Creran Homes Ltd: Erection of 6 Dwellinghouses and Installation of 2 Septic Tanks: Land South East of Inverbhreach Cottages, Barcaldine (Ref: 23/02409/Pp)

Argyll and Bute Council · 19 June 2024
Back to Planning, Protective Services and Licensing Committee — 19 June 2024 and its agenda

Text extracted from the council's PDF. Layout and reading order may differ from the original.

Original council PDF · Download plain text

Page 1

LDP2 format template March 4th 2024
Report of Handling Template for PPSL and Delegated Planning Applications – Updated 10.11.2023 
Argyll and Bute Council
Development & Economic Growth   
Planning Application Report and Report of Handling as required by Schedule 2 of the
Town and Country Planning (Development Management Procedure) (Scotland)
Regulations 2013 relative to applications for Planning Permission or Planning
Permission in Principle 
Reference No: 23/02409/PP
Planning Hierarchy: Local 
Applicant: Creran Homes Ltd 
Proposal: Erection of 6 Dwellinghouses and Installation of 2 Septic Tanks 
Site Address:  Land South East of Inverbhreach Cottages, Barcaldine 
DECISION ROUTE 
☐Delegated - Sect 43 (A) of the Town and Country Planning (Scotland) Act 1997 
☒Committee - Local Government Scotland Act 1973 
(A)  THE APPLICATION 
(i) Development Requiring Express Planning Permission 
• Erection of 6 dwellinghouses 
• Installation of 2 septic tanks 
• Formation of private access road 
(ii) Other specified operations 
• Utilisation of existing vehicular access 
• Connection to public water main 
(B) RECOMMENDATION: 
Having due regard to the Development Plan and all other material considerations, it
is recommended that planning permission be granted subject to the conditions and
reasons appended to this report. 
(C) CONSULTATIONS:   
Argyll and Bute Council – Roads Authority 
Report dated 16/04/24 advising no objection to the proposed development subject
to conditions being imposed on the grant of permission to secure the upgrade of the
existing access at the junction with the B845 public road and provision of a 2 metre
footway; the provision of speed calming measures; the provision of a passing place
along the new stretch of private access track; the provision of a turning head within
the new stretch of private access track; the provision of parking and turning for three

Page 2

LDP2 format template March 4th 2024
Report of Handling Template for PPSL and Delegated Planning Applications – Updated 10.11.2023 
vehicles for each dwellinghouse; and the provision of a bin storage area on the new
stretch of private access track. 
Argyll and Bute Council – Environmental Health Service
Memo dated 17/01/24 advising no objection to the proposed development subject to
a condition being imposed on the grant of permission to restrict the hours of
construction of the proposed development.  However, this is not something that
should ordinarily be controlled by planning condition. Should construction noise
become an issue within the development, this is a matter that would be dealt with
directly by the Environmental Health Service. 
Scottish Water 
Letter dated 28/12/23 advising no objection to the proposed development which
would be serviced from the Tullich Water Treatment Works but providing advisory
comments for the applicant regarding connection to their infrastructure. 
JBA Consulting Ltd  
Final report dated 25/04/24 advising no objection to the proposed development. 
Consultation responses are published in full on the planning application file and are
available to view via the Public Access section of the Council’s website. 
(D) HISTORY:   
22/02546/PP 
Erection of 12 dwellinghouses, formation of vehicular access and installation a
sewage treatment plant – Withdrawn: 11/01/24 
22/01113/PP
Erection of 21 dwellinghouses, installation of sewage treatment plant, formation of
access and a play park area – Withdrawn: 06/09/22   
20/01879/NMA 
Non material amendment for change of house type and relocation of driveways on
plots 6 and 9 relative to Planning Permission 19/00150/PP for erection of 10
dwellinghouses and installation of septic tank – Granted: 28/10/20 
20/01228/NMA
Non material amendment for amendment to boundary treatment relative to
application 17/03075/PP – Granted: 17/07/20 
19/00150/PP 
Erection of 10 dwellinghouses and installation of septic tank – Granted: 28/05/19 
18/02621/NMA
Non material amendment to 17/03075/PP - Relocation of plots 1 -4 south east by
3m – Granted: 13/12/18 
18/01843/NMA
Non Material Amendment to planning permission reference 17/03075/PP (Erection
of 10 affordable dwellinghouses, installation of private drainage system and
formation of vehicular access) Adjustment to the location of the dwellinghouses and
driveways for plots 1-4 – Granted: 31/08/18

