NORTH AYRSHIRE COUNCIL 
25 June 2025 
Council 
Title:    Ardrossan Campus 
Purpose:  To provide Council with an update on progress with the delivery
of the Ardrossan Campus project, the overall transformational
regeneration outcomes which will be delivered, the current
financial position, and to set out the additional funding that is
required as a result of market conditions in the construction
industry to enable the delivery of the project in accordance with
current programme timelines. 
Recommendation:  It is recommended that Council notes the current project status,
the overall transformational regeneration outcomes which will be
delivered, the current financial position, and approves additional
funding now required to enable the delivery of the project in
accordance with current programme timelines. 
1. Executive Summary 
1.1 The Ardrossan Campus project is a key component of the wider Ardrossan Coastal
Quarter regeneration programme and will deliver an educational and community
campus comprising:  
• 1200 pupil secondary school (including 18 place Astra Base). 
• 220 pupil primary school
• 34 pupil early years provision
• a public library
• a public swimming pool 
• community access to other sporting facilities outwith school hours 
• Health and Social Care Partnership (HSCP) office accommodation 
• a Campus Police Officer base 
1.2 The vision for the wider site also includes the provision of new housing and commercial
uses, providing ambitious transformational regeneration of a vacant and derelict site on
land within one of North Ayrshire’s most deprived communities. The project also
supports the ambitions of the Local Development Plan. 
1.3 The project has been progressed in partnership with the Scottish Futures Trust and
forms part of the Scottish Government’s Learning Estate Investment Programme (LEIP).
This programme provides a significant proportion of funding towards the cost of the

Page 2

Campus and is predicated on alignment with the national School Estate Strategy and
delivery of specific outcomes. 
1.4 The Campus project follows preparatory investment in the site, including the
replacement of an ageing revetment (sea-defence wall), land remediation works,
creation of site access and road infrastructure, utilities connections and construction of
an extension to the coastal path. These works are almost complete, and subject to
anticipated confirmation from the Scottish Environment Protection Agency (SEPA ) and
the Council’s Environmental Health team, the site will be available for the Campus
project construction to commence in July. 
1.5 The design development phase of the Campus project has been undertaken in parallel
with the remediation and enabling works and has recently been subject to a market
testing process to provide a final cost proposal. This period has seen extra-ordinary
volatility in the construction sector. Analysis of the market tested tender package returns
for the campus, following application of identified efficiencies and agreed value
engineering proposals, have identified a significant shortfall between the current budget
allocation of £86.8 million and the amount identified to deliver the project at £114.6
million. 
1.6 The project team has undertaken a thorough review of the project costs against all
budget lines to remove any duplication and identify areas of efficiencies and savings.
This has resulted in a reduction of £4 million from the original stage 4 submission. To
further narrow this gap and minimise the amount of additional funding that is required,
a further £4.3 million of value engineering has also been agreed by the Programme
Board. These savings were selected to minimise the impact on teaching, learning and
the community spaces and the project outcomes which are an integral part of the SFT
funding offer, whilst recognising the imperative to deliver both value for money (VfM)
and affordability. 
1.7 An approach was also made to Scottish Futures Trust (SFT) for additional funding to
support the abnormal elements of the project. It was agreed at their board meeting on
17 June that an additional £4m would be allocated to assist with the specific challenges
being encountered with the Ardrossan Campus project.   
1.8 The existing Ardrossan Academy is rated condition D (poor) and is considered beyond
its useful economic lifespan. Whilst necessary repairs continue to be undertaken, the
existing school’s condition highlights the urgent need for investment. 
1.9 The current construction programme, subject to approval of additional funding as
requested in this report, is for the new Campus to be handed-over and operational in
October 2027. 
2. Background 
2.1 The Ardrossan Campus project is a key component of the wider Ardrossan Coastal
Quarter regeneration programme and will deliver an educational and community
campus comprising: 
• 1200 pupil secondary school (including 18 place Astra Base). 
• 220 pupil primary school
• 34 pupil early years provision
• A public library

