaking such works on a Scheduled Monument.
2.8 An external design team remains in place, led by specialist Conservation Architects as
the lead consultant and project managers.  The relevant consents to undertake the
works have now been pre-approved and the Quantity Surveyor has costed the
updated design and specification at £452,420, which figure includes professional fees
for all remaining works to completion.
2.9 The total project costs, including professional fees, is therefore estimated to be
approximately £513,420.
2.10 This figure does allow for some contingency; however, the historic nature of the
building means the risk of uncovering additional essential works during the course of
the works is high.  Additionally, works will at all stages be scrutinised by HES and it is

Page 3

possible additional works or scope can be imposed by them to allow our continuance
of the project.  This still has the potential to impact the overall project cost and
programme.
2.11 The figures do allow for expected inflationary cost elements related to the further
delay required for formal SMC being granted by HES. 
2.12 The table below notes the value expended to date, the total overall cost and amount
required to completion: 
Seagate Castle Stabilisation and Conservation Works. Estimated Project Costs, April
2024
Total approved in March 2020 £250,000   
Total costs of work caried out to date,
including investigative works,
professional fees and consent
applications 
£61,000  
Estimate of work remaining to be
carried out 
£452,420  
Total cost of project   £513,420 
Total required to completion*     £263,420 
*NB. the risk of uncovering additional essential works during the course of the works is
high. 
2.13 The programme below follows the recommendations of the Project Manager to
commence the construction works phase in early Spring 2025, thereby avoiding
potential additional complication, delay and costs caused by undertaking such nature
of works during the later Autumn and Winter months.  Additionally, this avoids any
works ongoing and the erection of any scaffolding and localised restrictions to
pedestrians during the Marymass Festival in August 2024.
2.14 Should funding be approved; works will progress to tender stage and, due to the
specialist conservation nature of the scheme, this will be procured though the
appointed design team, commencing in June 2024 with formal application for SMC.
Currently estimated programme dates are given below: 
Seagate Castle Stabilisation and Conservation Works. Estimated Project Programme,
April 2024
Approval of funding request May 2024
SMC Application June 2024
SMC Approval September 2024
Tender issue October 2024
Tender return November 2024
Contractor Appointment December 2024
Site Start March 2025
Completion*  September 2025
*NB. the risk of uncovering additional essential works during the course of the works is
high.

Page 4

3. Proposals                                                                           
3.1 It is proposed that a further allocation of £263,420 is made from the 
Irvine Common Good to complete the required stabilisation and conservation works
and that these works are progressed immediately through the appointed external
design team.
4. Implications/Socio-economic Duty 
Financial 
4.1 Previous approval was given for the allocation of £250,000 from Irvine Common
Good. Works to the value of £61,000 have been carried out to date, leaving a
remaining approved allocation of £189,000. An additional £263,420 is required to
allow all required works to be carried out giving a total project cost of £513,420. The
current balance of funds available within Irvine Common Good is £921,756 which
would leave a remaining balance of £658,336 if Council agree to allocate this further
£263,420. 
Human Resources 
4.2 There are no human resources implications arising from the report. 
Legal 
4.3 The Council must comply with Historic Environment Scotland (HES) requirements and
Statutory Obligations as custodian of this listed, ancient monument. 
Seagate Castle is an Irvine Common Good Asset and Council approval is therefore
required. 
Equality/Socio-economic 
4.4 There are no equality implications of the proposal. 
Climate Change and Carbon 
4.5  There are no implications in relation to climate change and carbon. 
Key Priorities 
4.6 If approved, undertaking the works will support the Council’s key priorities of 
Wellbeing and Communities and Local Democracy through the following outcomes: 
• Places and public spaces across North Ayrshire are well maintained and
accessible.
• Our places encourage strong inclusive communities and respect the local
environment and cultural heritage. 
Community Wealth Building

Page 5

4.7 Seagate Castle plays an important community role in Irvine and the wider North
Ayrshire. It also attracts visitors and enthusiasts to the area, thereby increasing
opportunities for local businesses through greater footfall and local spend. 
5. Consultation 
5.1 Consultation has been undertaken with Finance and Legal Services in preparation of
this report. 
5.2 Full consultation and liaison has also taken place with HES and with appointed
archaeological specialists throughout all stages of the project to date, informing this
report. 
Russell McCutcheon
Executive Director (Place) 
For further information please contact Laurence Cree, Senior Manager, Property
Management and Investment , on 01294 324463. 
Background Papers
N/A