NORTH AYRSHIRE COUNCIL 
28 February 2024 
North Ayrshire Council 
Title:    Capital Investment Programme 2024/25 to 2033/34 
Purpose:  To advise Council on the draft Capital Investment Programme to
2033/34 
Recommendation:  That Council : 
(a)  approves the revised Capital Investment Programme to
2033/34 included in appendix 3;
(b)  notes that the programme will be reviewed on an on-going
basis with the next major review in 2026/27; and 
(c)  approves the refreshed Capital Investment Strategy included
in appendix 4. 
1. Executive Summary 
1.1 This report outlines the recommendations of the full review of the capital investment
programme which was undertaken during 2023/24. 
1.2 The review considered the current Capital Investment Programme and takes
cognisance of subsequent changes, including: 
• The ongoing impact of construction industry inflation, cost volatility and supply
chain issues across the overall Capital Investment Programme;
• Reductions in Scottish Government capital grants as detailed in the Local
Government Finance Settlement 2024/25;
• A review of spending profiles across key capital projects to support the Council’s
priorities; and  
• Revised levels of investment across projects, taking cognisance of Council
priorities, external funding sources and investing in core assets through asset
management plans. 
1.3 The review included an assessment of all funding sources over the 10 years of the
plan, including assumed levels of general capital grant, specific grants and a prudent
assessment of the level of capital receipts over the period. Total available funding has
been projected at £189.987m. The balance of funding required to deliver the capital
programme will be met through prudential borrowing and this is anticipated at
£216.472m. 
1.4 The proposed Capital Investment Programme, aligned to the Council Plan priorities, is
attached in Appendix 3 and will deliver a total programme of £406.459m to 2033/34.

Page 2

1.5 Compliance with Regulations and the Prudential Code requires assurance to be
provided on affordability and sustainability of the Capital Investment programme, this
is provided in the Treasury Management and Investment Strategy (TMIS) which
follows this report on the Council agenda. The TMIS recognises that this will require to
be kept under review to ensure the underlying assumptions continue to apply. 
1.6 The longer-term affordability of the current and future Capital Investment Programmes
requires incremental increases the current General Fund financing budgets. A review
of available General Fund financing budgets has been undertaken, with significant
increases in revenue support recommended, as part of the General Services Revenue
Estimates 2024/25 to 2026/27, to support the delivery of the draft Capital Investment
Programme. 
1.7 In addition to the TMIS, there is a requirement for the Council to publish a Capital
Investment Strategy (CIS). As part of the review of the Capital Investment
Programme, a review of the previous CIS has also been undertaken and a draft
revised CIS is attached at Appendix 4. 
1.8 The capital programme will continue to be reviewed on an on-going basis by Cabinet
with any additional funding brought forward for approval as appropriate. Major reviews
will be undertaken on a 3-year basis, with the next due to be completed during
2026/27. 
2. Background 
Capital Investment Programme 2024/25 to 2033/34 
2.1 North Ayrshire Council approved the current Capital Investment Programme for the
period 2023/24 to 2030/31 on 1 March 2023. A comprehensive review of the
Programme was undertaken during 2023/24. This report contains the outcome of that
review. 
Review of Capital Funding 
Scottish Government General Capital Grant 
2.2 Local Government Finance Circular 8/2023 confirmed the level of General Capital
Grant as £8.628m for 2024/25. This comprises a core General Capital element of
£9.068m, which is a reduction of (£0.939m) from that previously anticipated, less a
(£0.440m) reduction linked to the re-phasing of the Flooding Projects. In addition, the
Scottish Government has indicated that North Ayrshire will receive an allocation of
£0.100m during 2024/25 to support Coastal Change Adaptation. Projected at the core
level of £9.068m to 2033/34, the total General Capital Grant for the period is forecast
as £90.780m.

Page 3

Scottish Government Specific Capital Grants 
2.3 In addition to the General Capital Grant, the Council will receive two Specific Grants: 
• £0.963m to tackle Vacant and Derelict Land with projects requiring Scottish
Government approval; and
• £0.587m, to fund Cycling, Walking and Safer Streets (CWSS). 
The Vacant and Derelict Land funding is a reduction of (£0.543m) from that received
during 2023/24 and has only been confirmed for 2024/25. However, the CWSS
funding has been projected at current levels to 2033/34. 
2.4 A further Specific Grant allocation of £0.925m to support the Renewal of Play Parks
programme has been confirmed outwith the Local Government Finance Settlement for
the period 2024/25 to 2025/26. 
2.5 In addition, the programme includes previous Specific Grant allocations in relation to a
number of programmes which have been carried over into 2024/25 in line with revised
project plans, including: 
• £1.414m from the 2023/24 Vacant and Derelict Land allocation;
• £0.500m from the 2023/24 Islands Pit Stops; and
• £0.505m from the 2023/24 Place Based Investment Programme. 
2.6 As a result, the total forecast Specific Grant income to 2033/34 is £9.214m. 
Other Government Funding 
2.7 The programme includes funding from the Scottish and UK Governments to support
the Ayrshire Growth Deal. The total anticipated funding over the period is £57.265m.
This has been aligned to the latest programme planning information. 
2.8 The UK Government previously confirmed that North Ayrshire Council has been
awarded £23.693m from the Levelling Up Fund to support the upgrading of the B714
to improve connectivity between North Ayrshire and the wider motorway network.
£21.553m of this award is anticipated for receipt during financial years 2024/25 to
2025/26. 
2.9 During 2024-25 the UK Government confirmed total funding of £0.253m to support the
Digital SIP Great Harbour project. £0.128m of this is anticipated during 2024/25. 
Other Internal Funds 
2.10 The programme includes previously approved contributions from earmarked funds of
£3.299m to support the Solar PV project and £5.595m to support the B714 Upgrade.
However, these have been reduced by £4.000m to facilitate the transfer of the
General Capital Grant support for the 2023/24 pay settlement to Revenue.

Page 4

Capital Receipts 
2.11 A review of projected income from capital receipts has been undertaken during
2023/24. This is forecast to realise income of £4.143m over the period of the
programme in relation to the sale of other Council owned assets. 
Other External Funding 
2.12 In relation to additional grant funding from other external bodies, given the level of
uncertainty around securing these funds, only those funds which have been
confirmed, but not yet drawn down, have been included at this time. These include: 
Funding Source £m Project
NAVT 0.800 Marine Tourism
NAVT 0.110 Repurposing Property Grant Fund
NAVT 0.101 Irvine Enterprise Area
Sustrans 0.036 AGD Great Harbour 
£1.047m 
Prudential Borrowing 
2.13 The difference between the Council's Capital Investment Programme and funding from
the above sources is met through prudential borrowing of £216.472m. The Capital
Investment Programme will be delivered within the approved loan charges revenue
budget, utilising the balances held in the Prudential Investment Fund and Capital Fund
to smooth the revenue implications of the borrowing costs associated with the revised
programme. 
Development of the Capital Investment Programme to 2033/34 
2.14 The approach to developing the draft Capital Investment Programme to 2033/34
included: 
• A full review of the current programme to 2030/31;
• Identification of opportunities to reprioritise uncommitted projects;
• Review of the phasing of projects from a delivery and affordability perspective;
• Options appraisal of new requirements within the context of Council priorities;
• Consideration of lifecycle investment to protect core assets. 
2.15  The current capital investment programme to 2030/31, as approved by Council on 1
March 2023, has been updated to reflect the changes to the Programme approved by
Cabinet during 2023/24, including any re-phasing of programmes to reflect updated
project plans. 
Re-Profiling 
2.16 A total of £33.336m of planned expenditure has been re-profiled from 2023/24 into
2024/25 to 2033/34 in line with updated project delivery timelines. Full details of
individual projects re-phased from 2023/24 have been reported to Cabinet throughout
the year.

Page 5

2.17 In order to address the recommendations made within the Audit Scotland report on the
audit of the 2022/23 annual accounts, the phasing of expenditure within the draft
Capital Investment Programme has been reviewed to reflect historic expenditure
patterns and organisational capacity. This has resulted in the rephasing of
approximately 19% of the planned expenditure in both 2024/25 and 2025/26 for
delivery in later years, without impacting on the overall value of investment within the
programme. The actual levels of expenditure will be continually monitored and
reported to Cabinet throughout the life of the programme. 
Lifecycle Investment 
2.18 Informed by the asset management plans, an additional £31.542m has been included
in the Capital Investment Programme to ensure the Council continues to invest in its
core assets and infrastructure. Many of these programmes include recurring annual
investment which has been extended to include the period between the end of the
current Capital Programme and 2033/34.These include: 
• £11.400m for Roads investment to maintain a steady state road condition over the
next ten years;
• £6.000m for the Vehicle Renewal programme;
• £4.200m for Property Lifecycle Investment to enable high priority cyclical and
statutory investment to extend the life of the Council’s core assets, ensuring that
they remain fit for purpose and supporting delivery of core front line services;
• £3.612m for Schools ICT investment; 
• £3.000m for Street Lighting replacement reflecting the age and condition of the
lighting network;
• £1.680m for the Bridges infrastructure programme;
• £1.500m to support the Improvement Grants programme; and
• £0.150m for the Access Paths Network programme. 
Additional Investments linked to Revised Funding 
2.19 On 23 January 2024 Cabinet noted the provisional award of £37.4m for the Levelling
up for Ayrshire – Commercial and Low Carbon Infrastructure project under round 3 of
the UK Government’s Levelling Up Fund (LUF). The bid centred around commercial
estate development and associated low carbon infrastructure in Irvine and around
Prestwick airport. However, all funding is currently provisional pending completion of
the current validation and onboarding process. The Council requires to provide a
minimum of 10% match funding to support all LUF bids and a provision for £2.000m of
match funding has been included within the Capital Investment Programme. 
2.20 Local Government Finance Circular 8/2023 confirmed the level of Cycling, Walking
and Safer Streets specific grant for 2024/25 at £0.587m. Expenditure has been
projected at this level for the full period of the Capital Investment Programme,
resulting in additional investment of £1.768m to 2033/34. In addition, Vacant and
Derelict Land specific grant for 2024/25 has been confirmed at £0.963m and has been
reflected in additional investment at this level.