Page 3

• A public swimming pool 
• Community access to other sporting facilities outwith school hours. 
• Health and Social Care Partnership (HSCP) office accommodation 
• Campus Police Officer base 
2.2 The vision for the wider site also includes the provision of new housing and
commercial uses, providing transformational regeneration of a vacant and derelict
land site within one of North Ayrshire’s most deprived communities. 
2.3 The Local Development Plan has allocated the Ardrossan Coastal Quarter area as
part of Strategic Policy 3: Strategic Development Areas. Along with the residential/
mixed use site, the policy proposes a new Maritime hub and commercial centre. The
transformational regeneration of the area supports development that:
• addresses socio-economic needs of local communities in capturing new,
inclusive economic activity that extends economic resilience across the
community.
• delivers community priorities identified through the Three Towns Charrette.
• includes commercial, leisure and employment uses.
• provides active travel routes into and throughout the site 
2.4 The Campus project follows preparatory investment in the regeneration of the site,
including the replacement of an ageing revetment (sea-defence wall), remediation
works, creation of site access and road infrastructure, utilities connections and
construction of an extension to the coastal path. These works are nearing completion
and, subject to anticipated confirmation from the Scottish Environment Protection
Agency (SEPA ) and  the Council’s Environmental Health team, the site will be
available for the Campus construction project to commence in July. 
2.5 The existing Ardrossan Academy is rated condition D (poor) and is considered
beyond its useful economic lifespan. Whilst necessary repairs continue to be
undertaken, maintaining the facility’s statutory compliance and suitability as an
environment for teaching and learning presents an on-going challenge and revenue
budget burden, thereby highlighting the urgent need for investment .   
2.6 The existing Ardrossan Academy condition and the transformational benefits that will
be delivered through incorporation of a new Campus into the wider Coastal Quarter
Programme have been recognised by the Scottish Futures Trust (SFT) and the
Council have successfully bid for inclusion in the Scottish Government’s Learning
Estate Investment Programme (LEIP). 
2.7 The LEIP programme provides a significant proportion of funding towards the
Campus and is predicated on alignment with the national School Estate strategy and
delivery of specific outcomes. The high-level LEIP programme requirements include: 
• in-use energy figures of between 67-83KWh/m²/annum
• maintenance of the facilities in condition A/B for 25 years following handover
• delivery of 1GB connectivity to teaching and learning spaces
• delivery of stated employment targets 
In addition, there are also project specific objectives, which align with the Council
Plan and include: wellbeing, resilient growth, community wealth building and lifelong
learning.

