Democracy Spraffa

NAC230621 DirApp Council Plan Report (combined)

North Ayrshire Council · 21 June 2023
Back to North Ayrshire Council — 21 June 2023 and its agenda

Text extracted from the council's PDF. Layout and reading order may differ from the original.

Original council PDF · Download plain text

Page 1

NORTH AYRSHIRE COUNCIL 
21 June 2023   
North Ayrshire Council 
Title:    North Ayrshire Council Plan 2023-28 
Purpose:  To consider and agree the Council Plan 2023 - 2028. 
Recommendation:  Council agrees: (i) to approve the Council Plan 2023-28
attached at Appendix 1; (ii) that the Performance
Management frameworks including delivery plans will be
approved by Cabinet and thereafter considered by the
Audit and Scrutiny Committee; and (iii) that progress
reports on the delivery of the Council Plan are submitted
twice per year to Cabinet and thereafter considered by the
Audit and Scrutiny Committee. 
1. Executive Summary 
1.1. The Council Plan is the overarching strategy of the Council.  It details the
Council’s strategic priorities. The current Council Plan, 2019-24, is nearing the
end of its life cycle and Council requires to review and set its priorities for the
next five years. The draft Council Plan for 2023-28 is attached at Appendix 1 and
was prepared through working closely with our communities across North
Ayrshire.  
1.2. This report asks Council to consider and approve the draft Council Plan 2023-
28.
2. Background 
2.1. The Council Plan is the Council’s most important strategic document setting out
our vision for North Ayrshire and key priorities to support achievement.  In turn
these priorities inform how we allocate and target resources.  The current Council
Plan 2019 – 2024 was approved in March 2019 and set out the Council’s Mission,
Vision and Strategic Priorities. As it is nearing the end of its life cycle, the
Council’s priorities for the next five years now require to be determined. 
2.2. Many of the challenges North Ayrshire experiences are complex and longer-term
solutions are required to address them sustainably.  As a result, each Council
Plan is designed to build on the progress of the previous plan and a degree of
continuity can be identified in each.

Page 2

2.3. As a result, our aim remains to achieve ‘A North Ayrshire that is fair for all’.
2.4. Consultation and Data Analysis
2.4.1. A collaborative approach has been taken to develop the new Council Plan.
Internal consultation has included Chief Officer Development Workshops, the
wider staff Leadership Conference, and the Executive Leadership Team.
2.4.2. In January 2023 the Leader of the Council, the Chief Executive and Chief Officers
held in-depth discussions with community group representatives across all six
localities to ensure our Council Plan reflected the priorities of local residents.  We
also invited views through a survey, attracting 1,400 responses.   We worked
with the Customer Contact Centre, the Community Learning and Development
Team, the Education Service, Library Service and specialist Engagement
Officers within the Council to ensure as many of our residents as possible had
the opportunity to have their say. We offered British Sign Language interpreters
on request at events, induction hearing loops and information in alternative
languages.
2.4.3. Since October 2022 we have held a series of mini-enquiries directed by our Child
Poverty and Cost of Living Board to discuss and inform our approach to
addressing Child Poverty.  These events have included public, private and third
sector partners, alongside representatives from our communities, enabling
honest conversations about challenges and how they could be addressed. 
These have directly informed both our recent Child Poverty Action Plan and the
draft Council Plan, particularly within the Wellbeing and Communities and Local
Democracy priorities. At time of writing this has included the following themes:
• No Wrong Door 
• Employability 
• Food 
• Islands – Arran
• Islands – Cumbrae 
• Childcare 
2.4.4. Formulation of the draft Plan has been informed by use of data including that
relating to population decrease and demographic change, child poverty, the
Scottish Index of Multiple Deprivation as well as data on climate change. The
financial sustainability of the Council is essential to the future delivery of services
and due regard is therefore paid to that as a priority in the draft Plan so that we
can continue to work in partnership to meet the needs of our communities.   
2.4.5. Details of our engagement/consultation approach and responses to
engagement, are included at Appendix 2 along with the key outcomes of the
engagement. This engagement was added to earlier consultations that took
place for the Community Plan (Local Outcomes Improvement Plan), Health and
Social Care Partnership Strategic Plan, Locality Partnership Plans and Island
Plans.  It was considered alongside the Strategic Needs Assessment undertaken

Page 3

for the Health and Social Care Partnership Strategic Plan and the People’s Panel
Survey 2022.  This ensured we gathered as wide a range of views as possible
while minimising duplication.  
2.4.6. The views from the consultation exercises were used to shape our draft priorities
which were thereafter shared with our Modern Apprentices (aged 16 to 24 years)
in April 2023 for their comments.  They confirmed that the draft priorities are “the
most important and crucial” to them and were satisfied that the language and
layout of the plan is clear, straightforward and easy to read.  They provided very
helpful guidance on providing effective and relevant feedback on progress and
we will continue to work with them. 
2.5. The Council Plan 2023-2028 
2.5.1. The draft Council Plan is attached at Appendix 1 and details the proposed
strategic priorities and aims along with the key activities we will undertake to
achieve those. The Council’s Vision and Mission, as proposed in Plan are: 
• Vision – A North Ayrshire that is ‘Fair For All’.
• Mission – Working together to improve the lives of our people in North Ayrshire. 
2.5.2. The draft Plan is constructed around four strategic priorities and aims: 
• Wellbeing – To transition to a wellbeing economy, delivering prosperity,
wellbeing and resilience for local people. 
• Communities and Local Democracy – We will have active and inclusive
communities 
• Climate Change – To achieve bet-zero by 2030 
• A Sustainable Council – A Community Wealth Building Council that is efficient
and accessible, maximising investment and focusing resources towards our
priorities. 
2.5.3. Our four priorities are interlinked and interdependent as the progress of each
priority directly impacts the other three areas.  This encourages a joined-up
approach to policy and delivery within the Council and alongside our partners.  
2.5.4. Wellbeing, Communities and Local Democracy and Climate Change focus on
frontline delivery of our services.  The fourth priority A Sustainable Council
enables effective delivery through effective governance and management of
resources.  In addition, some key activities are so large in scale that they are
woven throughout all four of our priorities such as Community Wealth Building,
as detailed in the Council Plan.