Page 6

Additional / Revised Investments 
2.21 In support of the Council’s Sustainable North Ayrshire Strategy 2024-27, an additional
investment of £5.430m in the decarbonisation of the Council’s fleet is included. This
investment will support the Council’s Fleet Decarbonisation Route Map through the
replacement of fossil fuelled vehicles with electric vehicles and more environmentally
sustainable fleet solutions. 
2.22 On 29 August 2023 Cabinet approved an additional investment of £5.000m to support
the B714 Upgrade project. As previously noted, the UK Government confirmed an
award of £23.693m from the Levelling Up Fund to support the upgrading of the B714
to improve connectivity between North Ayrshire and the wider motorway network. 
Following a review of the costs involved in the delivery of the project, together with
appropriate value engineering, it was determined that an additional investment of
£5.000m was required. The UK Government confirmed that no additional funding was
being made available to support this project and Cabinet approved the additional
investment, supported by funding from the Investment and Recovery & Renewal
Funds, additional allocations from anticipated capital receipts not currently committed
and the proposed utilisation of existing resources from within the existing programme. 
2.23 Following completion of the initial tender process for Ardrossan North Shore, an
additional investment of £3.914m is included to reflect the additional tender costs
through inflationary related cost volatility and the requirement to maintain an
appropriate level of contingency funding within the project. 
2.24 An additional investment of £2.500m has been included to support the anticipated
outcomes of the ongoing locality-based property review. This review is developing
options around how the Council best utilises its property assets within a Best Value
context, taking account of the needs of our communities, staff workstyles and climate
impact. This investment provision will remain under review as the programme of work
develops through 2024/25. 
2.25 On 7 November 2023 Cabinet approved changes to the Home Ownership Made Easy
(HOME) project with the site being transferred to the HRA for the provision of social
housing. This has resulted in the withdrawal of investment from the current General
Services Capital Investment Programme, including a (£1.033m) reduction in planned
expenditure for 2024/25. 
2.26 Recent years have witnessed periods of significant volatility across the construction
industry linked to the ongoing legacy impacts of the Covid-19 pandemic, the influence
of national economic developments and international externalities arising from global
conflicts and their impacts on costs and supply chains. These volatilities have
manifested locally through increased borrowing costs, inflationary pressures, limited
availability of contractors, supply chain issues and material shortages which are
impacting on tender returns and the cost of materials. Where the resultant cost
pressures have been quantified, additional expenditure requirements have been
identified in relation to specific projects. However, unquantified risks have also been
identified, or are anticipated, across a number of other projects, including the Upper
Garnock Flood Protection Scheme, Moorpark Primary School and Ardrossan Harbour
Landside works. In order to support the management of these and other emerging
risks, it is proposed that the £10.000m investment within the Flexibility budget over the
next five years is maintained.

Page 7

2.27 The current approved Capital Investment Programme to 2030/31 is attached at
appendix 1. Full details of the proposed changes to the programme following the
review, as outlined above, are included in appendix 2. The revised Capital Investment
Programme covering the period from 2024/25 to 2033/34 is included in appendix 3.
This will deliver a total programme of investment of £406.459m. 
Future Affordability 
2.28 The Prudential Investment Fund was created as part of the 2015/16 budget strategy to
utilise short term underspends on General Fund financing budgets to offset longer
term pressures to support Prudential Borrowing arising from the Capital Investment
Programme. 
2.29 Due to the significant investment planned by North Ayrshire Council over the period to
2033/34, set within the context of government grant forecasts and combined with the
additional cost pressures identified across a number of projects, it is projected that
these funds will be exhausted before the end of the current 10 year Capital Investment
Programme. In order to ensure the affordability of current and future capital
investments beyond this, it will be necessary to incrementally increase the current
General Fund financing budgets over the period of the programme. Additional funding
support to mitigate the significant cost increases and the increased cost of borrowing
includes the use of the recurring element of the Service Concession flexibility,
approved at Council on 15 February 2023, which resulted in an average contribution
of £3.437m from 2022/23 and the utilisation of the balance of savings from the
temporary reduction in the employers’ superannuation contributions during 2024/25
and 2025/26. 
2.30 In addition to the application of these non-recurring funds, it is necessary to include an
indicative recurring pressure within the General Services Revenue Estimates 2024/25
to 2026/27. This includes an incremental contribution of £0.250m per annum from
2024/25, increasing to £0.450m from 2025/26 and £0.500m per annum from 2026/27.
The impacts of inflationary pressures and interest rate fluctuations will continue to be
monitored on an ongoing basis and the resultant increases in revenue contributions
will be reviewed as part of the next major review of the capital programme, due to be
undertaken during 2026/27. 
Treasury Management and Investment Strategy (TMIS) 
2.31 Compliance with Regulation and the Prudential Code requires assurance to be
provided on affordability and sustainability of the Capital Investment Programme. This
is provided in the Treasury Management and Investment Strategy (TMIS) which
follows this report on the Council agenda. The TMIS recognises that this will require to
be kept under review to ensure the underlying assumptions continue to apply. 
Capital Investment Strategy 
2.32 In addition to the TMIS there is also a requirement for the Council to publish a Capital
Investment Strategy (CIS) which provides the overarching framework under which the
draft Capital Investment Programme has been developed. The current CIS was
approved by Council on 1 March 2023. During 2023/24 this has been refreshed with
the revised CIS included at Appendix 4.

Page 8

Conclusion 
2.32 The draft Capital Investment Programme 2024/25 to 2033/34, including proposed
funding, is attached at Appendix 3. This confirms total investment of £406.459m over
the period. The proposed investment aligns with the Council's key priorities, as set out
in the Council Plan 2023-2028, core asset management plans and the refreshed
Capital Investment Strategy, included at Appendix 4. 
2.33 The programme is affordable based on the estimated funding streams set out in the
2024/25 to 2026/27 Medium Term Financial Plan and from the mitigating actions
noted earlier in this report to supplement the Loans Fund. These proposals have been
developed within a very challenging financial landscape impacted by a combination of
significant cost volatility across the Programme and an increased cost of borrowing.
The affordability of the Programme is also highlighted within the Treasury
Management and Investment Strategy, reported elsewhere on the agenda, and this
will be monitored on an ongoing basis. A further, full assessment of the Programme’s
affordability will be undertaken as part of the next major review of the capital
programme due for completion during 2026/27. 
3. Proposals 
3.1 It is proposed that Council : 
(a)  approves the draft Capital Investment Programme 2024/25 to 2033/34 included in
appendix 3;
(b)  notes that the programme will be reviewed on an on-going basis with the next
major review in 2026/27; and 
(c)  approves the refreshed Capital Investment Strategy included in appendix 4. 
4. Implications/Socio-economic Duty 
Financial 
4.1 The revised capital programme is based on a number of assumptions around the
availability of finance including capital grant and capital receipts. Given the forward
projection for 10 years, it is essential that these and the cost of projects are kept
under review. 
There are a number of assumptions underpinning the current revenue projection
including; the level of loans fund support, the level of future interest rates, delivery of
the programme within the timelines outlined in the programme and application of the
Capital Fund and the Prudential Investment Fund to smooth the revenue implications
across the life of the plan. 
Due to the long-term nature of the borrowing required to support this programme, a
review of available financing budgets has been undertaken with a view to increasing
the available funding and maintaining the future affordability of the Programme.

Page 9

Human Resources 
4.2 Through investment in the Capital Investment Programme, it is anticipated there will
be additional staffing requirements. This will be considered on a project basis. 
Legal 
4.3 None. 
Equality/Socio-economic 
4.4 Where the Council is making decisions in relation to its spending priorities, it is obliged
to comply with the public sector equality duty set out in the Equalities Act 2010. To
meet this requirement, the Council assesses the impact of applying a decision against
key groups to ensure that certain groups are not disadvantaged by those decisions. A
number of the projects within the revised capital programme, will make a positive
contribution to the Council’s commitment to equalities. 
Environmental and Sustainability 
4.5 All projects within the revised plan will be delivered to minimise the impact on the
environment and maximise sustainability. Further, specific projects within the plan will
have a positive environmental impact. 
Key Priorities 
4.6 The refreshed Capital Investment Programme 2024/25 to 2033/34 supports the
delivery of the outcomes as outlined in the Council Plan 2023-2028 by focusing our
investment on priorities, managing risk and supporting the delivery of key priorities. 
Community Wealth Building 
4.7 The Council will aim to maximise opportunities within the context of the 5 pillars of
Community Wealth Building from its investment programme. In particular, Ayrshire
Growth Deal and growth and investment projects will make a positive contribution to
economic regeneration across the region. 
5. Consultation 
5.1 Executive Directors have been consulted as part of the review the current capital
investment programme and the identification of the proposed revisions and additions
to the programme detailed in this report.
Mark Boyd
Head of Service (Finance) 
For further information please contact David Forbes, Senior Manager (Strategic
Business Partner), on 01294 324551. 
Background Papers
Capital Investment Programme 2023/24 to 2030/31 – North Ayrshire Council 1 March 2023