Page 4

2.8 SFT have been closely involved in the project and supportive throughout, including
representation on and regular attendance at the officer Ardrossan Programme Board
which co-ordinates and provides governance to the various elements of the Coastal
Quarter programme. An approach was also made to Scottish Futures Trust (SFT) for
additional funding to support the abnormal elements of the project. It was agreed at
their board meeting on 17 June that an additional £4m would be allocated to assist
with the specific challenges being encountered with the Ardrossan Campus
project.  A pre-construction workshop with SFT and Scottish Government is also
scheduled for 2nd July to allow the project team to demonstrate to Scottish
Government and SFT representatives how the project aligns with the LEIP
programme objectives, prior to awarding the construction contract. 
2.9 The Council procured a team of external designers and advisors with the requisite
expertise and experience to undertake a project of this scale and complexity. The
procurement scoring process of these parties included a substantial focus on quality
to ensure the team had the correct capability and capacity to undertake the work.
The design team have worked closely with the Council to develop the project scope,
outline proposals and detailed designs, including providing cost advice throughout.
The design development phase has also included significant stakeholder
engagement with relevant Council services, building users, external agencies (KA
Leisure, SEPA, Care Inspectorate, SFT, etc), and community groups, to ensure the
proposals meet the needs of the Council and the wider community that will benefit
from the development.   
2.10 The Council also procured a construction contractor, Morgan Sindall, through an
extensive procurement exercise, also with a focus on quality and to ensure that the
Council’s ambitions could be delivered successfully. This procurement exercise was
a two-stage process whereby the main-contractor is appointed on the basis of their
construction prelims, overhead and profit on-costs. The remainder of the supply
chain subsequently tenders for relevant work-packages on an “open-book” basis.
One of the components of the two-stage procurement process chosen for the project
is that the contractor becomes involved in the design development and is able to give
advice on issues such as buildability and costs at an earlier stage of the project than
a traditional one-stage tender process whereby no contractor input received until the
point of tender-return. 
2.11 Cost review exercises have been undertaken by Atkins Realis (Quantity Surveyors)
on behalf of the Council throughout each design stage of the project. The figures
which have informed the development of the cost plans have been based on current
market intelligence from a range of recent school campus tender returns of similar
complexity and scale, including other LEIP funded projects, to inform the expected
tender return rates. 
2.12 Cost pressures have been noted throughout the project; however, the project team
have taken corrective action at each stage to reduce the anticipated costs and to
address potential budget shortfalls and have liaised with the Council’s Finance Team
throughout. In March 2024, a divergence in the cost plans of the cost consultants and
the contractor was identified. An independent assessment of Atkins Realis and
Morgan Sindall’s cost plans was undertaken by a third party cost advisor, Currie and
Brown, on behalf of the Council to better understand the differences between the two
parties. This assessment highlighted the main area of difference was in the
assessment of the Mechanical and Electrical work package. As this work-package

Page 5

forms a substantial portion of the overall contract value, options to address this
potential issue were investigated. 
2.13 As a result, it was agreed that, in view of the cost forecast and the fact that the
project could still deliver on the LEIP in-use energy requirements and the project’s
low-carbon sustainability ambitions, the project team should remove the requirement
to deliver the Passivhaus Classic standard from the Campus specification and to
investigate further options for value engineering to reduce the overall cost of the
project. 
2.14   At that stage Morgan Sindall advised they believed that the majority of the delta
could be addressed by taking this approach. Advice was also sought from other
Local Authorities experiencing cost challenges in their projects; this confirmed the
move away from the formal Passivhaus standard is a mitigation that has been
applied elsewhere. 
2.15 Due to the significant change in scope of the project, a new procurement exercise
was undertaken, in order to comply with procurement legislation. The design of the
project was awarded through the SCAPE framework to Morgan Sindall in August
2024. This approach was selected to maintain design continuity and reduce any
further delays on the delivery of the project, in recognition of the condition status of
the current Ardrossan Academy learning environment. 
2.16 Prior to the market testing process commencing in November 2024, a further cost
review exercise was undertaken by Atkins Realis in collaboration with Morgan
Sindall. The Atkins Realis cost plan at £80.1 million was once again based upon
recently tendered rates on a number of similarly sized and scoped projects. The
Morgan Sindall cost plan was £84.2 million.   
2.17 In recognition of the intelligence received and the extremely volatile construction cost
landscape, the Council approved an initial capital flexibility provision of £15million in
the Council budget set on 26 February 2025. This was agreed to help address
anticipated financial pressures across a number of projects in the capital programme. 
2.18 The market testing process undertaken by Morgan Sindall and completed in April
2025 on this project has identified a further significant gap between the cost plans
prepared prior to market testing and the actual returns. 
2.19 Analysis of the reasons for the increase in costs has been undertaken, including
input from the external cost advisors, the contractor and SFT. Prevailing conditions in
the construction industry at present are impacting the costs of all capital projects,
including the Campus: 
• Construction inflation
o The Campus project requires to follow the remediation and enabling
works contracts, which are nearing completion. The programme for
these works has been extended, principally as a result of construction
market appetite and capacity to undertake the works.  Overall
construction inflation, as measured by the Building Cost Information
Service (BCIS), has increased markedly in the period. The two main
indices which reflect construction inflation, Tender Price (TPI) and
Outturn Price (OPI), have risen by 26% and 37% respectively.