Page 3

LDP2 format template March 4th 2024
Report of Handling Template for PPSL and Delegated Planning Applications – Updated 10.11.2023 
17/03075/PP 
Erection of 10 affordable dwellinghouses, installation of private drainage system and
formation of vehicular access – Granted: 16/03/18 
(E) PUBLICITY:   
The proposal has been advertised in terms of Regulation 20 and Neighbour
Notification procedures, overall closing date 01/02/24. 
(F) REPRESENTATIONS:   
(i) 18 objections and 1 representation has been received from: 
Oban and District Access Panel – by e-mail only – (21/0124) 
Odile Francois, Glensalloch House, Barcaldine, PA37 1SF (13/01/24)
David Jackson, 17 Inverbhreach Cottages, Barcaldine, PA37 1AH (11/01/24)
Keira Jackson, 17 Inverbhreach Cottages, Barcaldine, PA37 1AH (11/01/24)
Liam Roberts, 23 Inverbhreach Cottages, Barcaldine, PA37 1AH (11/01/24) 
Mr Jeremy Moore, Ashfield, Barcaldine (11/01/24) 
Mrs Suzanne Black, 10 Inverbhreach Cottages, Barcaldine, PA37 1AH (13/01/24) 
Mr Gregory Black, 10 Inverbhreach Cottages, Barcaldine, PA37 1AH (12/01/24) 
Ms Sine MacKay, Tigh Sonas, Barcaldine, PA37 1SG (12/01/24)
Mrs Kirsten Leach, 21 Inverbhreach Cottages, Barcaldine, PA37 1AH (12/01/24) 
Mr Andrew Leach, 21 Inverbhreach Cottages, Barcaldine, PA37 1AH (12/01/24) 
Stephanie Brain, 14 Inverbhreach Cottages, Barcaldine, PA37 1AH (11/01/24)
Emily Buchanan, 16 Inverbhreach Cottages, Barcaldine, PA37 1AH (11/01/24) 
Martin George, 9 Inverbhreach Cottages, Barcaldine, PA37 1AH (10/01/24)
Miss Laura Sage, 8 Inverbhreach Cottages, Barcaldine, PA37 1AH (11/01/24)
Mrs Caroline MacInnes, 3 Inverbhreach Cottages, Barcaldine, PA37 1AH (11/01/24)
Christy Walton – by e-mail only – (09/01/24) 
Christine Wood - by e-mail only - (06/01/24) 
Ms Margaret Taylor, 15 Inverbhreach Cottages, Barcaldine, PA37 1AH (05/01/24) 
Representations are published in full on the planning application file and are
available to view via the Public Access section of the Council’s website. 
(ii) Summary of issues raised: 
• Flooding and Surface Water Drainage 
There are ongoing issues with flooding within the surrounding area, with
many of the neighbouring properties often flooded. 
Consideration will require to be given to a suitable drainage scheme for
the proposed development to ensure that the existing situation is not
exacerbated and that existing dwellinghouses are not affected by surface
water flooding arising from the proposed development. 
Concerns over the siting of an open SuDS pond which would have open
access in an area where children regularly play. 
Officer Comment:  The agent has worked closely with the Council’s
flooding advisors JBA Consulting Ltd to agree a suitable scheme for the

Page 4

LDP2 format template March 4th 2024
Report of Handling Template for PPSL and Delegated Planning Applications – Updated 10.11.2023 
treatment of surface water from the proposed development to ensure that
surface water flooding does not arise.  A condition is proposed on the
grant of permission to ensure that the surface water scheme agreed with
JBA Consulting Ltd is implemented within the development. 
With regards to the safety issue of the proposed SuDS Pond, this will be
covered by the appropriate health and safety legislation and appropriate
site management procedures. 
• Road and Access Issues 
The road access from the B845 is too narrow for vehicles to enter and
exit Inverbhreach Cottages at the same time with vehicles requiring to
reverse back into the development or out onto the main road. 
The view when exiting Inverbhreac Cottages is obstructed on both sides,
on the left by a sign and on the right by a pole. 
Due to the lack of visitor parking within the existing development, with
vehicles parked on the street, access for works vehicles is likely to be a
problem.   Approximately 7 visitor parking spaces are required prior to
any work starting on the next phase. 
Will there be street lighting within the proposed development. 
Barcaldine needs a speed restriction. 
Officer Comment:  The agent has worked closely with the Council’s
Roads Authority regarding the access regime to serve the proposed
development.   
The Roads Authority have requested that conditions are imposed on the
grant of permission to secure the upgrade of the existing access at the
junction with the B845 public road involving it being widened to 6 metres,
a 2 metre footway being provided and speed calming measures being
provided within the development.  The condition will require the access
improvements to be provided to at least base course prior to work starting
on the proposed development. 
The other requirements of the Roads Authority, specific to the 6
dwellinghouse development, are discussed in more detail in the main
assessment of the application within Appendix A of this report. 
The Roads Authority has not indicated a requirement for street lighting. 
The reduction in speed limit is a matter for the Roads Authority, it does
not represent a material planning consideration relating to this planning
application. 
• Impact on Wildlife 
Concerns over the impact of the proposed development on wildlife due
to the proximity to an area of Ancient Woodland and the sea.