Page 10

Appendix 1
Project Description
Revised
24/25
Revised
25/26
Revised
26/27
Revised
27/28
Revised
28/29
Revised
29/30
Revised
30/31 Total
£ £ £ £ £ £ £ £
EXPENDITURE
Place
Roads Improvement / Reconstruction 3,800,000 3,800,000 3,800,000 3,800,000 3,800,000 3,800,000 3,800,000 26,600,000
Lighting 1,000,000 1,000,000 1,000,000 1,000,000 1,000,000 1,000,000 1,000,000 7,000,000
Millport Coastal FPS 20,035,000       20,035,000
Millport Pier 349,920       349,920
Millburn FPS 1,109,982       1,109,982
Bridges infrastructure programme 954,564 560,000 560,000 560,000 560,000 560,000 460,000 4,214,564
B714 Improvements 8,000,000 16,351,443      24,351,443
Property lifecycle investment 1,000,000 1,000,000 1,000,000 1,100,000 1,000,000 1,000,000 1,000,000 7,100,000
HOME  1,033,021       1,033,021
Cemetery extns, walls & infra 300,000 268,162 23,042     591,204
Cmty, Kilbirnie - Works 200,000       200,000
Cmty, Ardrossan - Extension 300,000       300,000
Renewal of Play Parks 347,000 578,000      925,000
Vehicles 1,022,023 2,000,000 2,977,977 2,000,000 2,000,000 2,000,000 2,000,000 14,000,000
Montgomerie Park Masterplan 50,000 100,000 600,000 350,000 490,000 500,000 2,090,000
Cycling / Walker / Safer Streets 586,000 586,000 586,000 586,000 586,000 586,000 586,000 4,102,000
Access Paths Network Programme 50,000 50,000 50,000 50,000 50,000 50,000 50,000 350,000 
Growth & Investment
Ayrshire Growth Deal:       
AGD - i3 DPMC Phase 1 394,551       394,551
AGD - i3 DPMC Phase 2 400,000 2,000,000 2,150,030     4,550,030
AGD - i3 Flexible Business Space Phase 1 978,000 2,419,000 7,591,500 411,818    11,400,318
AGD - Hunterston - Centre for Low Carbon Energy & Circular Economy 335,000 335,000 4,196,000 4,196,000 4,196,000 4,195,881  17,453,881
AGD - Great Harbour 4,025,000 4,188,000 2,335,000 2,221,000 86,000 88,474  12,943,474
AGD - IMSE 250,000 273,740 3,200,000 3,250,000 3,250,000  10,223,740
AGD Marine Tourism - Ardrossan 512,000 4,500,000 1,689,621     6,701,621
AGD Marine Tourism - Arran 30,000 40,000 150,000 1,600,000 104,611   1,924,611
AGD Marine Tourism - Cumbrae 50,000 150,000 1,600,000 96,750    1,896,750
Ardrossan Harbour & Landside 1,793,701 1,793,702      3,587,403
Irvine Enterprise Area 103,079       103,079
Ardrossan North Shore 10,912,238 1,694,804      12,607,042
Sub Total 59,621,079 43,614,111 30,082,910 21,421,568 16,982,611 17,020,355 9,396,000 198,138,634
Communities
Montgomerie Park School 15,413,953       15,413,953
Universal Free School Meals Expansion 122,420 1,538,830 2,090,270 1,944,294 333,087 3,067,241  9,096,142
Schools ICT Investment 752,000 752,000 752,000 752,000 752,000 752,000 752,000 5,264,000
Ardrossan New Build 15,183,238 19,000,185 35,238,359 4,600,000    74,021,782
Sub Total 31,471,611 21,291,015 38,080,629 7,296,294 1,085,087 3,819,241 752,000 103,795,877
North Ayrshire Council
Approved Capital Programme 2024/25 - 2030/31 (Base)

Page 11

Appendix 1
Project Description
Revised
24/25
Revised
25/26
Revised
26/27
Revised
27/28
Revised
28/29
Revised
29/30
Revised
30/31 Total
£ £ £ £ £ £ £ £
North Ayrshire Council
Approved Capital Programme 2024/25 - 2030/31 (Base)
Chief Executive
ICT Investment Fund 382,400 376,600 702,600 297,600 282,600 282,600 297,600 2,622,000
WAN   500,000    500,000
LAN/WiFi   1,500,000    1,500,000
Telephony   650,000    650,000
Sub Total 382,400 376,600 702,600 2,947,600 282,600 282,600 297,600 5,272,000
Health & Social Care Partnership
Community Alarms - Analogue to Digital 333,000       333,000
Improvement grants 500,000 500,000 500,000 500,000 500,000 500,000 500,000 3,500,000
Sub Total 833,000 500,000 500,000 500,000 500,000 500,000 500,000 3,833,000
Other
Flexibility / Infrastructure Fund 7,000,000 100,000     7,100,000
Sub Total 7,000,000 100,000     7,100,000
TOTAL EXPENDITURE 92,308,090 72,781,726 69,466,139 32,165,462 18,850,298 21,622,196 10,945,600 318,139,511 
Revised
24/25
Revised
25/26
Revised
26/27
Revised
27/28
Revised
28/29
Revised
29/30
Revised
30/31 Total
£ £ £ £ £ £ £ £
INCOME
Prudential Borrowing 68,762,811 33,183,283 50,474,139 13,173,462 1,218,552 (7,035,058) 352,600 160,129,789
Specific Grants - AGD 4,839,000 8,399,000 8,399,000 8,399,000 7,038,746 18,064,254  55,139,000
Specific Grants - Cycling, Walking & Safer Streets 586,000 586,000 586,000 586,000 586,000 586,000 586,000 4,102,000
Specific Grants - B714 Improvements 5,630,000 16,351,443      21,981,443
Specific Grants - Renewal of Play Parks 347,000 578,000      925,000
General Capital Grant 10,007,000 10,007,000 10,007,000 10,007,000 10,007,000 10,007,000 10,007,000 70,049,000
Recovery & Renewal 1,235,180       1,235,180
Grants & Contributions 901,099       901,099
Sale of land & buildings 3,677,000      3,677,000
TOTAL INCOME 92,308,090 72,781,726 69,466,139 32,165,462 18,850,298 21,622,196 10,945,600 318,139,511

Page 12

Appendix 2
Project Description
Changes
24/25
Changes
25/26
Changes
26/27
Changes
27/28
Changes
28/29
Changes
29/30
Changes
30/31
Changes
31/32
Changes
32/33
Changes
33/34 Total
£ £ £ £ £ £ £ £ £ £ £
EXPENDITURE
Place
Roads Improvement / Reconstruction       3,800,000 3,800,000 3,800,000 11,400,000
Traffic Calming 82,953       82,953
Lighting  1,000,000 1,000,000 1,000,000 3,000,000
Upper Garnock FPS 467,828 467,828
Millport Pier (329,920) 154,960 134,960 (40,000)
Millburn FPS 343,547 343,547
Coastal Adaptations 99,727 99,727
Bridges infrastructure programme (100,000) 100,000 560,000 560,000 560,000 1,680,000
Largs Promenade Seawall 50,000 50,000 100,000
B714 Improvements (5,435,000) (1,574,749) 12,211,695 5,201,946
Property lifecycle investment 51,160 400,000 600,000 1,000,000 1,000,000 1,000,000 4,051,160
Locality Based Property Review 1,000,000 1,500,000 2,500,000
HOME  (1,033,021) (1,033,021)
Cemetery extns, walls & infra (229,285) (63,365) 122,560 11,521 (158,569)
Cmty, Kilbirnie - Works (200,000)      (200,000)
Cmty, Ardrossan - Extension 150,000 450,000      600,000
Cmty, Kilbirnie - Walls 36,071 36,072      72,143
Cmty, Beith - Walls 51,416 51,417      102,833
Cmty, Abbey Tower - Walls 44,469 44,469      88,938
Cmty, Stev Hawkhill - Walls 51,196 51,196  102,392
Cmty, West Kilbride - Walls 47,282 47,282  94,564
Cmty, Kilbirnie - New 288,916 288,917  577,833
Goldcraigs Refurbishment 608,438 132,562  741,000
Vehicles (2,023) 2,023  2,000,000 2,000,000 2,000,000 6,000,000
Fleet Decarbonisation 2,320,000 1,660,000 1,950,000 5,930,000
Shewalton landfill  48,949  48,949
Solar PV Investment -  Nethermains 260,720 260,721  521,441
Solar PV Investment -  Shewalton 1,825,377 1,825,377  3,650,754
Repurposing Property Grant Fund 250,000  250,000
Islands Pit Stops 500,000 500,000
Place Based Investment Programme 350,000  350,000
Digital - SIPP Great Harbour 127,882 127,882
PBIP 36 Bank Street 50,000  50,000
PBIP Galt House 25,000  25,000
Montgomerie Park Masterplan 137,500 112,500 (25,000) 50,000 275,000
VDLF - 2024/25 allocation 963,000 963,000
VDLF - Irvine Kyle Road Phase 2 1,087,018 1,087,018
VDLF - Development Work 119,012 119,012
VDLF - Tree Planting 47,600 47,600
VDLF Stalled Spaces Fund 100,000 100,000
Cycling / Walker / Safer Streets 1,000 1,000 1,000 1,000 1,000 1,000 1,000 587,000 587,000 587,000 1,768,000
Access Paths Network Programme 445,000 50,000 50,000 50,000 595,000  
North Ayrshire Council
Capital Programme 2024/25 - 2033/34 - Revisions