Page 6

• Material availability
o Recent changes and uncertainty in relation to tariffs introduced in 2025
have significant implications for international trade and supply chains.
Delays and uncertainties in shipping affects the timely delivery of
materials, leading to increased project costs.
o Other areas of pressure specific to the construction industry, include a
10% rise in specific product markets, for example insulation costs and
anomalies in timber and ironmongery. There are also early indications
of price strain in the steel industry.
• Labour and Skills Shortages
o Labour shortages have been a persistent issue over the past few years,
exacerbated by more recent immigration requirements. 
o This issue is recognised in the Scottish Construction Accord
Transformation action plan which highlights the need to increase the
capacity, capability, and diversity of the workforce with a focus on
future skills.
• Regional Supply Chain Pressures
o The abundance of other large-scale construction work in the Central
Belt (HMP Glasgow, Monklands Hospital, Glasgow University, SFRS,
and other LEIP projects) is significantly affecting competitive pricing for
projects outside of Glasgow and Edinburgh. The high demand for
labour and staff resources in the Central Belt has created a shortage of
available personnel for the project in Ardrossan. This shortage is
particularly acute among key specialist subcontractors in cladding and
mechanical and electrical services.
o There has been a requirement to incentivise labour to travel to
Ardrossan due to the abundance of projects in the Central Belt. The
value of this labour incentive has been reported by the supply chain as
up to 7.5% on labour costs alone which equates to over £4 million
across several key work packages.
• Design Development
o To ensure warranty / guarantee on the longevity of the components,
linked to the LEIP funding requirements in relation to sustained building
condition, the specification of some components has been enhanced to
reflect the exposed, marine conditions of the site. 
o Marginal additional building area (61m²) arising from the final co-
ordination of services, including increases to risers and changes to
voids within the secondary wing. (Area increases have been mitigated
through value engineering).
o Additional items were identified through the supply chain engagement
in increased sheet piling to the basement excavations, the well pointing
system, pond undercroft for filtration pipes to ensure no tidal impact of
the system and increasing the extent of gas venting. 
2.20 Robust scrutiny from officers and governance through the Ardrossan Programme
Board, including engagement with key stakeholders, has taken place to address the
budgetary challenges on this project. This has included:
• a thorough review of the Contractor Tender Packages (CTP) by Atkins Realis
to remove any duplications and inconsistencies across each work package.
This has resulted in a reduction in the CTP allowance of £4 million from the
original stage 4 submission.
• additional value engineering options have been accepted by the Programme

Page 7

Board up to a value of £4.3 million.
• a review of all the project budget lines to identify efficiencies and savings.
• a request for additional funding from Scottish Futures Trust to support the
‘abnormal’ abnormals on the project. 
2.21 The value engineering options have sought to maintain the integrity of the design
and energy efficiency requirements and to maximise the available partnership
funding from the Scottish Futures Trust which is released over the 25 years following
handover and is dependent on the attainment of the LEIP funding criteria noted
above. Any major changes to the scope and specification of the project could affect
future revenue funding streams. 
2.22 Notwithstanding the agreed value engineering, the proposals will deliver a high-
quality teaching, learning and community environment which will fully meet the
Scottish Futures Trust LEIP funding requirements including the in-use energy
targets. 
2.23 The review process described above has resulted in a projected final cost for the
Ardrossan Campus of £114.6 million which is currently anticipated at £27.8 million
above the current budget allocation. 
2.24 As is prudent at a major gateway review stage of all large capital investment
projects, in view of the budget impacts, the following wider options available have
been considered: 
• re-tender the project in its current form
• revise the project scope and re-tender 
o Omit key elements to reduce costs
o Refurbish / partial new-build existing building 
A high-level appraisal of these options highlights the following key issues: 
• programme delays will result in further inflationary pressures, which
would offset (in-part or in-full) any potential savings
• market conditions are unlikely to ease in the short to medium term
• SFT funding has been secured based on the current transformational
vision for the learning environment and the wider site
• existing facilities are already in poor condition and subject to further
deterioration as the programme extends. 
• no other suitable sites were identified to deliver the project scope
• preparatory investment has been made in the remediation / enabling
works
• disruption to teaching and learning should be mitigated to the
maximum extent possible. 
2.25  The key current risks which could arise through the construction phase of the project
and associated mitigations are noted, for which a project contingency fund has been
included within the latest cost estimates to help address the risks: 
Risks  Mitigations
Systemic Construction impacts on project
delivery e.g. conflicts, tariffs that could
impact on the supply chain required for
delivery, etc. 
Legal processes have been used in the
development of the contracts to minimise risk.
Close monitoring of contractor and supply
chain to overcome potential risk of human