Page 4

2.6. Policy Landscape
2.6.1. The draft Plan has been prepared taking cognisance of the wider national and
local policy landscape including:
• The Best Value Assurance Audit and continuous improvement
• National Performance Framework (NPF)
• Human Rights Based Approach
• United Nations Convention on the Rights of the Child (UNCRC)
• Scottish Government Programme for Government
• Accounts Commission Strategy 2021-26
• COSLA Plan 2022-27
• Scottish Government Community Wealth Building Consultation
• Wellbeing Economy Toolkit 
2.6.2. The policy landscape is summarised below:
National Themes / Policies 
• Best Value and continuous improvement
• Community Empowerment (Scotland) Act
2015
• Best Start Bright Futures Tackling Child
Poverty Plan 2022-26
• The United Nations Convention on the
Rights of the Child (UNCRC) 
• The Promise
• Getting it Right for Every Child (GIRFEC)
• Islands (Scotland) Act 2018
• Human Rights Based Approach
• Fairer Scotland Duty
• Equality Act 2010
• Climate Change (Emissions Reduction
Targets) (Scotland) Act 2019 – Net Zero
Scotland by 2045
• Placemaking Approach
• National Strategy for Economic
Transformation (NSET)
• Green recovery and renewal 
Local Strategies
• Community Wealth Building Strategy
• The Regional Economic Strategy
• Community Plan (LOIP)
• Health and Social Care Partnership
Strategic Plan
• Education Service Improvement Plan
• Child Poverty Action Plan
• Children’s Services Plan
• Children’s Rights Report
• Youth Participation and Citizenship
Strategy
• Island Plans
• Regeneration Delivery Plan
• Local Housing Strategy
• Strategic Housing Investment Plan
(SHIP)
• Local Development Plan
• Environmental Sustainability and Climate
Change Strategy
• KA Leisure (North Ayrshire Leisure
Limited) Business Plan 
2.7. The Performance Framework
2.7.1. Actively managing performance through the collection of accurate and relevant
information and setting informed targets is crucial to the successful delivery of
our Council Plan and demonstrating Best Value.  The Direction 2021 states local
authorities must publish information that compares with previous years as well
as with other local authorities in order to demonstrate Best Value.  Information
must be presented in an accessible style for all of our citizens and communities.

Page 5

2.7.2. The Performance Management Framework aligned to the Local Government
Benchmarking Framework and other local performance indicators to support
delivery, implementation and performance measurement of the Council Plan will
be presented to Cabinet for approval. Performance will thereafter be measured
through regular reporting to Cabinet and the Audit and Scrutiny Committee.  In
setting the indicators and in measuring our performance, we recognise that for
some outcomes, the input of government and other agencies will be required.
This will be recognised in the performance measures set which will assess our
contribution to those wider priorities and outcomes.
2.7.3. The key principles underlying the framework which will be presented to Cabinet
to deliver and report on the Council Plan are as follows:
• A clear golden thread of policy cognisant of the National Performance
Framework and Community Plan (LOIP) leading through to the Council
Plan, its Delivery Strategies and Action Plans and performance
management; 
• It must monitor performance against the Council Plan priorities and use
that information to drive improvement;
• A transparent framework to ensure that Members retain control of the
strategic direction of Council and have adequate information to scrutinise
performance against agreed priorities. 
2.7.4. We will continue to prepare an annual Delivery Plan approved by Cabinet setting
out how the priorities of the Council Plan will be delivered. Once approved this
will be remitted to the Audit and Scrutiny Committee for further scrutiny. It is
proposed to report on the Delivery Plan every six months to Cabinet, and
thereafter to the Audit and Scrutiny Committee for further scrutiny.  As an integral
part of that reporting process, our residents and communities will be actively
encouraged to scrutinise our performance through our six monthly ‘magazine
style’ accessible reports which will be published on our website.
2.7.5. Once the Council Plan has been approved, Delivery Strategies and Action Plans
will be prepared to ensure cross Council delivery of the strategic aims and
outcomes. This approach will support a cross-council working and therefore
maximise best outcomes for communities. Performance will be reported to the
Executive Leadership Team (ELT) on a quarterly basis using a traffic light
system. 
2.7.6. We will review our Performance Framework regularly to ensure the information
continues to be relevant and takes account of external changes. Our
Performance Framework is not developed in isolation.  
Every plan, strategy and policy within our Council aligns with our Council Plan
and is listed on our website.  
2.7.7. Our Performance Strategy will be updated following the publication of our
Council Plan 2023-28 and published on our website.