Page 13

Appendix 2
Project Description
Changes
24/25
Changes
25/26
Changes
26/27
Changes
27/28
Changes
28/29
Changes
29/30
Changes
30/31
Changes
31/32
Changes
32/33
Changes
33/34 Total
£ £ £ £ £ £ £ £ £ £ £
North Ayrshire Council
Capital Programme 2024/25 - 2033/34 - Revisions
Growth & Investment 
Ayrshire Growth Deal:       
AGD - i3 DPMC Phase 1 5,898 300,000 305,898
AGD - i3 DPMC Phase 2 (300,449) (1,750,000) (693,169) 2,908,275 164,657
AGD - i3 Flexible Business Space Phase 1 1,047,920 (2,419,000) (7,591,500) (411,818) (9,374,398)
AGD - i3 Flexible Business Space Phase 2 600,000 4,900,000 4,900,000 148,000 352,000 10,900,000
AGD - Hunterston - Centre for Low Carbon Energy & Circular Economy 333,892 (1) 333,891
AGD - Great Harbour (2,737,647) (1,881,436) 516,490 2,552,566 1,804,928 (31,909) 222,992
AGD - IMSE 445,000 (352,253) 92,747
AGD Marine Tourism - Ardrossan (512,000) (4,500,000) (1,689,621) 2,000,000 2,500,000 224,285 (1,977,336)
AGD Marine Tourism - Arran 10,482 (37,837) (27,355)
AGD Marine Tourism - Cumbrae 175,000 775,000 600,000 899,504 2,449,504
Ardrossan Harbour & Landside (914,222) (17,372) 896,851 (34,743)
Irvine Enterprise Area (51,540) 51,540 
Ardrossan North Shore 18,500,543 35,500  18,536,043
Sub Total 20,255,740 422,591 13,436,289 8,207,997 4,620,091 (158,878) 101,000 8,997,000 8,997,000 8,997,000 73,875,830
Communities
Montgomerie Park School (2,364,552) (2,364,552)
Universal Free School Meals Expansion 392,425 (327,021) (544,010) 1,136,848 (913) (137,500) 519,829
Schools ICT Investment 451,908 451,908 451,908 752,000 752,000 752,000 3,611,724
Ardrossan New Build (8,080,621) 1,371,270 (4,559,147) 17,410,374  6,141,876
Sub Total (9,600,840) 1,496,157 (4,651,249) 18,547,222 (913) (137,500) 752,000 752,000 752,000 7,908,877
Chief Executive
ICT Investment Fund (158,700) 52,900 (145,500) 351,300    100,000
Telephony 115,000 115,000      230,000
Sub Total (43,700) 167,900 (145,500) 351,300       330,000
Health & Social Care Partnership
Community Alarms - Analogue to Digital (264,024) 68,977      (195,047)
Improvement grants  500,000 500,000 500,000 1,500,000
Sub Total (264,024) 68,977      500,000 500,000 500,000 1,304,953
Other
Flexibility / Infrastructure Fund (7,000,000) 3,223,000 3,521,036 3,155,964 2,900,000
Core Infrastructure, property and Vehicles Renewal Investment 2,000,000  2,000,000
Sub Total 2,000,000 (7,000,000) 3,223,000 3,521,036 3,155,964      4,900,000
TOTAL EXPENDITURE 12,347,176 (4,844,375) 11,862,540 30,627,555 7,775,142 (296,378) 101,000 10,249,000 10,249,000 10,249,000 88,319,660

Page 14

Appendix 2
Project Description
Changes
24/25
Changes
25/26
Changes
26/27
Changes
27/28
Changes
28/29
Changes
29/30
Changes
30/31
Changes
31/32
Changes
32/33
Changes
33/34 Total
£ £ £ £ £ £ £ £ £ £ £
North Ayrshire Council
Capital Programme 2024/25 - 2033/34 - Revisions
Changes
24/25
Changes
25/26
Changes
26/27
Changes
27/28
Changes
28/29
Changes
29/30
Changes
30/31
Changes
31/32
Changes
32/33
Changes
33/34 Total
£ £ £ £ £ £ £ £ £ £ £
INCOME
Prudential Borrowing 9,537,439 (3,597,408) 5,359,081 22,110,062 7,534,232 12,703,178 914,000 594,000 594,000 594,000 56,342,584
Specific Grants - AGD (1,435,109) (1,743,415) 6,731,279 9,455,493 1,178,910 (12,061,556) 2,125,602
Specific Grants - Cycling, Walking & Safer Streets 1,000 1,000 1,000 1,000 1,000 1,000 1,000 587,000 587,000 587,000 1,768,000
Specific Grants - Vacant & Derelict Funding 2,376,630 2,376,630
Specific Grants - Islands Pit Stop 500,000 500,000
Specific Grants - Place Based Investment Programme 505,000 505,000
Specific Grants - B714 Improvements (428,054) (428,054)
Specific Grants - Digital - SIPP Great Harbour 127,882 127,882
General Capital Grant - Flooding (440,000) 440,000 
General Capital Grant (839,273) (939,000) (939,000) (939,000) (939,000) (939,000) (939,000) 9,068,000 9,068,000 9,068,000 20,730,727
Capital Fund 885,000 885,000
Recovery & Renewal 1,359,673 703,707 710,180 2,773,560
Grants & Contributions 96,988 49,560 146,548
Sale of land & buildings 100,000 241,181 125,000 466,181
TOTAL INCOME 12,347,176 (4,844,375) 11,862,540 30,627,555 7,775,142 (296,378) 101,000 10,249,000 10,249,000 10,249,000 88,319,660

Page 15

Appendix 3
Project Description
Revised
24/25
Revised
25/26
Revised
26/27
Revised
27/28
Revised
28/29
Revised
29/30
Revised
30/31
Revised
31/32
Revised
32/33
Revised
33/34 Total
£ £ £ £ £ £ £ £ £ £ £
EXPENDITURE
Place
Roads Improvement / Reconstruction 3,800,000 3,800,000 3,800,000 3,800,000 3,800,000 3,800,000 3,800,000 3,800,000 3,800,000 3,800,000 38,000,000
Traffic Calming 82,953          82,953
Lighting 1,000,000 1,000,000 1,000,000 1,000,000 1,000,000 1,000,000 1,000,000 1,000,000 1,000,000 1,000,000 10,000,000
Upper Garnock FPS 467,828          467,828
Millport Coastal FPS 20,035,000          20,035,000
Millport Pier 20,000 154,960 134,960        309,920
Millburn FPS 1,453,529          1,453,529
Coastal Adaptations 99,727          99,727
Bridges infrastructure programme 854,564 560,000 560,000 560,000 560,000 560,000 560,000 560,000 560,000 560,000 5,894,564
Largs Promenade Seawall 50,000 50,000         100,000
B714 Improvements 2,565,000 14,776,694 12,211,695        29,553,389
Property lifecycle investment 1,051,160 1,400,000 1,600,000 1,100,000 1,000,000 1,000,000 1,000,000 1,000,000 1,000,000 1,000,000 11,151,160
Locality Based Property Review 1,000,000 1,500,000        2,500,000
Cemetery extns, walls & infra 70,715 204,797 145,602 11,521       432,635
Cmty, Ardrossan - Extension 450,000 450,000         900,000
Cmty, Kilbirnie - Walls 36,071 36,072         72,143
Cmty, Beith - Walls 51,416 51,417         102,833
Cmty, Abbey Tower - Walls 44,469 44,469         88,938
Cmty, Stev Hawkhill - Walls 51,196 51,196         102,392
Cmty, West Kilbride - Walls 47,282 47,282         94,564
Cmty, Kilbirnie - New 288,916 288,917         577,833
Goldcraigs Refurbishment 608,438 132,562         741,000
Renewal of Play Parks 347,000 578,000         925,000
Vehicles 1,020,000 2,000,000 2,980,000 2,000,000 2,000,000 2,000,000 2,000,000 2,000,000 2,000,000 2,000,000 20,000,000
Fleet Decarbonisation 2,320,000 1,660,000 1,950,000        5,930,000
Shewalton landfill    48,949       48,949
Solar PV Investment -  Nethermains 260,720 260,721         521,441
Solar PV Investment -  Shewalton 1,825,377 1,825,377         3,650,754
Repurposing Property Grant Fund 250,000          250,000
Islands Pit Stops 500,000          500,000
Place Based Investment Programme 350,000          350,000
Digital - SIPP Great Harbour 127,882          127,882
PBIP 36 Bank Street 50,000          50,000
PBIP Galt House 25,000          25,000
Montgomerie Park Masterplan 137,500 162,500 75,000 650,000 350,000 490,000 500,000    2,365,000
VDLF - 2024/25 allocation 963,000          963,000
VDLF - Irvine Kyle Road Phase 2 1,087,018          1,087,018
VDLF - Development Work 119,012          119,012
VDLF - Tree Planting 47,600          47,600
VDLF Stalled Spaces Fund 100,000          100,000
Cycling / Walker / Safer Streets 587,000 587,000 587,000 587,000 587,000 587,000 587,000 587,000 587,000 587,000 5,870,000
Access Paths Network Programme 495,000 50,000 50,000 50,000 50,000 50,000 50,000 50,000 50,000 50,000 945,000    
North Ayrshire Council
Revised Capital Programme 2024/25 - 2033/34