Page 8

resource and material unavailability, supply
chain insolvency, etc. 
Ground conditions relating to the deeper
excavation activities required to construct
the pool, piling and deep drainage. The
works undertaken to date have addressed
known issues to an average depth of 3.5m
in accordance with industry best practice.
The site investigations undertaken to date
do not indicate any issues, however, it is
prudent to hold a contingency. 
Regular coordination meetings have been held
with enabling works team through the design
development stage. Extensive site
investigations to identify areas requiring
remediation and works undertaken in
accordance with agreed strategy. An
assessment has been made on the likely
worst-case costs that could arise from this
eventuality.
Obtaining statutory consents in a timeous
manner to permit construction to proceed.
Meetings held with Building Standards and
Planning to understand optimum processes for
discharge of conditions. 
Business continuity decisions should there
be a delay to the construction of the new
Campus
Robust business continuity plan in place and
strategy for managing buildings in interim is
being implemented. 
Overall risk profile associated with the
NEC4 form of contract. 
A £5m project contingency allowance has
been incorporated into the project budget. This
is intended to address any compensation
events which arise through the contract. 
2.26 In consideration of the significant transformational opportunity of the Coastal Quarter
Programme, the options available, the condition of the current Ardrossan Academy, the
remaining risks and the financial context, the assessment is that allocating additional
funding and proceeding to Financial Close with Morgan Sindall is the recommended
course of action. 
2.27 If Council approves the additional budget allocation, the Chief Executive will have
authority to sign the Financial Close documents, entering the Council into a contract to
construct the Campus. Subject to this approval and entering into the contract,
construction works will be able to commence in mid-July 2025 with a programmed hand-
over and operational date of October 2027. 
3. Proposals 
3.1 It is proposed that Council notes the current status of the Ardrossan Campus project, in
particular the positive outcomes that will be delivered in relation to:
• The improved teaching and learning environment for the pupils of Ardrossan
Academy and Winton Primary School.
• The improved user experience for the patrons of Auchenharvie Swimming Pool
and Ardrossan Library.
• The improved user experience relating to the Children and Families team
currently located at Aitken Place in Ardrossan. 
• The transformational economic regeneration opportunities arising from the
wider Ardrossan Coastal Quarter programme and the alignment with the
Council Plan priorities. 
• The LEIP programme deliverables (in-use energy, building condition, local
employment and digital connectivity).