Page 5

LDP2 format template March 4th 2024
Report of Handling Template for PPSL and Delegated Planning Applications – Updated 10.11.2023 
Officer Comment:  The site is not covered by any specific nature
designation, however, as part of the landscaping scheme for the
development which will be sought by planning condition, details of
biodiversity enhancement and protection measures will be sought. 
• Future Phases of Development 
There are concerns over future phases of development and the potential
impact they could have on the privacy and amenity of existing properties. 
Should permission be granted, does this set a precedent for continued
development, how many properties can be expected to be built. 
Will there be improvements to local infrastructure to support further
development. 
Officer Comment:  The site forms part of Housing Allocation H4017
allocated for the overall development of 50 dwellinghouses.  Phases 1
and 2 have provided 20 of those units with the current application
proposing a further 6. 
Any future application for further development within the Housing
Allocation will require to be assessed against the provisions of the
Development Plan in force at the time along with all other material
considerations, including the requirements of consultees with regards to
suitable infrastructure and comments from third parties with regards to
the impact of the development on their privacy and amenity. 
• Hours of Operation for Construction Works 
Consideration has to be given to the hours and days of work if approved. 
There are many young families leaving for school and work, with children
playing on the street after school and at weekends. 
Officer Comment:  This is not a material planning consideration but a
matter for the developer as part of the good practice for the management
of the construction phase of the development. 
• Is there a guarantee that the planting on the proposed plans will
materialise if permission is granted as this was not done in the previous
phases.  This is considered to be false marketing to prospective
purchasers. 
Officer Comment:  A landscaping condition is proposed on the grant of
permission which requires a timescale for the implementation of the
proposed landscaping together with details of its ongoing maintenance. 
Should the agreed timescale not be adhered to, the Planning Authority
has the ability to commence enforcement action to ensure compliance
with the requirements of the condition. 
• Will there be provision for the maintenance and upkeep of the
proposed public areas.

Page 6

LDP2 format template March 4th 2024
Report of Handling Template for PPSL and Delegated Planning Applications – Updated 10.11.2023 
Officer Comment:  If this forms part of the landscaping condition, then
the powers of the Planning Authority set out above would be relevant. 
• The proposal represents creeping development without any provision or
consideration for the residents of the existing dwellinghouses of Phases
1 and 2. 
Officer Comment: The site is within a Housing Allocation in LDP2
allocated for residential development and Scotland has recently declared
a ‘housing emergency’.   
• Lack of Neighbour Notification 
Not all properties within Inverbhreac Cottages have received neighbour
notification. 
Officer Comment:  Neighbour Notification is issued to those properties
who have a boundary within 20 metres of the red line which delineates
the application site.   
• Issues with the Previous Phases of Development 
Some of the gardens of Inverbhreac Cottages have not been completed
properly, there is no drainage and they are not level resulting in them
being waterlogged for a good part of the year.   
The play area approved in the previous phases has not been provided
resulting in children playing in the street, representing a road and
pedestrian safety issue. 
The planting and landscaping has not been completed. 
There are ongoing issues with the operation of the septic tanks serving
the dwellinghouses within the previous phases.   
There has been sewage in one of the driveways due to this issue and
ongoing odour issues. 
SEPA or Environmental Health should investigate the installation of these
existing septic tanks before any further septic tanks are installed or
building works start as this poses a rise to the health and safety of
residents. 
This is the third planning application for Phase 3, would it not be
advisable for the developer to meet with the existing residents to resolve
the issues with the previous phases before the next phase starts. 
Officer Comment:  If the development has not been undertaken in
accordance with the approved plans, this is something which can be
investigated by the Planning Enforcement Officer. 
With regards to the operational arrangements of the existing septic tanks,
this is not a matter for the Planning Authority, this is a matter for the
developer and/or the Council’s Building Standards Service.

