ARGYLL AND BUTE COUNCIL          PPSL COMMITTEE
DEVELOPMENT AND ECONOMIC GROWTH     22 MAY 2024 
SIMPLIFIED PLANNING ZONES: PROPOSED CLOSURE OF PROJECT 
1.0 EXECUTIVE SUMMARY
1.1 The purpose of this report is to advise PPSL of the proposed closure of the
Scottish Government Simplified Planning Zones (SPZ) Pilot Project, which was
being progressed jointly by Development Policy (Planning and Regulatory
Services) and Housing (Community and Culture) in association with a private
developer on behalf of the Scottish Government.
1.2 The Simplified Planning Zone project was brought to the PPSL Committee on
the 15th March 2017, which endorsed the principle of preparing an SPZ Scheme
for a site in Lochgilphead and another site on Mull. This was to investigate the
use of an SPZ Scheme to enable the delivery of self/custom build homes in
differing situations.
1.3 A number issues arose during the course of the project which have impacted
adversely on its delivery. These included issues relating to flooding, access,
sustainable development, market changes and changed economic and policy
environment. These issues mean that the feasibility of progressing a successful
SPZ Scheme is now unlikely. Therefore continuation with this approach is not
considered to be a practical solution. However, there still remains good
potential to develop both sites more effectively outwith this project through the
normal planning process, including for self/custom build homes. The option to
close the project was discussed with the Scottish Government. Given the
significant issues the Scottish Government would permit the closure of the
project. A requirement of closing the project would be the return of any unspent
grant money.
1.4 Recommendations 
It is recommended that the members of PPSL:
i) note and consider the information in the Report;
ii) recommend to the Policy and Resources Committee, the closure of the
project with the return of unspent monies to the Scottish Government;
and
iii) continue to support the development of the sites through the normal
planning process, utilising information gained during the project where
possible.

Page 2

ARGYLL AND BUTE COUNCIL                  PPSL COMMITTEE
DEVELOPMENT AND ECONOMIC GROWTH    22 MAY 2024 
SIMPLIFIED PLANNING ZONES: CLOSURE OF PROJECT 
2.0 INTRODUCTION 
2.1. The Scottish Government sought projects from local authorities to assist with a
pilot study into the use of the Simplified Planning Zone (SPZ) process. The aim
was to investigate the potential for an SPZ Scheme to assist in the delivery of
self/custom build housing. A Simplified Planning Zone is an area where the
need to apply for planning permission is removed for certain types of
development. 
2.2. Argyll and Bute proposed a project for the Scottish Government pilot that
consisted of a remote rural island location (Mull) with a green field site in private
control and a Main Town (Lochgilphead) location on a brown field site in Council
ownership. Due to a range of issues it has become unfeasible to progress the
project to a successful conclusion. The closure of the project would require the
remaining grant monies to be reimbursed to the Scottish Government. 
3.0 RECOMMENDATIONS 
3.1 Recommendations 
It is recommended that the members of PPSL:
i) note and consider the information in the Report;
ii) recommend to the Policy and Resources Committee, the closure of the
project with the return of unspent monies to the Scottish Government;
and
iii) continue to support the development of the sites through the normal
planning process, utilising information gained during the project where
possible.

Page 3

4.0 DETAIL 
4.1 An SPZ Scheme may be used to promote self/custom build housing delivery.
However, in the case of the 2 sites piloted within Argyll and Bute the issues
encountered during the progression of the scheme significantly reduced the
viability of the approach. 
4.2 The issues include:
• Flooding – full modelling of the Lochgilphead site highlighted issues that were
difficult to resolve within an SPZ Scheme.
• Access – constraints at Lochgilphead that may be better overcome using
land outwith the Scheme.
• Sustainable development – constraints resultant from a Scheme are liable
to reduce delivery capacity and result in a less effective use of a valuable
town centre site.
• Market changes – the Scheme is not easily amended and may constrain
development in changing market conditions.
• Changed economic and policy environment - the Scheme has experienced
significant delays related to the pandemic and SEPA cyber attack. There
are new options for the delivery of self build/custom housing with greater
policy support mechanisms. 
4.3 The benefits of having taken part in the pilot have been the raising of awareness
of self and custom build options with developers and communities, assisting in
developing national policy and technical survey work undertaken on the Council
owned Lochgilphead site. 
4.4 Both sites from the project can progress successfully without the use of an SPZ
Scheme. The Mull site is a designated housing allocation and the Lochgilphead
site is within a Main Town Centre near infrastructure and key facilities. 
5.0 CONCLUSION
5.1 The issues with the SPZ Scheme are such that the sites are not liable to achieve
their full potential through this approach. In addition, market conditions are subject
to change and it is considered that the SPZ Scheme is not as responsive to this
as the normal planning process. The recommended approach is to close the
project and support the delivery of the sites through the normal planning process. 
6.0 IMPLICATIONS
6.1 Policy – None 
6.2 Financial – Unused grant monies totalling £37,099.09 require to be returned to
the Scottish Government.

Page 4

6.3  Legal – There is a requirement to return unused grant monies to the Scottish
Government. 
6.4  HR - None
6.5  Fairer Scotland Duty: None 
6.5.1   Equalities - protected characteristics – None 
6.5.2   Socio-economic Duty – None 
6.5.3  Islands - None
6.6 Climate Change – None 
6.7 Risk – Failure to close the project would utilise additional resource on potentially
abortive work and is liable to result in a less effective route to delivery of
development on the project sites. 
6.8  Customer Service – None
6.9 The Rights of the Child (UNCRC) - None 
Kirsty Flanagan,
Executive Director with responsibility for Development and Economic Growth
Policy Lead Cllr Green
07/02/24                                                
For further information contact: 
Sybil Johnson 01546 604308 sybil.johnson@argyll-bute.gov.uk