Page 6

2.7.8. Cabinet and Audit and Scrutiny Committee will continue to receive other
performance information in the wider performance landscape. As at present,
reports will continue to be submitted on national benchmarking information
relating to key performance indicators, the Local Government Benchmarking
Framework, the Scottish Index of Multiple Deprivation (SIMD) and Education
data. Audit and Scrutiny Committee also retain the ability to review and
investigate in depth any aspect of the Council’s performance.
2.7.9. In considering the Council’s overall performance framework, the role of internal  
and external audit and of statutory regulators will also form an integral part of
the delivery process. 
2.7.10. In summary, the aim has been to produce a Council Plan which is strategic, is
clear and accessible to employees and communities alike, and which has buy-in
from communities evidenced by consultation responses. 
3. Proposals 
3.1. It is recommended that Council agrees: (i) to approve the Council Plan 2023
-28 attached at Appendix 1; (ii) that the Performance Management Framework
including delivery plans will be approved by Cabinet and thereafter considered
by the Audit and Scrutiny Committee; and (iii) that progress reports on the
delivery of the Council Plan will submitted twice per year to Cabinet and
thereafter considered by the Audit and Scrutiny Committee. 
4. Implications/Socio-economic Duty 
Financial
4.1.   The Council Plan will set the priorities for investment and allocation of resources   
for the next five years.
Human Resources
4.2. The Council Plan recognises the importance of effective workforce planning to
support delivery of our priorities.
Legal
4.3. There are no legal implications arising from this report.
Equality/Socio-economic
4.4. The Council Plan 2023-2028 has been subject to an equalities impact
assessment which includes a Children’s Rights Impact Assessment, an
assessment against the socio-economic or Fairer Scotland Duty and an Islands’
Communities Assessment in relation to the Islands’ Duty.  On the basis that the
priorities in turn inform how we allocate and target resources, the Plan is
expected to have positive impacts for both those with protected characteristics

Page 7

and in terms of the socio-economic and islands’ duties.  As Children and Young
People are a key focus within the Plan, there should be overall benefits for
children and young people. The Council Plan’s impact on islands and the extent
to which any of its priorities has a disproportionate impact on Arran or the
Cumbraes, either positive or negative has also been assessed and no concerns
have been identified. Islands impacts will continue to be considered in the
development of specific actions, Delivery and Action Plans.  All plans that are
developed to sit underneath the Council Plan will undertake appropriate
equalities impact assessments to ensure that no adverse impacts are identified.
The assessments undertaken can be viewed via the link below:
https://www.north-ayrshire.gov.uk/council/strategies-plans-and-
policies/equality-policy-and-performance.aspx 
Climate Change and Carbon
4.4. The Council Plan priorities include ‘Climate Change’ and will directly focus
resources to mitigating the impact of climate change on our residents and reduce
our emissions.
Key Priorities
4.5. The Council Plan sets our strategic priorities for the next five years.
Community Wealth Building
4.6. Community Wealth Building is central to the successful delivery of our Council
Plan and is specifically outlined within the Council Plan 2023-28.
Consultation 
4.7. Consultation was undertaken Chief Officers, Council staff, and
communities. Our communities helped design our priorities. 
This was in addition to previous consultation undertaken for other
Council and HSCP strategies which link into the new Council Plan. 
Craig Hatton
Chief Executive of North Ayrshire Council 
For further information please contact Isla Hardy, Team Manager (Policy and
Performance), on 01294 324035 or email IslaHardy@north-ayrshire.gov.uk.

Page 8

Our Council Plan 2023-28
Appendix 1

Page 9

About us
ARRAN
NORTH
COAST
THREE
TOWNS
SOUTH
AYRSHIRE
EAST 
AYRSHIREIRVINE
KILWINNING
Population: 
134,220
(2021)
12 Scottish National Party (SNP)
10 Scottish Conservative and Unionist
6 Scottish Labour Party
3 Labour and Co-operative Party
2 Independent
33
ELECTED MEMBERS
2 3
GARNOCK
VALLEY

Page 10

Revenue Budget:  £406.064m
General Fund Capital Budget:  £115.931m
Housing Revenue Account (HRA) Revenue
Budget: £57.967m
Housing Revenue Account (HRA) Capital
Budget:  £172.316m
Estimated Budget Gaps:
2024/25:  £16.773m
2025/26:  £10.382m
(£27.155m cumulative)
OUR 
BUDGET
2023-24
29%
of children in North Ayrshire live
in poverty (after housing costs)
19,669
children and young people attend 
our schools and early  years centres 
(including partner early years centres)
Created by berkah terus
from the Noun Project
40.9%
of our residents live in the most 
deprived Scottish Index of Multiple
Deprivation areas
42 Local Authority Early Years Provisions
14 Partner Early Years Provisions
48 Primary Schools
8 Secondary Schools
1 Additional Support Needs School
1 Through School (Early Learning Centre,
Primary & Secondary School combined)
Our schools:
13,135 Council Homes
1,044km carriageways
1,020km footpaths
23,735 streetlights
16 beaches (including 3 Sites of
Special Scientific Interest (SSSI)
275 Hectares of woodland
11,680kW Total installed capacity of
low carbon heat and electricity
generation across our Council’s
estate
28% of households are in fuel
poverty
5.43 tonnes of CO2 emissions area
wide per head of population (4.62 at
Scotland level) 22.7%
of children are looked 
after by our Council 
(14% at Scotland level)
71.2%
of residents 
are in employment
Pioneers of Community Wealth
Building
10 Year Island Plans established
We have Scotland’s first Young
People’s Commission
Language Café for people where
English is not their first language
Over 100,000 trees to be 
planted to achieve net zero
4 5

Page 11

Welcome to our
Council Plan
We have developed our Council Plan 2023-28 together.
This plan is not simply a document, it is our living
contract with our communities in North Ayrshire.  It is
the most important plan for our Council as it contains
the priorities of our residents, it is our joint plan, “our
Council Plan”.  
Our Council Plan explains how we will meet our
communities’ needs and expectations over the next five
years.  It helps steer resources to the areas that can
make the greatest difference to the lives of our people
in North Ayrshire both now and in the future.
Craig Hatton
Chief Executive,
North Ayrshire 
Council
Marie Burns
Leader, 
North Ayrshire
Council
We are aware that many of the issues
we face in North Ayrshire are
extremely complex and will take longer
than a five-year Council Plan to fully
resolve. 
With this in mind, each Council Plan
should be viewed as a substantial step
towards addressing significant
challenges such as child poverty in our
communities and the impact of climate
change. 
By building on each plan, we can drive
immediate and longer-term sustainable
improvements to the lives of our
residents.
Our communities are at the heart of
everything we do and as we move to
deliver our Council Plan we would like
you to hold us to account.  
Are we delivering well?  Could we
improve and how?  We publish Council
Plan Progress Reports on our website
every six months and always welcome
your thoughts and any feedback you
may have. 
We strive to make our Council as
accessible as possible and appreciate
opportunities to discuss how this can
be achieved. Together we will build a
North Ayrshire that is fair for all.
Our Vision
A North Ayrshire 
that is fair for all
Our Mission
Working together 
to improve the lives
of our people in 
North Ayrshire
6 7