Page 16

Appendix 3
Project Description
Revised
24/25
Revised
25/26
Revised
26/27
Revised
27/28
Revised
28/29
Revised
29/30
Revised
30/31
Revised
31/32
Revised
32/33
Revised
33/34 Total
£ £ £ £ £ £ £ £ £ £ £
North Ayrshire Council
Revised Capital Programme 2024/25 - 2033/34
Growth & Investment   
Ayrshire Growth Deal:          
AGD - i3 DPMC Phase 1 400,449 300,000         700,449
AGD - i3 DPMC Phase 2 99,551 250,000 1,456,861 2,908,275       4,714,687
AGD - i3 Flexible Business Space Phase 1 2,025,920          2,025,920
AGD - i3 Flexible Business Space Phase 2 600,000 4,900,000 4,900,000 148,000 352,000      10,900,000
AGD - Hunterston - Centre for Low Carbon Energy & Circular Economy 668,892 335,000 4,196,000 4,196,000 4,196,000 4,195,880     17,787,772
AGD - Great Harbour 1,287,353 2,306,564 2,851,490 4,773,566 1,890,928 56,565     13,166,466
AGD - IMSE 445,000 250,000 273,740 3,200,000 3,250,000 2,897,747     10,316,487
AGD Marine Tourism - Ardrossan   2,000,000 2,500,000 224,285     4,724,285
AGD Marine Tourism - Arran 40,482 40,000 150,000 1,600,000 66,774      1,897,256
AGD Marine Tourism - Cumbrae 225,000 925,000 2,200,000 996,254       4,346,254
Ardrossan Harbour & Landside 879,479 1,776,330 896,851        3,552,660
Irvine Enterprise Area 51,539 51,540         103,079
Ardrossan North Shore 29,412,781 1,730,304         31,143,085
Sub Total 79,876,819 44,036,702 43,519,199 29,629,565 21,602,702 16,861,477 9,497,000 8,997,000 8,997,000 8,997,000 272,014,464
Communities
Montgomerie Park School 13,049,401          13,049,401
Universal Free School Meals Expansion 514,845 1,211,809 1,546,260 3,081,142 332,174 2,929,741     9,615,971
Schools ICT Investment 1,203,908 1,203,908 1,203,908 752,000 752,000 752,000 752,000 752,000 752,000 752,000 8,875,724
Ardrossan New Build 7,102,617 20,371,455 30,679,212 22,010,374       80,163,658
Sub Total 21,870,771 22,787,172 33,429,380 25,843,516 1,084,174 3,681,741 752,000 752,000 752,000 752,000 111,704,754
Chief Executive
ICT Investment Fund 223,700 429,500 557,100 648,900 282,600 282,600 297,600    2,722,000
WAN   500,000       500,000
LAN/WiFi   1,500,000       1,500,000
Telephony 115,000 115,000  650,000       880,000
Sub Total 338,700 544,500 557,100 3,298,900 282,600 282,600 297,600    5,602,000
Health & Social Care Partnership
Community Alarms - Analogue to Digital 68,976 68,977         137,953
Improvement grants 500,000 500,000 500,000 500,000 500,000 500,000 500,000 500,000 500,000 500,000 5,000,000
Sub Total 568,976 568,977 500,000 500,000 500,000 500,000 500,000 500,000 500,000 500,000 5,137,953
Other
Flexibility / Infrastructure Fund  3,323,000 3,521,036 3,155,964      10,000,000
Core Infrastructure, property and Vehicles Renewal Investment 2,000,000          2,000,000
Sub Total 2,000,000  3,323,000 3,521,036 3,155,964      12,000,000
TOTAL EXPENDITURE 104,655,266 67,937,351 81,328,679 62,793,017 26,625,440 21,325,818 11,046,600 10,249,000 10,249,000 10,249,000 406,459,171

Page 17

Appendix 3
Project Description
Revised
24/25
Revised
25/26
Revised
26/27
Revised
27/28
Revised
28/29
Revised
29/30
Revised
30/31
Revised
31/32
Revised
32/33
Revised
33/34 Total
£ £ £ £ £ £ £ £ £ £ £
North Ayrshire Council
Revised Capital Programme 2024/25 - 2033/34
Revised
24/25
Revised
25/26
Revised
26/27
Revised
27/28
Revised
28/29
Revised
29/30
Revised
30/31
Revised
31/32
Revised
32/33
Revised
33/34 Total
£ £ £ £ £ £ £ £ £ £ £
INCOME
Prudential Borrowing 78,300,250 29,585,875 55,833,220 35,283,524 8,752,784 5,668,120 1,266,600 594,000 594,000 594,000 216,472,373
Specific Grants - AGD 3,403,891 6,655,585 15,130,279 17,854,493 8,217,656 6,002,698     57,264,602
Specific Grants - Cycling, Walking & Safer Streets 587,000 587,000 587,000 587,000 587,000 587,000 587,000 587,000 587,000 587,000 5,870,000
Specific Grants - Vacant & Derelict Funding 2,376,630          2,376,630
Specific Grants - Islands Pit Stop 500,000          500,000
Specific Grants - Place Based Investment Programme 505,000          505,000
Specific Grants - B714 Improvements 5,201,946 16,351,443         21,553,389
Specific Grants - Digital - SIPP Great Harbour 127,882          127,882
Specific Grants - Renewal of Play Parks 347,000 578,000         925,000
General Capital Grant - Flooding (440,000) 440,000         
General Capital Grant 9,167,727 9,068,000 9,068,000 9,068,000 9,068,000 9,068,000 9,068,000 9,068,000 9,068,000 9,068,000 90,779,727
Capital Fund 885,000          885,000
Recovery & Renewal 2,594,853 703,707 710,180        4,008,740
Grants & Contributions 998,087 49,560         1,047,647
Sale of land & buildings 100,000 3,918,181     125,000    4,143,181
TOTAL INCOME 104,655,266 67,937,351 81,328,679 62,793,017 26,625,440 21,325,818 11,046,600 10,249,000 10,249,000 10,249,000 406,459,171

Page 18

Appendix 4

Page 19

Introduction 
The Capital Investment Strategy for North Ayrshire Council provides an overview of
how capital expenditure plans, capital financing and treasury management activity
contribute to the infrastructure and provision of services for the benefit of North
Ayrshire communities and citizens. This refreshed strategy takes a long-term view
and covers the period from 2024 to 2034. This is aligned to the Capital Investment
Programme. 
The Capital Investment Strategy is a reporting requirement of the CIPFA Prudential
Code. Local authorities produce many plans and strategies in the course of their
operations. However, it is recognised that within the context of capital planning, there
is a need to produce an overarching view that addresses the following key
considerations: - 
• Ensuring that capital plans are aligned to the strategic priorities as set out in the
Council Plan. 
• Ensuring that capital plans are affordable, prudent and sustainable. 
• Demonstrating the linkage to local strategic planning and local asset
management planning. 
• Ensuring that financing decisions are taken in accordance with good
professional practice and a full understanding of the risks involved. 
• Demonstrating the Council has robust governance arrangements to support its
capital planning activities

Page 20

Background 
North Ayrshire Council has ambitious plans to deliver significant capital investment
over the planning period across housing, schools, economic development and
infrastructure. Working in partnership with East Ayrshire, South Ayrshire, the UK and
Scottish Government, the Ayrshire Growth deal will see the regeneration of the
region through investment in strategic infrastructure across various sectors, including
life sciences, tourism, manufacturing and aerospace. 
Throughout 2023/24 the wider construction industry has reported significant, ongoing
inflationary pressures linked to a number of factors, including additional costs as an
ongoing consequence of the Covid-19 pandemic; upward pressure on input costs
linked to international externalities such as ongoing global conflicts and its impact on
global supply chains; material and labour shortages; and increased demand linked to
reduced contractor availability. This has resulted in the identification of increased
cost risks in relation to a number of our investment priorities. 
The Capital Investment Strategy takes account of the Council’s strategic priorities
and considers any new investment within the context of outcomes, affordability or
invest to save. Decisions made over the course of the programme for capital and
treasury management will have financial consequences for the Council for many
years in the future. There is also recognition of the need to balance investment
between maintaining current assets and infrastructure against the ambitions for
acquiring new assets.  North Ayrshire Council’s Capital Investment Programme is
shaped and influenced by various associated strategies and plans.

Page 21

The primary purpose of the Capital Investment Strategy is to provide an overarching
view of how various plans and strategies inform capital investment and to
demonstrate that this is both affordable and sustainable. The associated plans and
strategies each focus on specific priority areas and, through appropriate governance
structures, ultimately shape and influence the investment plans delivered through the
Capital Investment Programme. Underpinning the Capital Investment Programme is
the Treasury Management and Investment Strategy and Loans Fund Policy. Both
ultimately consider the delivery of the capital programme within the context of
affordability and risk and apply a measurement of what this means against key
prudential and treasury indicators. The aim being to demonstrate affordability and
sustainability over the long term.

Page 22

Plans and Strategies 
Council Plan 2023-2028 
The mission for North Ayrshire Council is “Working together to improve the lives
of our people in North Ayrshire.”  To deliver on this mission 4 key strategic
priorities, outlined below, have been developed to direct plans now and into the
future. 
Through appropriate governance frameworks all capital investment must
demonstrate that it is aligned to the Council’s strategic themes, with particular focus
and priority given to capital investment opportunities that meet multiple strategic
priorities.