Page 7

LDP2 format template March 4th 2024
Report of Handling Template for PPSL and Delegated Planning Applications – Updated 10.11.2023 
With regards to the treatment of surface water within the development,
again this would be a matter for the developer and/or the Council’s
Building Standards Service. 
(G) SUPPORTING INFORMATION 
Has the application been the subject of: 
(i) Environmental Impact Assessment Report: ☐Yes ☒No 
(ii) An Appropriate Assessment under the
Conservation (Natural Habitats) Regulations
1994:   
☐Yes ☒No 
(iii) A Design or Design/Access statement:    ☒Yes ☐No 
A Supporting Statement
has been submitted with
the application the
content of which is
discussed in the main
assessment of the
application within
Appendix A of this report. 
(iv) Sustainability Checklists (with reference to the requirements of LDP2
Policy 04) 
TN06 Sustainability Checklist
TN07 Sustainable Buildings Checklist
☒Yes ☐No
☒Yes ☐No  
(v) A report on the impact of the proposed
development e.g. Retail impact, transport
impact, noise impact, flood risk, drainage
impact etc:  
☒Yes ☐No 
Flood Risk Assessment
which is discussed in
more detail in the main
assessment of the
application within
Appendix A. 
(H) PLANNING OBLIGATIONS 
Is a Section 75 agreement required:   ☐Yes ☒No 
(I) Has a Direction been issued by Scottish Ministers in terms of Regulation 30,
31 or 32:  ☐Yes ☒No

Page 8

LDP2 format template March 4th 2024
Report of Handling Template for PPSL and Delegated Planning Applications – Updated 10.11.2023 
(J) Section 25 of the Act; Development Plan and any other material considerations
over and above those listed above which have been taken into account in the
assessment of the application 
(i)  List of all Development Plan Policy considerations taken into account
in assessment of the application. 
National Planning Framework 4 (Adopted 13th February 2023) 
Part 2 – National Planning Policy 
Sustainable Places
NPF4 Policy 1 – Tackling the Climate and Nature Crises
NPF4 Policy 2 – Climate Mitigation and Adaption
NPF4 Policy 3 – Biodiversity
NPF4 Policy 4 – Natural Places
NPF4 Policy 9 – Brownfield, Vacant and Derelict Land and Empty Buildings (includes
provisions relevant to Greenfield Sites)
NPF4 Policy 11 – Energy
NPF4 Policy 12 – Zero Waste
NPF4 Policy 13 – Sustainable Transport 
Liveable Places
NPF4 Policy 14 – Design, Quality and Place
NPF4 Policy 15 – Local Living and 20 Minute Neighbourhoods
NPF4 Policy 16 – Quality Homes
NPF4 Policy 17 – Rural Homes
NPF4 Policy 18 – Infrastructure First
NPF4 Policy 22 – Flood Risk and Water Management 
Argyll and Bute Local Development Plan 2 (Adopted 2024) 
Spatial and Settlement Strategy 
Policy 01 – Settlement Areas
Policy 04 – Sustainable Development 
High Quality Places 
Policy 05 – Design and Placemaking
Policy 06 – Green Infrastructure
Policy 08 – Sustainable Siting
Policy 09 – Sustainable Design
Policy 10 – Design – All Development 
Diverse and Sustainable Economy 
Policy 30 – The Sustainable Growth of Renewables 
Connected Places 
Policy 34 – Electric Vehicle Charging
Policy 36 – New Private Accesses
Policy 37 – Development Utilising an Existing Private Access or Existing Private
Road