Page 12

Our Priorities 
in More Detail
Our four priorities are interlinked and interdependent - they do not sit in isolation as the
progress of each priority directly impacts the other three areas.
This is intentional as it encourages a
joined-up approach to policy and delivery
within our Council and alongside our
partners.  Wellbeing, Communities and
Local Democracy and Climate Change
focus on our frontline delivery of our
services.  
The fourth priority A Sustainable Council
enables effective delivery through
effective governance and management of
resources.  In addition, some key activities
are so large in scale that they are woven
throughout all four of our priorities. 
For example, we are pioneers in Scotland
for Community Wealth Building.  
Community Wealth Building aims to
increase wealth within our area and
create a healthier and more resilient
North Ayrshire.  This is achieved by
encouraging organisations to use their
economic power, to work closely with
communities and invest within North,
South and East Ayrshire.  
It also encourages better use of land and
assets to bring more social and economic
benefits for our residents, while
supporting and promoting fair
employment throughout the region. 
As well as organisations, our residents
have key roles through actively
participating in decision making
(such as participatory
budgeting), ensuring skills
meet the needs of existing
and new good quality local
jobs, volunteering within
our community and
spending locally where 
possible. 
All these areas are key to
supporting what is
known  as a ‘wellbeing
economy’ – an economy
that delivers fair
distribution of wealth and
opportunities within a healthy
environment.  It is therefore a
direct contributor to our vision 
of ‘A North Ayrshire that is fair for all’.
Climate
Change
Communities and 
Local Democracy
Wellbeing
A Sustainable
Council
8 9

Page 13

STRATEGIC AIM –
To transition to a wellbeing
economy, delivering
prosperity, wellbeing and
resilience for local people.
Wellbeing
Key Activities
Ensuring that wellbeing is at the heart
of local life and opportunities, with a
focus on tackling inequalities. 
Developing a Community Wealth
Building approach to a wellbeing
economy:
• Ensuring the best possible labour
market outcomes for residents.
• Support pathways to employment for
residents.
• Promoting a Fair Work economy.
• Developing appropriate skills for the
local and regional economy.
• Supporting local businesses and
economic opportunities.
• Using our assets to support
wellbeing in local communities.
Improving educational attainment and
achievement and closing the attainment
gap.
Improving outcomes for care-
experienced young people including
implementation of The Promise.
Developing the Young Workforce and
ensuring positive destinations for
school leavers.
Providing lifelong learning opportunities
for individuals and organisations,
including digital literacy.
Maximising access to and uptake of
benefits, entitlements and financial
advice.
10 11

Page 14

Ensuring that supports are available in
communities to alleviate cost-of-living
pressures through community hubs and
networks.
Through our housebuilding programme
and wider Housing Investment provide
homes for life that meet the needs of
our residents.
Increase the number of homes in the
area through a mix of private and social
developments and bringing empty
buildings back in to use.
Exploration of models and the
development of pilot schemes to
increase access to and use of
public/community transport.
Ensure our places and spaces where we
live, work and visit are well maintained
and accessible.
Developing infrastructure to support
business growth.
Support KA Leisure’s leadership of
North Ayrshire’s Health and Wellbeing
Alliance.
Through the Health and Social Care
Partnership Strategic Plan we will
protect and provide care and support
for those in need. 
There is a sustained decrease in the
percentage of children living in
poverty.
More of our residents actively
participate in a wide range of
opportunities such as education, social
and democratic participation, mental
health supports and physical activity.
Community Wealth Building is
embedded as an approach and is
contributing to the delivery of a
wellbeing economy.
The specific needs of our island
communities continue to be addressed. 
Attainment and achievement continue
to improve. More of our young people
enter sustained positive destinations
such as further study or employment
after leaving school.  
Good quality affordable ‘homes for
life’ are developed and available to
rent in North Ayrshire.  
More people are employed in good
quality jobs, through having the
necessary skills and qualifications.
We have a growing and sustainable
business base.
Places and public spaces across North
Ayrshire are well maintained and
accessible.
Wellbeing
We will know we’re making progress when:Key Activities Continued
12 13

Page 15

STRATEGIC AIM –
We will have active,
inclusive and resilient
communities.
Communities and
Local Democracy
Developing strong relationships with
communities and partners based on
trust and shared aspirations using their
experiences to inform service provision.
Providing support for community
organisations in achieving their goals,
including as Community Wealth Building
anchor organisations.
Creating a participation and
engagement framework which ensures
opportunities and support for all
residents to take part in influencing
local democracy and Council and
partner strategies. 
Supporting participatory budgeting.
Key Activities
14 15

Page 16

Supporting community asset transfer
and community owned and
operated/managed assets.
Supporting the Community Planning
Partnership and the Community Plan
(LOIP).
Developing partnerships with the third
and voluntary sector.
Placemaking, including creation of
locality action plans based on the
Community Plan (LOIP) priorities and
support the delivery of Islands Plans.
Ensuring an inclusive, fair, rights-based
and asset-based approach in our work.
Accessible public services, both digitally
and locally, ensuring a ‘No Wrong Door’
approach.
More residents are actively involved in
their communities.  Strong, relevant
social support networks are
established that value diversity.
Communities are directly managing
and operating more assets and are
allocating community funding to
initiatives that are local priorities.
Our residents, including our children
and young people, are confident in
exercising their rights and actively do
so.  
Our places encourage strong inclusive
communities and respect the local
environment and cultural heritage.  
Our approach to Community Wealth
Building is further embedded across
partners.
Communities and
Local Democracy
We will know we’re making progress when:Key Activities Continued
16 17