Page 23

Community Planning Partnerships and Local Outcomes Improvement Plan 
The North Ayrshire Community Planning Partnership is a partnership across a wide
range of organisations. The Local Outcomes Improvement Plan (LOIP) 2022 –
2030 provides a commitment by all partners to North Ayrshire communities and
citizens across three main priority areas: 
The Community Planning Partnership consists of 6 Locality Partnerships across
North Ayrshire. Key to the success of the LOIP is working in partnership with a
number of agencies to deliver better outcomes for citizens and communities. The
partnership includes Scottish Government, Police Scotland, NHS Ayrshire and Arran,
Skills Development Scotland, KA Leisure, Scottish Fire and Rescue and Scottish
Enterprise. Through the Local Development Plan, one of the strategic policies is to
deliver on local community priorities. Each Locality Partnership has agreed their own
local priorities. The following diagram illustrates the links between the locality
priorities and those in the LOIP:

Page 24

This framework of community engagement and structured partnership working is
vital when planning capital investment. More importantly, that local priorities are
considered as part of any strategic planning framework. 
Health and Social Care Partnership Strategic Commissioning Plan 2022-2030 
The North Ayrshire Health & Social Care Strategic Plan 2022-2030 was developed
through engagement and collaboration with local people, service users, members of
staff and other key stakeholders. It sets out our long-term ambitions for improving the
health and wellbeing of everyone who lives in North Ayrshire. 
The 2022-2030 plan continues the existing vision that “all people who live in North
Ayrshire are able to have a safe, healthy and active life” and to achieve this the
HSCP focuses on key priorities: 
WELLBEING
WORK
WORLD

Page 25

Asset Management Plans 
Asset Management Plans aim to ensure that the Council holds the right assets and
that they are fit for purpose in terms of condition, suitability and accessibility. The
plans also provide the vehicle for identifying future investment needs across all asset
classes. In line with the CIPFA “Guide to Asset Management and Capital Planning in
Local Authorities” North Ayrshire has classified its assets into six categories: 
The Council’s assets play a key role in the delivery of a wide range of essential
services to our local communities, contribute to regeneration and help drive
economic growth. The plans set out clear actions and include details of lifecycle
investment costs required to maintain assets and infrastructure to an appropriate
standard that supports service delivery. The plans are updated on an annual basis
and chief officers across all Directorates hold the responsibility for maintaining the
plans and reporting progress to the Council’s Cabinet on a bi-annual basis. 
A snapshot of the asset portfolio for North Ayrshire Council includes: 
Both capital and revenue financial resources across the General Fund and Housing
Revenue Account are used to maintain the current asset base. From a capital
perspective, planned investment which has been incorporated in the current Capital
Investment Programme includes:
Fleet and Plant •Around
570
Vehicles
and items
of Plant
Roads • Over
1,000 Km
of roads
Structures •Around
400
bridges
and
structures
Street Lighting •Over 23,000
street
lighting
columns
Operational Buildings • Over 70 
offices,
libraries and
community
centres
Council Houses
•Around
13,000
Council
Houses
Schools and Early Years
•63
Schools
and Early
Years
Facilities
Social Care •21 Social
Care
Facilities

Page 26

Local Housing Strategy 2023-28 and Strategic Housing Investment Plan 2024-
29 
The Local Housing Strategy sets out the Council’s ambition: ‘We want all our people
to live in the right homes, in great places, with access to any support services they
need.” 
The strategy mirrors the format of Scotland’s first 20 year housing strategy, Housing
to 2040 and sets out four overarching outcomes which align to the four key strategies
in Housing to 2040: 
•Planned investment of £112.8m to 2033/34 including improvements to the roads and
street lighting network, upgrading of the B714, flood prevention works at Upper
Garnock and Millport and bridges infrastructure improvement.
Roads,
Structures
and Lighting
•Procurement and maintenance of all Council fleet vehicles and plant ensuring the
fleet of 566 vehicles and heavy plant are maintained and operated in accordance with
the Council’s Operator’s licences and Road Transport legislation. Prioritisation of
emissions reductions through decarbonisation of vehicle fleet. Vehicle and plant
capital investment is planned at £25.9m to 2033/34.
Fleet,Plant
and
Equipment
•To ensure Council properties meet all legislative requirements and they are sustainable, energy
efficient and maintained to a high standard as well as ensuring the physical environment is able
to support mobile and flexible work programmes, Investment is planned at £18.6m to 2033/34.
It is also recognised that through the Estates Strategy further rationalisation and remodelling
will continue to be progressed on a locality by locality basis, with capital receipts incorporated
into the capital programme.
Property
•Underpinned by the Local Housing Strategy, the Strategic Housing Investment Plan
and the 30 Year HRA Business Plan, responsibility for maintenance of around 13,000
council houses, ensuring legislative compliance and meeting the needs of tenants. In
addition, delivery of an ambitious house building and improvement programme over
the period 2024/25-2028/29 will see capital investment by the Council total £352.0m.
Housing
•The Technology Strategy sets out how ICT supports service delivery and transformation.
Significant changes to our ICT infrastructure have been reflected in the ICT Asset
Management Plan. To deliver on the 6 key principles as outlined in the Technology
Strategy £5.6m investment to 2033/34 is planned.
ICT
•The service maintains 2,410 hectares of public open space, a Country Park, 14 local parks, 44
cemeteries and burial grounds, 37 war memorials & monuments, 366 hectares of woodlands, 3
allotments, 91 sports facilities and playing fields, 84 equipped play areas and 12 multi-use games
areas, residential greenspace, 38 water courses and open water features, 5 promenades and 16
beaches, three of which are Sites of Special Scientific Interest. The majority of investment is
delivered through the Place service revenue budget, however, specific capital investment of 
£2.4m is planned to 2033/34 for cemetery infrastructure.
Open
Spaces

Page 27

The Strategic Housing Investment Plan is an extension of, and aligns to, the Local
Housing Strategy, supporting the objectives of the Council Plan. 
The Strategic Housing Investment Plan also aligns with the Council’s Community
Wealth Building Strategy and supports the North Ayrshire Child Poverty Action Plan
2022-2023. Access to good quality and affordable housing is a key asset in
addressing child poverty, and poverty overall.   
The SHIP will secure investment in a total of 1,302 properties across North Ayrshire
and provide sustainable, affordable, accessible high-quality homes which will
contribute to the wider regeneration aims for the area. The Council projects in the
SHIP represent investment of £194.464m (including an estimated £78.07m Scottish
Government grant funding). Developments continue to be progressed across all six
localities: 
Public sector investment can have a transformational impact for communities, and
the Council explores site and area specific opportunities with partners to secure
maximum regeneration benefits. This supports the ambitions of the Council’s
Regeneration Delivery Plan to drive forward place-based development on strategic
regeneration sites, including town centres. Several SHIP projects completed to date
are within, or near, town centres. The plan supports major housing led regeneration
including the replacement of the 275 homes in the Fullarton tower blocks in Irvine and 
the provision of funding to assist the delivery of Housing’s Estate Based Regeneration
Programme. 
The Strategic Housing Investment Plan prioritises new social housing developments
which include the provision of outdoor green space, and which support the principles
of 20-minute neighbourhoods, where feasible. Developments are also planned
utilising ‘secure by design’ principles.   
The Council and its partners recognise that bringing former social housing stock into
ownership can assist with housing management and maintenance issues and
increase housing available through the North Ayrshire Housing Register. All
developing registered social landlord partners with stock in North Ayrshire now have
provision for buyback programmes in the SHIP.  
Housing to
2040
Strategy
Local
Housing
Strategy
Outcome
More homes at
the heart of
great places
Affordability and
choice
Affordable
warmth and
zero emission
homes
Improving the
quality of all
homes
Our places
support thriving
and inclusive
communities
Our people
have affordable
homes in the
place they
choose to live
Our homes are
energy efficient
and release less
emissions
Our homes are in
good condition
and people can
access any
support services
they need
Arran Garnock
Valley Irvine Kilwinning North
Coast
Three
Towns

Page 28

New housing has a key role to play in carbon reduction, climate change mitigation,
and in the alleviation of fuel poverty. The Council and its partners will continue to
consider innovative and sustainable approaches to heat and power, such as low
carbon heat, solar photovoltaic panels and smart technologies.  The Council
recognises that a ‘fabric first’ approach to sustainability can provide benefits to
tenants, in terms of reducing heating costs. This investment aligns to the Council’s
Environmental Sustainability and Climate Change Strategy in supporting affordable
warmth to households across North Ayrshire. Developments will also be designed to
promote sustainable travel. 
All amenity and sheltered housing in North Ayrshire should be built to an ambulant
housing standard as a minimum. To ensure need is met now and in the future, the
new Local Housing Strategy increased the target to ensure at least 10% of all tenure
new build stock is suitable for wheelchair users (increased from 7% in the previous
strategy). 
Officers within the Place Directorate and the Health and Social Care Partnership
developed a new supported accommodation housing model which has been
implemented at sites across North Ayrshire to maximise tenant independence 
The Local Housing Strategy recognises that the proportion of older people in North
Ayrshire is higher than that of Scotland as a whole. The SHIP estimates the delivery
of a further 311 amenity homes and 28 sheltered housing units. Alongside the new
build programme, the Council will continue to deliver its sheltered housing re-
provisioning programme, which includes £25m investment in the refurbishment of
sheltered housing units out with the SHIP. 
Regeneration Delivery Plan and Local Development Plan 
The Regeneration Delivery Plan sets out our priorities for delivering on the
regeneration ambitions of the Council Plan and Community Wealth Building strategy,
working in partnership with communities.  The Plan focuses on the delivery of
physical regeneration across North Ayrshire through an ambitious project-based
rolling action programme.  The Regeneration Delivery Plan focuses activity around
the four key regeneration themes: 
Mission
Enhancing local wealth and the creation of fair jobs and maximising the
potential of all our places through working in partnership with out communities
and businesses
Strengthening
Communities
Inclusive and
Green Economy Placemaking Enabling
Infrastructure