Page 9

LDP2 format template March 4th 2024
Report of Handling Template for PPSL and Delegated Planning Applications – Updated 10.11.2023 
Policy 39 – Construction Standards for Private Accesses
Policy 40 – Vehicle Parking Provision
Policy 41 – Off Site Highway Improvements 
Sustainable Communities 
Policy 55 – Flooding
Policy 58 – Private Water Supplies and Water Conservation
Policy 60 – Private Sewage Treatment Plants and Wastewater Drainage Systems
Policy 61 – Sustainable Urban Drainage Systems (SUDS)
Policy 63 – Waste Related Development and Waste Management 
Homes for People 
Policy 64 – Housing Development on Allocated Sites
Policy 67 – Provision of Housing to Meet Local Needs Including Affordable Housing 
High Quality Environment 
Policy 71 – Development Impact on Local Landscape Areas (LLA’s)
Policy 73 – Development Impact on Habitats, Species and Biodiversity 
(ii)  List of all other material planning considerations taken into account in
the assessment of the application, having due regard to Annex A of
Circular 3/2013. 
• Third Party Representations
• Consultation Reponses
• Planning History
• ABC Technical Note – Biodiversity (Feb 2017)
• TN06 Sustainability Technical Note and Checklist (Oct. 2023)
• TN07 Sustainable Buildings Technical Note and Checklist (Oct. 2023)
• ABC Housing Needs and Demand Assessment
• ABC Housing Emergency Statement 
(K) Is the proposal a Schedule 2 Development not requiring an Environmental
Impact Assessment:  ☐Yes ☒No 
(L) Has the application been the subject of statutory pre-application consultation
(PAC):  ☐Yes ☒No 
(M) Does the Council have an interest in the site:  ☐Yes ☒No 
(N) Requirement for a pre-determination hearing: ☐Yes ☒No 
In deciding whether to hold a discretionary hearing Members should consider:  
• How up to date the Development Plan is, the relevance of the policies to the
proposed development, and whether the representations are on development

Page 10

LDP2 format template March 4th 2024
Report of Handling Template for PPSL and Delegated Planning Applications – Updated 10.11.2023 
plan policy grounds which have recently been considered through the
development plan process. 
• The degree of local interest and controversy on material considerations, together
with the relative size of community affected, set against the relative number of
representations and their provenance. 
At the time of writing, representations have been received by the Planning Authority
from 19 respondents in relation to this planning application. 18 respondents raise
objection and 1 submits a representation. 
The main thrust of objection relate to the unsuitability of the junction with the public
road and the ongoing issues with surface water flooding.  In this regard the agent
has worked closely with the Council’s Roads Authority to agree an upgrade of the
access at the junction with the public road which involves an increase in its width
and the provision of a pedestrian footway, works on which will require to be
undertaken before works on the construction of the dwellinghouses commences.   
The agent has also worked closely with the Council’s flooding advisors JBA
Consulting Ltd to agree a suitable scheme for the treatment of surface water within
the proposed development. 
The main other concerns raised by objectors relate to the standard of completion of
the previous phases of the development and ongoing issue they are having with the
developer. 
It is the opinion of the Planning Authority that the representations received, together
with officer assessment of the relevant planning issues contained within this report,
provide all the information required to enable Members to make an informed
decision based on all of the material planning considerations in this case. 
In this instance it is not considered that the objections raise any complex or technical
issues that have not been addressed in the current Report of Handling and it is not
considered that a discretionary local hearing would add value to the planning
process. 
The determining factor in the assessment of this application is whether the proposed
small scale housing development is consistent with the provisions of the adopted
National Planning Framework 4 and Local Development Plan 2 and whether the
issues raised by third parties raise material considerations of sufficient significance
to withhold planning permission. 
In this instance the proposed housing development is within an area recently
adopted as a housing allocation within LDP2 and is considered to be wholly
consistent with that allocation and with the provisions of both National and Local
Planning Policy whilst helping to address the locally and nationally declared ‘housing
emergency’.    
(O)(i) Key Constraints/Designations Affected by the Development: 
• North Argyll LLA 
• H4017 – Barcaldine – 50 Units