Page 17

Climate
Change
Embedding our net-zero ambition in all
democratic decision-making.
Reducing the carbon footprint of our
estate through rationalisation utilising a
locality-based approach, and taking a
fabric first and low carbon energy
generation approach to homes and
buildings.
Improving resilience and reducing
carbon by developing and supporting
supply chains where materials and
goods are sourced locally.
Promoting new woodland creation and
protecting our green spaces to provide
a natural resource for carbon
sequestration.
Supporting local businesses as they
meet their climate change obligations.
Promoting a circular economy in North
Ayrshire to reduce consumption of raw
materials and promote reuse, repair
and recycling, and generating energy
from residual waste. 
Developing local Low Carbon energy
generation schemes and networks. STRATEGIC AIM –
To achieve net-zero
by 2030.
Key Activities
18 19

Page 18

Unlocking the potential of community
owned energy generation to bring new
income streams into communities and
help them take direct action to combat
climate change.
Learning for Sustainability, and work
with communities to adopt low carbon
behaviour change and encourage
climate-based volunteering activities.
Improving communities’ preparedness
to deal with the impacts of climate
change already locked-in.
Working with communities to adopt low
carbon behaviour change and
encourage climate-based volunteering
activities.
Taking a nature-based approach to
protect our habitats and species. 
Developing and promoting active travel
infrastructure.
Transitioning to low and zero carbon
travel.
Carbon emissions are reducing with a
clear pathway to net zero
We are generating, clean, renewable
municipal and community-owned
electricity.
Our local businesses and communities
recognise how they can mitigate the
impacts of climate change and adopt
changes to help reduce their carbon
footprint.
Our homes and buildings are well-
insulated and energy efficient, making
them cheaper to heat and reducing
their emissions. 
The amount of waste generated is
reducing, whilst levels of reuse and
recycling increase.
Our transport infrastructure enables
people to make active travel choices
and switch to low and zero carbon
vehicles. 
The carbon emissions within our
supply chain are reduced and
community benefits contribute to the
mitigation of climate change where
possible.
Our woodlands and green spaces are
expanding and are providing a natural
resource for carbon sequestration.
Our natural resources are flourishing,
with improvements to the extent and
quality of our habitats. 
Climate
Change
We will know we’re making progress when:Key Activities Continued
20 21

Page 19

A Sustainable
Council
Ensuring robust governance
arrangements are in place to fulfil the
Council’s statutory duties, manage risk
and support delivery of key priorities.
Using dynamic data and lived
experiences to inform decision-making.
Working with partners nationally,
regionally and locally to secure
investment and target resources
towards our priorities.
STRATEGIC AIM –
A Community Wealth
Building Council that is
efficient and accessible, 
maximising investment and
focusing resources towards
our priorities.
Key Activities
22 23

Page 20

Driving change and transformation,
using technology where appropriate, to
deliver efficient and effective services
and support delivery of priorities.
Maximising financial flexibilities to help
support delivery of priorities.
Maximising value from the use of our
assets.
Focusing our investment on priorities.
Effective workforce planning ensuring
that we have the right skills/resources
to deliver priorities.
Lived experience is central in our
approach to improving services and
developing policy.
We use the data we hold to target
resources effectively in line with Data
Protection legislation.
We welcome innovation that improves
the lives of our residents either
directly, or indirectly through more
efficient working, while ensuring none
of our residents are digitally excluded.
The shape of our workforce is planned
and resourced to deliver our priorities,
ensuring our employees are supported
to develop, perform and thrive.  
Effective financial plans are in place to
support priorities.
A Sustainable
Council
We will know we’re making progress when:Key Activities Continued
24 25

Page 21

We combine these with
information on the wider impact
we are having in six monthly
‘magazine style’ reports to our
North Ayrshire Council Cabinet. 
They are then published on our
website www.north-
ayrshire.gov.uk/performance and
scrutinised at our Audit and
Scrutiny Committee.
We identify measures from the
Local Government Benchmarking
Framework (LGBF) that align to our
priorities to compare our
performance with other local
authorities Scotland-wide, so we
can learn from each other and
improve.  These are embedded
directly within our Performance
Framework.
Additionally, we utilise the North
Ayrshire Inclusive Economy
Dashboard which provides
comparisons between local and
national trends in areas relating to
achieving a wellbeing economy. 
This provides important context on
the environment in which we are
operating.
How we will know
we’re making progress
Our Council Plan 2023-28 is a new contract with our communities that we
need to deliver on.  We have a legal duty to demonstrate “Best Value”, this
has continuous improvement for the benefit of our residents at its core.  
Actively managing performance through the collection of accurate
and relevant information and setting informed targets is crucial 
to the successful delivery of our Council Plan and demonstrating 
Best Value.  This is achieved through our Performance 
Framework – a list of indicators (numerical data) 
and activities (detailed above) that reflect our work. 
26 27

Page 22

We review our Performance Framework regularly to
ensure the information we are managing continues to
be relevant to our delivery and takes account of any
external changes.  
This keeps our performance management
“fit for purpose”, enables our Council to
be as agile as possible to embrace
opportunities and makes sure we are
basing decisions on the most up to date
and useful information possible.
Our Performance Framework is not
developed in isolation.  Every plan,
strategy and policy within our Council
aligns with our Council Plan 2023-28 and
is listed on our website.  As a result, the
performance of areas across our Council
feeds into our Council Plan progress
reporting and management.  
Our Performance Strategy will be
updated following the publication of our
Council Plan 2023-28 and published on
our website.
We create our progress reports for our
residents and actively encourage our
communities to scrutinise our
performance.  We are always keen to
hear the best ways to support this – we
were pleased when positive feedback on
our reporting was received as part of our
Council Plan engagement meetings with
community representatives. 
28 29