Page 29

The Local Development Plan was adopted in November 2019 and aligns to the
themes set out in the Regeneration Delivery Plan, it brings a targeted local context in
guiding development and investment in North Ayrshire over the next 20 years. The
focus is supporting and growing the business base across key sectors including
manufacturing, engineering, life sciences, tourism and hospitality and regenerating
towns and communities. The overarching aim of the plan is to deliver the Community
Planning Partnership vision of a “Better Life” to the citizens and communities of
North Ayrshire. The plan outlines the land use strategy that supports delivery of the
Local Outcomes Improvement Plan 2022 – 2030 and focuses on four key strategic
policies: 
The Spatial Strategy is an overarching policy for supporting the LOIP. This directs
development to towns and villages to support communities, the economy and
environment, while recognising the value that the countryside and coastal areas offer
both as natural resources worthy of protection and as an economic driver. An
example of directing investment to towns is evidenced by the Montgomerie Park
development with Council investment in road and service infrastructure to facilitate
large scale housing development and regeneration and using capital receipts from
land sale as a key source of funding. 
The Placemaking policy supports the LOIP by ensuring that all development
contributes to making quality places. This is measured by six qualities that define a
successful place: 
Distinctive
Welcoming
Safe and
Pleasant
Adaptable
Resource
Efficient
Easy to
Move
Around and
Beyond

Page 30

Through the Local Development Plan eight strategic development areas have been
identified: 
Working in partnership with the UK and
Scottish Government and East Ayrshire and
South Ayrshire councils, the Ayrshire Growth
Deal will regenerate the region through
investment in strategic infrastructure across
various sectors, including life sciences,
tourism, manufacturing and aerospace, with
total investment of over £251.5m. From a North
Ayrshire perspective and to support investment
into the strategic development areas, including
the Ayrshire Growth Deal and wider economic
regeneration activity, the Capital Investment
Programme from 2024/25 to 2033/34 includes
planned investment of £70.6m. 
Finally, our Community Wealth Building Strategy helps to develop resilient, inclusive
local economies, with more local employment and a larger and more diverse
business base, ensuring that wealth is locally owned and benefits local people. All
capital and revenue investment will be considered within the context of the
Community Wealth Building Strategy, with maximising opportunities for local
suppliers through procurement a key priority and pillar of the strategy. 
Technology Strategy 
The Technology Strategy was approved by North Ayrshire Council in August 2021
and sets out the vision, principles and key technologies that will support
transformational change across North Ayrshire Council. Solutions will be designed in
partnership to improve processes, service delivery and collaboration and ultimately
improve outcomes. The six key Technology Strategy principles are: 
Hunterston
Ardrossan
Harbour and
North Shore
i3 - Irvine Montgomerie
Park, Irvine
Kilbirnie Irvine
Harbourside Brodick Cumbrae-
Millport
Deliberately
designed
•Holistic view of
the business and
deliver efficient,
effective and
agile solutions
People at the
core
•Solutions built
around the
needs of
customers and
people
Anytime,
anywhere access
•Access to
systems,
applications and
information
wherever they
are
Cloud where
appropriate
•Utilise cloud
based
technologies
where
appropriate
Data driven
•Utilise data to
effectively
inform our
decision making
Secure by design
•Operate securely
whilst still 
taking advantage
of technology
innovations

Page 31

Office 365 has been a transformative technology, enabling agile working and
simplifying collaboration.  The ICT Asset Management Plan incorporates the
technology principles and, in terms of investment, a total of £5.6m is planned to
2033/34 to deliver technology solutions aligned to this strategy. From a financial
planning perspective it is also recognised the shift from capital financing to revenue
through software as a service, will lead to a remodelling of the way in which ICT
investment is funded. 
Estates Strategy 
The key objective of North Ayrshire Council’s Estate Strategy is to achieve
rationalisation and remodelling of the Council’s property portfolio on a locality basis. 
The Estates Strategy plays a key role in maximising capital investment across
multiple strategic priority areas, e.g. moving away from the traditional like for like
school replacements to incorporating wider community campus facilities, including
leisure and health and social care facilities. This approach was evidenced through
the Largs campus facility which delivered primary, secondary, and early years
provision as well as community use sport, theatre and leisure facilities. 
Through rationalisation of the Council’s property portfolio, a key funding component
to support the capital programme and provide flexibility in the Council’s Revenue
account, is the generation of capital receipts. Anticipated income from land and
property capital receipts planned to support the capital programme totals £4.1m to
2033/34. 
The neighbourhood approach outlined in the Estates Strategy also recognises
community empowerment and, in particular, provides support to communities for
asset transfers. This engagement is progressed through the Community Planning
Partnerships.

Page 32

General Fund Capital Investment Programme 
North Ayrshire Council takes a long-term approach to capital investment, covering a
10-year period. The plan is updated annually and 2024/25 represents year 1 of the
10-year plan. A full refresh is undertaken every 3 years. The current Capital
Investment programme is aligned to the strategic priorities as set out in the Council
Plan and is the product of the various plans and strategies which impact on the
assets and infrastructure of North Ayrshire Council. Through the Community
Planning Partnerships and the Local Development Plan there is also clear linkage to
local strategic planning and local asset planning. 
Total capital investment of £406.5m from the Council’s General Fund is planned over
the period from 2024/25 to 2033/34, supporting the 3 key strategic priorities from the
Council Plan. This includes planned expenditure of £70.6m towards the Ayrshire
Growth Deal to 2033/34. It is recognised that the total level of investment across
Ayrshire will be in the region of £251.5m (including £103m commitments from both
the UK and Scottish Governments). 
Capital Programme 2024/25 to 2033/34
Total Investment
£406.5m

Page 33

The capital plan includes £111.7m planned investment in Education. The major
areas of education investment include; 
Investment in education reflects the Council’s desire
to ensure children and young people have access to
high quality facilities which support and promote
excellent learning and teaching. Well designed and
well-equipped buildings also support the promotion of
positive health and well-being. 
It is also recognised that investment in education
contributes to and can be integrated within wider
economic development and regeneration within
the localities and this is reflected in the nature of
the planned developments for Ardrossan
Academy and Montgomerie Park school. Through
stakeholder engagement, effective cross
Directorate working within North Ayrshire Council and collaboration with other
agencies including the Scottish Government, these new developments combine
education provision with community facilities, residential, respite and housing
provision as part of a wider focus on economic regeneration. 
Investing in core assets and infrastructure is key to ensuring sustainability. A
planned investment of £112.8m within Roads, Structures and Lighting includes
£38.0m road improvements, £22.0m on flood prevention works and £29.6m on the
upgrading of the B714 following a successful application to the UK Governments
Levelling Up Fund. Property lifecycle investment of £11.2m, to support the property
asset management plan, will ensure Council properties continue to be maintained to
the appropriate standards in delivering services to citizens and communities. The
plan includes investment in several key programmes of regeneration within North
Ayrshire and, in respect of the Ayrshire Growth Deal, on a wider pan Ayrshire basis. 
The Capital Investment Programme 2024/25 to 2033/34 sets out the ambition of
North Ayrshire Council and supports the key strategic themes of the Council Plan.
Through investment that supports regeneration and delivers first class education and
community facilities, this strategic approach will help grow the population and the
local economy. It is also recognised that key to a sustainable environment is the
requirement to continue to invest in core assets and infrastructure. 
Universal School meals
Expansion - £9.6m
•Improvements to current
kitchen and dining
facilities across the
school estate to create
capacity for the
anticipated uptake.
Ardrossan Campus-
£80.2m
•New build project as part
of an exciting wider
community facility
development
Montgomerie Park school
£13.0m
•New primary provision
linked to Montgomerie
park regeneration
project and housing
developments
Schools ICT Investment
£8.9m
•Investment on ICT
Equipment within the
School Estate
Figure 1 Artist impression of Ardrossan Campus
Figure 2 Artist impression of Montgomerie
Park Primary School

Page 34

Funding the Capital Investment Programme 
Funding the Capital Investment Programme requires to be planned in an affordable
and sustainable manner. The funding sources to support delivery of the £406.5m
capital investment programme to 2033/34 include; 
The major sources of funding include assumptions on the level of general capital
grant from Scottish Government to 2033/34 (£90.8m) and the level of prudential
borrowing (£216.5m) required. The cost of borrowing is included within the Council’s
revenue budget process through the Medium-Term Financial Plan and the impact of
borrowing is included as part of the Council’s Treasury Management and Investment
Strategy. 
The Council takes a prudent approach when phasing the capital investment over the
period, with the main objective to ensure general capital grant from Scottish
Government is maximised. 
Other income sources are also explored including external income, grants, partner
contributions and capital receipts. The balance of funding is met from affordable
prudential borrowing with annual loans fund repayments made to reduce the debt.
This approach helps to ensure that investment in assets to deliver on the Council’s
strategic priorities is sustainable in the long term. 
£216.5
£89.1
£90.8
£4.9 £1.1
£4.1
Funding the Capital Investment Programme £406.5million
Prudential Borrowing Specific Capital Grants General Capital Grant
Reserve Funds Other Grants and Contributions Capital Receipts

Page 35

Treasury Management Strategy and Loans Fund Policy 
The Prudential Code for Capital Finance in Local Authorities enables councils to set
their own borrowing limits with a requirement to ensure that investment plans are
affordable, prudent and sustainable. The Council can borrow over a number of years
to supplement its capital income, provided the resultant annual debt repayments can
be accommodated within future years’ revenue budgets. The Council’s annual
Treasury Management and Investment Strategy sets out the prudential indicators
and parameters over the medium to long term, with regular reporting to Council
members through: 
• Annual Treasury Management and Investment Strategy
• Mid-Year Treasury Update report
• Annual Report following the financial year end describing the activity compared
to the strategy 
The key prudential and treasury indicators include: 
• Capital expenditure and financing
• The Council’s overall borrowing need (the Capital Financing Requirement)
• Limits to borrowing activity through the Operational Boundary and the
Authorised Limit. 
As reflected in the Treasury Management Strategy for 2024/25, the analysis of the
Capital Financing Requirement for North Ayrshire Council indicates that the
borrowing needs to support delivery of the capital programme will increase to
£821.544m by 2030/31 and then reduce annually to 2033/34. The analysis also
indicates that this borrowing need continues to be within the parameters of both the
Operational Boundary (the expected maximum borrowing position of the Council)
and the Authorised limit (the limit beyond which external debt is prohibited).