Page 11

LDP2 format template March 4th 2024
Report of Handling Template for PPSL and Delegated Planning Applications – Updated 10.11.2023 
(O)(ii) Soils
Agricultural Land Classification:  Class 4.2 - Land capable of producing a
narrow range of crops, primarily on
grassland with short arable breaks of
forage crops. 
Class 5.2 - Land capable of use as
improved grassland. Few problems with
pasture establishment but may be difficult
to maintain.
Peatland/Carbon Rich Soils Classification: ☐Class 1
☐Class 2
☐Class 3
☒N/A
Peat Depth Classification: N/A  
Does the development relate to croft land? ☐Yes ☒No
Would the development restrict access to croft
or better quality agricultural land?
☐Yes ☐No ☒N/A
Would the development result in
fragmentation of croft / better quality
agricultural land?
☐Yes ☐No ☒N/A 
(O)(iii) Woodland  
Will the proposal result in loss of
trees/woodland?
(If yes, detail in summary assessment)
☐Yes
☒No 
Does the proposal include any replacement or
compensatory planting?
☐Yes
☐No details to be secured by condition
☒N/A  
(O)(iv) Land Status / LDP Settlement Strategy
Status of Land within the Application
(tick all relevant boxes)
☐Brownfield
☐Brownfield Reclaimed by Nature
☒Greenfield 
ABC LDP2 Settlement Strategy
(tick all relevant boxes) 
☒Settlement Area
☐Countryside Area
☐Remote Countryside Area
☐Helensburgh & Lomond Greenbelt
ABC LDP2 Allocations/PDAs/AFAs etc: 
H4017 – Barcaldine – 50 Units 
Short/Medium term timescale with 50%
affordable requirement 
(P) Summary assessment and summary of determining issues and material
considerations 
The proposal the subject of this application is seeking to secure planning permission
for the erection of 6 dwellinghouses, the formation of a private access track and the
installation of 2 septic tanks and soakaways.

Page 12

LDP2 format template March 4th 2024
Report of Handling Template for PPSL and Delegated Planning Applications – Updated 10.11.2023 
The principle of residential development on this site has been established by the
adopted LDP2 which identifies the site as a Housing Allocation (H4017) allocated for
development with 50 units with a 25% affordability requirement. 
The proposed dwellinghouses comprise two storey, pitched roof structures finished
in a mixture of white render and horizontal weatherboard cladding to the walls with
grey upvc doors and windows and a grey concrete roof tile, the design and finishes
of which are similar to those within the adjacent completed development of Phase 2. 
The dwellinghouses are situated within spacious plots, arranged adjacent to the
proposed private access track which will serve them which is taken from the
proposed future adoptable road that runs through Inverbhreac Cottages (Phase 2). 
Three of the dwellinghouses are accessed via one spur off and the remaining three
served by another spur. 
The proposed private access provides an access point into the future phase of the
housing allocation. 
Water supply is via connection to the public water main with drainage via the
installation of two septic tanks. 
At the time of writing, representations had been received by the Planning Authority
from 19 respondents in relation to this planning application. 18 respondents raise
objection and 1 provides a representation. 
The proposed small scale housing development is considered to be consistent with
the provisions of the adopted National Planning Framework 4 and Local
Development Plan 2 with the issues raised by third parties not considered to raise
material considerations of sufficient significance to withhold planning permission. 
Taking account of the above, it is recommended that planning permission be
approved subject to conditions.   
A full report is provided in Appendix A. 
(Q) Is the proposal consistent with the Development Plan: ☒Yes ☐No 
(R) Reasons why Planning Permission Should be Granted: 
The proposal is considered to be consistent with the relevant provisions of
the Development Plan and there are no other material considerations of
sufficient significance, including issues raised by third parties, to indicate that
it would be appropriate to withhold planning permission having regard to
Section 25 of the Act. 
(S) Reasoned justification for a departure to the provisions of the Development
Plan 
N/A

Page 13

LDP2 format template March 4th 2024
Report of Handling Template for PPSL and Delegated Planning Applications – Updated 10.11.2023 
(T) Need for notification to Scottish Ministers or Historic Environment Scotland:
☐Yes ☒No 
Author of Report: Fiona Scott   Date: 29/05/24 
Reviewing Officer: Tim Williams Date: 04/06/24 
Fergus Murray
Head of Development & Economic Growth