Page 23

Our Strategic
Environment - 
‘The Golden Thread’
Our Council Plan operates in an
environment of national and local
policies as well as linking to the
HSCP Strategic Plan and KA Leisure
(North Ayrshire Leisure Limited). 
This is shown in the diagram
opposite:
STRATEGIC
PLAN
BUSINESS
PLAN
Resourcing
30 31
Performance
Management 
& Use of Data/
Information
Delivery
Strategies &
Action Plans
LOCALITY
& ISLAND
PLANS
Our Community Plan

Page 24

How we link to the
National Outcomes
As a local authority, we contribute to the delivery of Scotland’s 11 National Outcomes
under the Community Empowerment (Scotland) Act 2015.  These are published within the
National Performance Framework which aims to create a more successful country with
more opportunities and better wellbeing for the people of Scotland. 
It looks to create sustainable and
inclusive growth and reduce inequalities
by giving equal importance to economic,
environmental and social progress and
aligns to the United Nations’ Sustainable
Development Goals.  
The National Performance Framework
and the National Outcomes within it,
were fully considered during the
development of our Council Plan.  This
ensures that our priorities are in line with
Scotland-wide priorities, yet
fundamentally our priorities are formed
on the needs of our residents and have
our communities at their heart.
The National Performance Framework is
currently under review (as at June 2023).
Should any changes be made to the
framework, we will publish a revised list
of links to the National Outcomes within
our six-monthly performance reporting.
32 33

Page 25

Our Community Plan (Local Outcome
Improvement Plan)
Our Community Plan is administered by
the North Ayrshire Community Planning
Partnership which is Chaired by the
Leader of North Ayrshire Council.  The
North Ayrshire Community Planning
Partnership consists of public, private
and third sector organisations, working
together to deliver better outcomes for
our residents.
Our Council Plan priorities and outcomes
align to the three priorities within the
LOIP.  These are:
• Wellbeing – Health and Wellbeing:
“We will reduce inequalities by
targeted support to improve
individual, family and community
health and wellbeing.”
• Work – Economy and Skills: “We will
address the causes and effects of
poverty through a strong local
economy and skills base.”
• World – Climate Change: “We will
work more closely and effectively
together to reduce carbon emissions
and mitigate the impacts of climate
change.”
Health and Social Care Partnership
(HSCP) Strategic Plan
The Health and Social Care Partnership
have their own specific governance
structure through the North Ayrshire
Integrated Joint Board, a joint board of
North Ayrshire Council and NHS Ayrshire
and Arran.  As such, their performance is
not directly reported through our Council
Plan reporting.
KA Leisure (North Ayrshire Leisure
Limited) Plan
KA Leisure is the Council's arms length
organisation, commissioned to work with
the community to deliver health and
wellbeing and physical activity
opportunities in North Ayrshire.  KA
Leisure operates our leisure centres such
as the Portal, Irvine, KA Leisure Campuses
and golf courses such as Routenburn and
Auchenharvie.  KA is providing leadership
and coordination of North Ayrshire’s
Health and Wellbeing Alliance to develop
a collaborative approach to wellbeing
with local partners.  KA Leisure is
governed by a board of directors and
reports on their performance to North
Ayrshire Cabinet.  Key highlights are
reported within our Council Plan.
34 35

Page 26

@north_ayrshire 
North Ayrshire Council  
lovenorthayrshire  
North Ayrshire Council  
North Ayrshire Council
Inviting your thoughts 
We would welcome your thoughts on our 
Council Plan and our progress as we deliver it. 
Please contact us on 01294 310000 or via email at
NorthAyrshirePerforms@north-ayrshire.gov.uk.  
www.north-ayrshire.gov.uk/performance

Page 27

Council Plan Engagement   Page 1 of 7
Council Plan Engagement
We value real lived experience as the most important way to inform our decisions.  Meaningful
engagement is crucial to ensure we truly are working to improve the lives of our people in North
Ayrshire.  Lived experience, data, the learning we have gained from our previous Council Plans and
other key strategies as well as our response to the pandemic has informed our approach to our
Council Plan 2023-28. 
Mini Enquiries
Since October 2022 we have held a series of mini-enquiries directed by our Child Poverty and Cost of
Living Board to discuss and inform our approach to addressing Child Poverty.  These events have
included public, private and third sector partners, alongside representatives from our communities,
enabling honest conversations about challenges and how they could be addressed.  These have
directly informed our recent Child Poverty Action Plan and Council Plan, particularly within the
Wellbeing and Communities and Local Democracy priorities. At time of writing (June 2023) this has
included the following themes:
• No Wrong Door (5th October 2022)
• Employability (28th November 2022, following an internal session on 15th November 2022)
• Food (11th January 2023)
• Islands – Arran (13th February 2023)
• Islands – Cumbrae (20th February 2023)
• Childcare (25th May 2023) 
Council Plan and Budget Engagement
During January 2023 we conducted an engagement exercise for our Council Plan 2023-28 alongside
our Budget for 2023-24.  This included six in person Locality Sessions hosted by our Leader of the
Council, Depute Leader, Chief Executive and Chief Officers, and an online survey.  Discussions were
facilitated by specialist Engagement Officers at each event, ensuring everyone had the opportunity
to state their points of view.  We offered British Sign Language interpreters on request at events,
induction hearing loops and information in alternative languages.
The Locality Sessions included participation from 37 community organisations, while the survey
attracted 1,400 responses.  We worked with our Customer Contact Centre, the Community Learning
and Development Team, our Education Service and Library Service to ensure as many of our
residents as possible had the opportunity to have their say and avoid digital exclusion.  
Feedback from this engagement exercise was considered alongside recent engagement exercises,
such as the Community Plan (Locality Outcomes Improvement Plan (LOIP)), Locality Partnership
Plans, Island Plans, Child Poverty Action Plan and Children’s Services Plan.
Once created, our priorities were shared with our Modern Apprentices (aged 16 to 24 years) in April
2023 for their comments.  They confirmed the priorities are “the most important and crucial” to
them.  They have provided very helpful guidance on providing effective and relevant feedback on
progress and we will continue to work with them.  Specifically, during summer 2023 our young
people will co-develop a Young Person’s Edit of our Council Plan. 
Appendix 2