Page 36

Another key affordability indicator is the ratio of financing costs to net revenue
stream. This indicator identifies the trend in the cost of capital (borrowing and other
long-term liabilities, net of investment income) against the net revenue stream of the
Council.  The estimates of financing costs include current commitments and those
arising from the capital programme.  The Housing Revenue Account (HRA) costs are
aligned with the 30-year business plan. 
The estimated ratio of debt to net revenue stream across the next 3 years averages
at 4.3% for General Services and 27.7% for the HRA. From a General Fund
perspective, the CIPFA Directors of Finance Performance Indicators 2022/23 show a
Scottish Local Authority average of 5.4%, therefore demonstrating a prudent
borrowing policy. For the HRA, the indicative Scottish average in 2022/23 was
21.4%. The rising ratio within the HRA is indicative of the significant capital
investment programme as outlined in the Strategic Housing Investment Plan. The
level of loan charges is deemed prudent and affordable within the framework of the
30 year Housing business plan. 
The Liability Benchmark, another treasury prudential indicator, is an important tool
used to identify whether the Council is likely to be a long-term borrower or long-term
investor, allowing it to shape its strategic focus and decision making. The liability
benchmark itself represents an estimate of the cumulative amount of external
borrowing the Council must hold to fund its current capital and revenue plans while
keeping treasury investments at the minimum level required to manage day-to-day
cash flow. 
2023/24 2024/25 2025/26 2026/27
Probable Outturn Estimate Estimate Estimate
% % % %
General Services 2.5% 3.5% 4.4% 4.9%
HRA 20.5% 24.0% 28.7% 30.5%
Proportion of financing costs to net revenue stream

Page 37

Loans Fund Policy 
In July 2016, the Scottish Government confirmed the new Loans Fund accounting
arrangements under the provisions of the Local Authority (Capital Finance and
Accounting) (Scotland) Regulations 2016. This regulation requires the Council to
outline its policy on the repayment of Loans Fund advances. The Loans Fund
advance is effectively the repayment of the principal linked to the capital expenditure
which is required to be funded from borrowing. The broad aim of prudent repayment
is to ensure that the authority’s unfinanced capital expenditure is financed over the
expected life of the asset and that each year’s repayment amount is reasonably
commensurate with the period and pattern of the benefits. 
From a governance perspective the Loans Fund policy of North Ayrshire Council is
included as part of the Treasury Management and Investment Strategy and
submitted for approval to the North Ayrshire Council committee on an annual basis.

Page 38

Governance 
Having robust governance arrangements in place is key to ensuring effective
strategic management of assets, from initial planning through to delivery, utilisation
and disposal. North Ayrshire Council delivers a governance framework through a
number of officer and member represented groups / committees. 
To ensure a consistent approach is adopted when considering any new capital
investment, a business case framework has been developed. The framework
includes key criteria across: 
• Aims and strategic objectives
• Scope and Benefits
• Options Appraisal, 
• Risks, Constraints & Dependencies
• Procurement arrangements
• Monitoring of Key milestones
• Evaluation criteria & scoring  
• Investment costs, funding and impact on revenue 
All business cases are considered by the Capital Programme and Assets Group and
the Executive Leadership Team, with a recommendation being made to Cabinet /
Council, for inclusion of new projects into the Capital Investment Programme. A key
focus when assessing potential capital investment is the alignment to the Council’s
strategic priorities, with the aim being to maximise opportunities where investment
meets multiple strategic priorities and where there is the potential to lever in external
funding. 
The current governance framework is illustrated below: 
Cabinet
North
Ayrshire
Council
Executive
Leadership
Team
Strategic
Assets
Group
Service
Project
Boards
Programme
Boards
Capital
Programme
and Assets
Group

Page 39

The Strategic Assets Group provides a strategic focus on the Council’s property
assets. The key objective of the group is the effective utilisation of Council assets
and to reduce the public sector’s building footprint and deliver improved services
from a smaller, more efficient and fit for purpose estate. 
Service Project Boards are chaired by Executive Directors across each Directorate
area with representation from relevant service managers. Following approval by
North Ayrshire Council committee on the Capital Investment Programme, the Service
Project Board is responsible for ensuring robust project management is in place to
deliver projects on time and within budget. 
Programme Boards provide a strategic focus at programme level and are chaired
by the responsible Chief Officer. Each programme can include a number of individual
projects across each Directorate which contribute to specific Council and programme
objectives. To ensure the objectives are met the Chief Officer for the programme is
responsible for strategic oversight including all projects that form part of the overall
programme. 
The Capital Programme and Assets Group is chaired by the Head of Service
(Finance) and is responsible for: 
• Ensuring a strategic and corporate overview of the Council’s capital programme
is in place.
• Developing and monitoring the Council’s capital investment programme,
tracking slippage on delivery and expenditure against approved budgets.
• Developing clear criteria for investment of Council resources on asset matters
and assessing all investment business cases.
• Developing a prudent capital receipts programme for inclusion in the Council’s
Capital Programme. 
The Executive Leadership Team consists of the Chief Executive, Executive
Director Communities, Executive Director Place, Head of Democratic Services, Head
of People and ICT and Head of Finance and is responsible for advising members on
the relative priorities of the Council’s long term investment needs and plays a key
monitoring role in ensuring the major capital projects deliver the anticipated benefits
on time and within budget. The Executive Leadership Team also considers all
business cases for new areas of capital investment as well as being the escalation
point for any key strategic decisions across the Capital Investment Programme prior
to consideration by Cabinet or Council. 
Cabinet is chaired by the Leader of the Council and is the main decision-making
body of the Council. It consists of member portfolio holders from the Administration.
Cabinet receives regular progress reports and approves amendments to the Capital
Investment Programme. 
North Ayrshire Council consists of all elected members and is chaired by the
Provost. The Council approves the corporate framework and the medium and longer
term Capital Investment Programme.

Page 40

Knowledge & Skills
North Ayrshire Council employs professionally qualified and experienced staff in
senior positions with responsibility for making capital expenditure, borrowing and
investment decisions. 
The Head of Finance is a qualified accountant and holds the position of Section 95
officer for the Council. The Council’s Section 95 Officer is responsible for the proper
administration of the Council’s financial affairs and is required: 
• to recommend treasury management policies / practices, review these regularly
and monitor compliance; 
• to submit regular treasury management updates; 
• to receive and review management information;
• to review the performance of the treasury management function;
• to ensure the adequacy of treasury management resources and skills and the
effective division of responsibilities within the treasury management function;
and 
• to approve the appointment of external service providers. 
Where the Council does not have the knowledge and skills required, use is made of
external advisers that are specialists in their field. The Council currently employs
Arlingclose Limited as treasury management advisers to ensure that we have access
to specialist knowledge and skills if required. 
Decisions to invest in land and property are overseen in accordance with Council
policies and the priorities from our Council plan, to capitalise on its position, power
and influence to deliver tangible improvements to the lives of people in North
Ayrshire. These decisions are made by suitably qualified personnel including
architects and surveyors. 
Risk 
There are risks inherent across all capital planning and project delivery activity. Key
planning risks are managed / mitigated through detailed business case development
prior to any capital investment project getting approved. From a project delivery
perspective, risk registers are maintained throughout the duration of the project and
in accordance with standard project management practice. The long-term view to
capital investment and the development of associated strategies also play a key role
in risk management. Examples include: 
• Development of a 10-year capital programme, considering funding and
priorities in the long term
• Asset Management Plans and lifecycle maintenance which inform capital plans
in the long term
• Treasury Management and Investment Strategy which considers borrowing
levels in the long term.
• Local Housing Strategy and Strategic Housing Investment Plan takes a medium
and long-term view of housing and regeneration priorities.

Page 41

Conclusion 
The Capital Investment Strategy for North Ayrshire Council provides an overview of
how capital expenditure plans, capital financing and treasury management activity
contribute to the infrastructure and provision of services for the benefit of North
Ayrshire communities and citizens. It is a reporting requirement of the CIPFA
Prudential Code. 
The Strategy takes account of the Council’s strategic priorities and considers any
new investment within the context of outcomes and affordability. There is also
recognition of the need to balance investment between maintaining current assets
and infrastructure against the ambitions for acquiring new assets. 
The current capital programme demonstrates an innovative approach in maximising
investment across multiple strategic priority areas, with developments that
incorporate education provision, community facilities, health and social care services
and housing. This approach, whilst providing key services that deliver positive
outcomes to communities, also contributes to the wider economic regeneration of
North Ayrshire, helping to grow the population and the local economy. 
Working in partnership with the UK and Scottish Government and East Ayrshire and
South Ayrshire councils, the Ayrshire Growth Deal will regenerate the region through
investment in strategic infrastructure across various sectors, including life sciences,
tourism, manufacturing and aerospace, with total investment of over £251.5m.

Page 42

Related Documents / Strategies / Plans 
Council Plan
Local Development Plan
Asset Management Plans
Local Outcomes Improvement Plan
Local Housing Strategy
Strategic Housing Investment Plan
Technology Strategy
Estates Strategy
10 Year Capital Investment Programme
Regeneration Delivery Plan
Treasury Management and Investment Strategy
Loans Fund Policy
HSCP Strategic Plan
Environmental,Sustainability & Climate Change Strategy