Page 14

LDP2 format template March 4th 2024
Report of Handling Template for PPSL and Delegated Planning Applications – Updated 10.11.2023 
CONDITIONS AND REASONS RELATIVE TO APPLICATION REF. NO. 23/02409/PP 
Standard Time Limit Condition  (as defined by Regulation) 
Standard Condition on Soil Management During Construction 
Additional Conditions  
1. PP - Approved Details & Standard Notes – Non EIA Development 
The development shall be implemented in accordance with the details specified on the
application form dated 15/12/23, supporting information and, the approved drawings
listed in the table below unless the prior written approval of the planning authority is
obtained for an amendment to the approved details under Section 64 of the Town and
Country Planning (Scotland) Act 1997. 
Plan Title. Plan Ref. No. Version Date Received
Pre-Development Surface Water Run
Off Layout 
0460-C-0004 P01  08/04/24 
Post-Development Surface Water
Run Off Layout 
0460-C-0005 P01 08/04/24 
Proposed Below Ground Drainage
Layout 
0460-C-0032 P03  08/05/24 
Location Plan  5021-02-301 B 19/12/23 
Site Plan  5021-02-302 B 19/12/23 
GF Plan HT01  5021-03-301 B 19/12/23 
GF Plan HT01H 5021-03-301H B 19/12/23 
FF Plan HT01  5021-03-302  B  19/12/23 
FF Plan HT01 Handed  5021-03-302H B 19/12/23 
GF Plan HT03  5021-03-305  B 19/12/23 
GF Plan HT03 Handed  5021-03-305H B 19/12/23
FF Plan HT03  5021-03-306  B  19/12/23 
FF Plan HT03 Handed  5021-03-306H B 19/12/23 
Elevations HT01  5021-04-301 B 19/12/23 
Elevations HT01 Handed  5021-04-301H B 19/12/23 
Colour Options HT01  5021-04-302 B 19/12/23 
Elevations HT03  5021-04-305 B 19/12/23 
Elevations HT03 Handed  5021-04-305H B 19/12/23 
Colour Options HT03  5021-04-306  B 19/12/23
Site Sections 01  5021-05-301 B 19/12/23 
Site Sections 02  5021-05-302  B  19/12/23 
Drainage, SUDS and Surface Water
Management Plan – 49 Pages 
21/03/24 
Flood Risk Assessment – 39 Pages   12/02/24 
Greenfield Run Off    08/04/24 
Percolation Tests – 4 Pages    08/05/24 
Supporting Statement – 15 Pages    18/12/23 
Surface Water Network (Land
Drainage) – 13 Pages  
08/04/24 
Surface Water Network (Soakaway) –
5 Pages  
08/04/24

Page 15

LDP2 format template March 4th 2024
Report of Handling Template for PPSL and Delegated Planning Applications – Updated 10.11.2023 
TN06 – Sustainability Checklist – 7
Pages 
18/12/23 
TN07 – Sustainable Buildings
Checklist – 4 Pages 
18/12/23 
Reason: For the purpose of clarity, to ensure that the development is implemented in
accordance with the approved details. 
Note to Applicant 
Regard should be had to Scottish Water and the Oban and District Access Panel
comments in relation to the proposed development, details of which are available to
view via the Public Access section of the Council’s website.  
2. PP – Vehicular Access 
No development shall commence until plans and particulars of the means of vehicular
access to serve the development have been submitted to and approved by the
Planning Authority in consultation with the Roads Authority. Such details shall
incorporate:   
i) Upgrade of the existing access at its junction with the B845 comprising a kerb
radius of 6 metres and provision of a 2 metre footway at the north west side of
the access road; 
ii) Visibility splays measuring 2.4 metres to point X by 75 metres to point Y from
the centre line of the junction; 
iii) Details of speed calming measures (speed cushions) within the development
road at locations to be agreed with the Roads Authority;
iv) Details of a passing place approximately midway on the private access road
serving Plots 3-04, 3-05 and 3-06;
v) Details of a 2 metre level service strip for pedestrian refuge along the extent of
the new private access roads;
vi) Details of a turning head to Figure 18 of The National Development Guide at
the end of the private access road serving Plots 3-04, 3-05  and 3-06;
vii) Details of a bin storage area at a point next to the private access road serving
Plots 3-01 and 3-02. 
Prior to work starting on site, the approved scheme of works in respect of junction
upgrade shall be formed to at least base course standard and the visibility splays shall
be cleared of all obstructions such that nothing shall disrupt visibility from a point 1.05
metres above the junction at point X to a point 0.6 metres above the public road
carriageway at point Y. The final wearing surface on the access shall be completed
prior to the development first being brought into use and the visibility splays shall be
maintained clear of all obstructions thereafter. 
The approved speed calming measures, passing place, service strips, turning head
and bin storage area shall be implemented in full prior to the development first being
occupied to the satisfaction of the Roads Authority. 
Reason: In the interests of road safety. 
Note to Applicant