Page 28

Council Plan Engagement   Page 2 of 7  
Locality Sessions Feedback
This section summarises the key feedback from each Locality Session that took place in January
2023.
Arran Locality
What is impacting on your locality?
• Affordable all year-round housing. 
• Demographics, ageing population, young people leaving and not coming back.
• Lack of Community Transport exacerbating social isolation. 
• Cost-of-living crisis, fuel / energy costs, food dignity.
• Tourism, holiday lets, 2nd & 3rd homes add to housing issues.
• Access to halls and centres for social events and activities.
• Importance of Arran Outdoor Centre: employment, opportunities for experiences and income
for local businesses. 
Priorities for next year and beyond 
• Holistic approach to health and social care, consider local community solutions, such as eco
wellbeing cafes.
• Encourage holistic support for tourism by introducing local tax increase for second homes.
• Education, skills and training to retain young people including intergenerational skills being
passed on.
• Facilities that help children and young people such as Arran Outdoor Education Centre.
• Affordable housing.
• Roads maintenance.
• Community transport.
• Local island office / library to maintain a balance of face-to-face and digital contact.
• Social and community spaces important. 
Preparations for Council Plan: What differences do you want to see?
• Joined up grant funding applications to maximise financial benefits – coordinated community
activity.
• Better access to external agencies, improved co-ordinated joint working.
• Additional tax payments on holiday homes.
• Affordable housing fund for Arran.
• Holistic approach to community, health well-being and safety.
• Community Solutions to island issues.
• Transport improvements and improved connectivity. 
• Better use of technology for Arran.
• Commitment and actions from Island Plan.
• Less bureaucratic systems and quicker decision-making. 
Three Most Important Services Three Least Important Services
1. Affordable housing
2. Education / Community Services
3. Health and Social Care
4. Additional comments included:
a. Empowering Communities to
access grant funding
b. Having an Island Officer 
All services are important but need
to be future proofed.

Page 29

Council Plan Engagement   Page 3 of 7
Garnock Valley Locality
What is impacting on your locality?
• Cost of living in general.
• Transport and fuel costs, especially for the elderly.
• Lack of roads investment, flood prevention.
• Lack of public transport, need for community transport. 
Priorities for next year and beyond 
• Food dignity provision for children and young people.
• Health education for children and young people.
• Community organisations should target activities for young people.
• Huge potential for green energy.
• Improved infrastructure and connectivity.
• High street / town centre rethink needed. Regeneration ideas needed.
• Repurpose derelict buildings.
• Business start-up help – create an entrepreneurial community.
• Attract industry to create jobs.
• Health wellbeing and fitness. 
Preparations for Council Plan: What differences do you want to see?
• Better road condition.
• More community-wide discussions.
• Attracting more quality employment / employers.
• Regeneration for Garnock Valley Towns.
• Invest more in solar panels / green energy.
• Growth in the North Ayrshire economy – in more modern and new ways – digital industries.
• Circular economy – more jobs and the knock-on effect this has for the community.
• Focus on alleviating poverty. 
Three Most Important Services Three Least Important Services
1. Waste services / bin collections.
2. Education and Youth services.
3. Social care / Care at Home.
4. Additional comments included:
a. Roads / pothole repairs.
b. Regeneration of main streets and 
B737 upgrade at Beith.
c. Attracting more employers, big
employers, to the area.
d. Improved mix of social rented
housing stock.
e. Climate change. 
1. All services are important it is about being
efficient.
2. Climate Change (until cost of living crisis
has passed).
3. Investment in digital services (due to it
being good already).

Page 30

Council Plan Engagement   Page 4 of 7
Irvine Locality
What is impacting on your locality?
• Rising fuel costs and the cost of living crisis.
• Lack of reliable public transport, particularly in evenings and in isolated communities.
• Council tax – current system is not fit for purpose and some residents feel they do not get value
for money.
• Roads – current condition is seen as poor.
• Empty town shops – are rates and rents too high? 
• Re-evaluate Town Centre First policy. If a company wants to create a new business out with the
town centre and bring new jobs, Council should encourage development.  
Priorities for next year and beyond 
• Ensure public spaces like community centres / libraries are open as long as possible for warmth
and socialising.
• Transform derelict parcels of land into allotments to allow people to plant vegetables. Involve
schools in the project to stimulate community involvement.
• Invest in renewable energy, such as solar farms and introducing measures which help the
environment and support people with rising energy bills.
• Invest in electric vehicle charging infrastructure.
• Lacks facilities for young people.
• Must continue to invest in school music programmes.
• Must continue to provide support to older people and those accessing Care at Home services or
living in nursing homes.
• Must engage with more rural communities who do not feel the investment put into more
populated communities. 
• Encourage more Community Asset Transfers to give local communities a chance to take
responsibility for a vital local resources.
• Council should be looking closely at its land assets – these should be used for the common good
(solar farms / community allotments etc). 
Preparations for Council Plan: What differences do you want to see?
• Better transport links.
• More investment in care homes / care at home services.
• More electric car chargers.
• More community food investment.
• Better use of rural / unused land. 
Three Most Important Services Three Least Important Services
1. Housing with a range to suit all ages.
2. Roads.
3. Improve people’s skills for employment.
4. Additional comments included:
a. Community Services 
“All services are important.”