Page 9

3.2 It is proposed that Council approves the additional budget provision of £27.8 million
which is required for the project. This would require to be funded through, the £4 million
additional awarded by SFT a re-direction of £7.8 million from existing capital flexibility
and additional borrowing of up to £16 million, at an annual revenue cost of £0.912 million
per annum. 
4. Implications/Socio-economic Duty 
Financial 
4.1 Additional expenditure budget provision of £27.8 million is required for the project. This
would require to be funded through, the £4 million additional awarded by SFT a re-
direction of £7.8 million from existing capital flexibility and additional borrowing of up to
£16 million, at an annual revenue cost of £0.912 million per annum. This funding will
require to be incorporated in the Council’s Medium-Term financial Plan covering the
period 2026/27 to 2028/29. It is also recognised that a further review of the Council’s
Capital Investment programme will be undertaken covering the period 2026/27 to
2033/34, to ensure the revised programme is prudent, affordable, and sustainable. This
review will include a long-term projection of interest rates associated with anticipated
borrowing need, as well as assessments of expenditure profiles, capital receipt
forecasts, anticipated capital grants and the profiled use of the loans fund reserve to
support the programme. 
Human Resources 
4.2 As part of the review of the budget lines across the project – an assessment was
undertaken of the resource requirements required to deliver the construction phase of
the project. This resulted in a reduction in the Schools for the Future project team with
the reduction of one post, facilitated through redeployment within PMI. 
Legal 
4.3 The legal arrangements on the project have been dealt with by Harper Macleod and the
contract has been prepared for signing should Council approve additional funding. 
4.4 If Council approves the additional budget allocation, the Chief Executive will have
authority to sign the Financial Close documents, entering the Council into a contact to
construct the Campus. 
Equality/Socio-economic 
4.4 The construction of the new campus, as a key component of the wider transformational
regeneration of the Ardrossan Coastal Quarter will have significant direct and wider
socio economic benefits. 
Climate Change and Carbon 
4.5 Ardrossan Campus has been designed to be highly energy efficient and to meet the
LEIP requirements of between 67-83KWh/m²/annum. The current stage 4 design shows

Page 10

a predicted attainment of 71KWh/m²/annum. A sustainability responsibility matrix has
been developed and incorporated into the contractual proposals to deliver facilities that
will contribute to the Council’s climate change priorities. 
Key Priorities 
4.6 The project supports the following Council priorities: 
Wellbeing 
• Developing appropriate skills for the local and regional economy
• Using our assets to support wellbeing in local communities
• Improving educational attainment and achievement and closing the attainment
gap
• Developing the young workforce and ensuring positive destinations for school
leavers
• Providing lifelong learning opportunities for individuals and organisations including
digital literacy
• Improving outcomes for care-experienced young people including implementation
of The Promise
• Ensure our places and spaces where we live, work and visit are well maintained
and accessible.
• Support KA Leisure’s leadership of North Ayrshire’s Health and Wellbeing Alliance
• Through the Health and Social Care Partnership Strategic Plan we will protect and
provide care and support for those in need. 
Communities and Local Democracy 
• Developing partnerships with the third and voluntary sector
• Placemaking, including creation of locality action plans.
• Accessible public services, both digitally and locally. 
Climate Change 
• Embedding our net-zero ambition in all democratic decision-making.
• Reducing the carbon footprint of our estate and taking a fabric first and low carbon
energy generation approach to homes and buildings
• Promoting new woodland creation and protecting our green spaces to provide a
natural resource for carbon sequestration. 
Community Wealth Building 
4.7 A suite of community benefits has been developed through the design and construction
phases of the project. The commitments from Morgan Sindall which are defined in the
SCAPE framework agreement have been incorporated into the contractual
requirements for the project. 
Islands Communities Impact Assessment (ICIA)

Page 11

4.8 None 
United Nations Rights of the Child (UNCRC) 
4.9 The development of the Campus fully supports these rights. 
Consumer Duty 
4.10 The project will deliver on these through the Stakeholder Reference Group and Client
Planning workstreams. 
5. Consultation 
5.1 Consultation has been undertaken with Education, Finance and Legal Services. 
RUSSELL McCUTCHEON
Executive Director (Place) 
For further information please contact Laurence Cree, Head of Service Sustainability,
Transport & Corporate Property, on 01294 324514. 