Page 31

Council Plan Engagement   Page 5 of 7
Kilwinning Locality
What is impacting on your locality?
• Cost of living impacting health, dignified access to food social isolation, businesses (premises
shutting).
• Environmental improvements needed as many shops and buildings are derelict and need
repurposed.
• Town centre investment required to encourage people to spend. 
• Kilwinning attracts shoppers from surrounding towns and we want this to continue and grow –
parking is an element of this. There are consequences to charging for parking and knock-on
effect for businesses and community.
• Community transport needed. 
Priorities for next year and beyond 
• Access to health and GP services – look at other services that could help, which might prevent
you needing to access a doctor.
• Need better signposting to services.
• Care within your own home – there isn’t a good enough package of care. 
• Solar Farms / solar panel powering energy efficient homes. Ensure community reaps rewards for
profits generated.
• Encourage planning for sea-based power generation – capitalise of our coastal assets.
• Improvement to transport plans and parking.
• Music services are important as are many vocational studies should be a mix between academic
and vocational.
• Transport to schools and parents’ approaches to parking.
• Kilwinning library is a fantastic service a central hub and local for so many different community
events and activities.
• Employment, spend and investment.
• Encourage small business start-ups.
• Worries expressed about the sustainability of community-based services run by volunteers. 
Preparations for Council Plan: What differences do you want to see?
• Regeneration of town centres.
• Transport and plans, improvements to transport.
• Sensible solutions to parking issues in town centre and surrounding areas. 
Three Most Important Services Three Least Important Services
1. Free Parking
2. Regeneration
3. Health / Social Care
4. Additional comments included:
a. Education / Communities
b. Waste Removal 
“Not necessarily least important but…” 
1. Close / repurpose Cunninghame House, if
not being used by staff.
2. No Christmas lights to save money.

Page 32

Council Plan Engagement   Page 6 of 7
North Coast and Cumbrae Locality
What is impacting on your locality?
• Cost of living, transport and fuel costs, especially for the elderly.
• No community centre in Largs, with no focal hub there is a fragmented community.
• Environmental improvements needed.
• Support local economy.
• Provide opportunities for the community.
• Improve social connections. 
Priorities for next year and beyond 
• Community Asset transfer process is complex and bureaucratic.
• No community centre in Largs, which has resulted in the community being fragmented. Centre
could be a focal hub for many Council and community services. 
• There needs to be better connections within and across the Council – no wrong door approach.
• Many teams offer similar services e.g., Money Matters, Welfare Rights, Better off North
Ayrshire. Could these services be amalgamated or could the Council purchase these services
from the Third Sector?
• Planting flowers in glen or vast open areas to save grass cutting.
• With proposed industrial developments at Hunterston Road, infrastructure needs improved.
• The Council’s website and digital services need to be better, not up-to-date and needs
simplified. 
Preparations for Council Plan: What differences do you want to see?
• There should be a Citizens Advice Bureau in Largs.
• Need for better information to enable people to contact the correct support services for
vulnerable people. 
• Need to improve the routes to get people into employment.
• Greater use of social media to recruit staff for example local care home is struggling to fill posts
e.g. Use of Facebook and TikTok. 
Three Most Important Services Three Least Important Services
1. Waste Management 
2. Community Development
3. Health Services
4. Additional comments included:
a. Roads & Infrastructure
b. Children & Youth Services 
“All services are important.”

Page 33

Council Plan Engagement   Page 7 of 7
Three Towns Locality
What is impacting on your locality?
• Improve the Environment, dilapidated buildings make the place look poor which discourages
investment and tourism.
• Mental Health and wellbeing support, social isolation.
• Tackling poverty.
• Provide opportunities for the community.
• Being in a commuter belt for Glasgow means money leaks out of the areas – impacts on
Community Wealth Building (CWB).
• Poor transport links make attracting visitors more difficult. 
Priorities for next year and beyond 
• Health and wellbeing, poverty and the cost of living crises need tackled.
• Education, schools and providing opportunities for children and young people and extended
support around mental health and wellbeing. 
• Community Asset Transfers (CATs) require a more strategic community development model to
empower local people to use CATs and form constituted organisations to enable local people to
apply for additional funding and bridge local authority funding gap (raise awareness of external
national funding etc). 
• Infrastructure limitations negatively impact the Three Towns and tourism, narrow roads, poor
links, poor road surfaces, dilapidated buildings. 
Preparations for Council Plan: What differences do you want to see?
• Town centre regeneration and proper town centre investment to encourage CWB.
• Repurpose shops and encourage pop-up shops. 
• Use buildings differently – close Cunninghame House.
• Green well-kept spaces - encourage partnerships between community and Streetscene.
• Regenerate the coast and make the area more appealing and increase tourism.
• Proper maintenance and repair of buildings.
• Need for more long-term planning as opposed to short term fixing. 
• Simpler language on community asset transfers.
• Procurement should be open to community and local groups.
• Taking a longer term, strategic view of community capacity building (work with an asset building
model). Allow constituted groups to apply for external funding and create additional skills.
• More volunteering including senior years at school – encouraging social responsibility factor in
Duke of Edinburgh Awards involvement.
• Greater investment in mental health and wellbeing in both schools and the wider community.
Look at the causes (prevention as opposed to cure).
• Encourage younger people on Community Councils.
• Make more use of council transport for community transport needs. 
Three Most Important Services Three Least Important Services
1. Connected Communities and Education
2. Streetscene
3. Regeneration 
“Not necessarily least important but…” 
1. More efficient smarter working
2. Better Communication
3. Close / repurpose Cunninghame House