Page 16

LDP2 format template March 4th 2024
Report of Handling Template for PPSL and Delegated Planning Applications – Updated 10.11.2023 
• A Road Opening Permit under the Roads (Scotland) Act 1984 must be obtained
from the Council’s Roads Engineers prior to the formation/alteration of a junction
with the public road. 
• The access shall be constructed and drained to ensure that no surface water is
discharged onto the public road. 
• No walls, fences, hedges etc. will be permitted within 2 metres from the channel line
of the public road. 
3. PP  - Sustainable Drainage System 
The surface water drainage system for the development shall be undertaken in
accordance with the Drainage, Suds and Surface Water Management Plan dated
March 2024 and the associated drawings set out in Condition 1 above and shall be
operational before the first occupation of the first dwellinghouse to be completed.   
Note to Applicant: 
Regard should be had to the consultation comments from JBA Consulting Ltd in
relation to the proposed development, details of which are available to view via the
Public Access section of the Council’s website.  
4. PP – Landscaping Scheme and Biodiversity Enhancement Measures 
No development shall commence until a scheme of boundary treatment, surface
treatment and landscaping has been submitted to and approved in writing by the
Planning Authority. The scheme shall comprise a planting plan and schedule which
shall include details of: 
i) Existing and proposed ground levels in relation to an identified fixed datum;
ii) Existing landscaping features and vegetation to be retained;
iii) Location design and materials of proposed walls, fences and gates;
iv) Proposed soft and hard landscaping works including the location, species
and size of every tree/shrub to be planted;
v) A programme for the timing, method of implementation, completion and
subsequent on-going maintenance;
vi) A biodiversity statement demonstrating how the proposal will contribute to
conservation/restoration/enhancement of biodiversity, and how these
benefits will be maintained for the lifetime of the development. 
All of the hard and soft landscaping works shall be carried out in accordance with the
approved scheme unless otherwise approved in writing by the Planning Authority. 
Any trees/shrubs which within a period of five years from the completion of the
approved landscaping scheme fail to become established, die, become seriously
diseased, or are removed or damaged shall be replaced in the following planting
season with equivalent numbers, sizes and species as those originally required to be
planted unless otherwise approved in writing by the Planning Authority. 
All physical biodiversity enhancement measures (bird nesting boxes, ‘swift bricks’,
wildlife ponds, bat and insect boxes, hedgehog homes etc.) shall be implemented in
full before the development hereby approved is first brought into use.

Page 17

LDP2 format template March 4th 2024
Report of Handling Template for PPSL and Delegated Planning Applications – Updated 10.11.2023 
All biodiversity enhancement measures consisting of new or enhanced planting shall
be undertaken either in accordance with the approved scheme of implementation or
within the next available planting season following the development first being brought
into use. 
The biodiversity statement should refer to Developing with Nature guidance |
NatureScot as appropriate. 
Reason: To assist with the integration of the proposal with its surroundings in the
interest of amenity and in order to comply with the requirements of NPF4 Policy 3. 
5. PP – Finishing Materials 
Notwithstanding the effect of Condition 1, no development shall commence until
written details of the proposed external finishing materials to be used in the
construction of the proposed dwellinghouses have been submitted to and approved in
writing by the Planning Authority. The development shall thereafter be completed
using the approved materials or such alternatives as may be agreed in writing with the
Planning Authority. 
Reason: In order to integrate the development into its surroundings.  
6. PP - Electric Vehicle Charging – Residential with off street parking 
Prior to the commencement of the development (or such other timescale as may be
agreed in writing with the Planning Authority), a scheme detailing the provision of a
minimum 7kw electric vehicle charging point shall be submitted to and approved in
writing by the Planning Authority. Where charging cannot be provided then the
appropriate ducting to future proof the property must be installed.  
The approved charging point, or where relevant, the approved cable ducting shall be
installed in full prior to the first occupation of the development, and thereafter retained
in perpetuity unless otherwise agreed in writing by the planning authority  
Reason: to comply with the provisions of NPF4 Policy 13 Sustainable Transport and
LDP2 Policy 34 – Electric Vehicle Charging.

Page 18

LDP2 format template March 4th 2024
Report of Handling Template for PPSL and Delegated Planning Applications – Updated 10.11.2023 
COMMITTEE REPORT
APPENDIX A – RELATIVE TO APPLICATION NUMBER:  23/02409/PP 
PLANNING LAND USE AND POLICY ASSESSMENT 
1. Introduction 
1.1. The proposal the subject of this application is seeking to secure planning permission for
the erection of 6 dwellinghouses, the formation of a private access track and the
installation of 2 septic tanks and soakaways. 
2. Settlement Strategy 
2.1. The principle of residential development on this site has been established by the adopted
LDP2 which identifies the site as a Housing Allocation (H4017) allocated for development
with 50 units with a 25% affordability requirement. 
In order to address the determining issues, the key considerations in this application are: 
2.1.1. Compliance with the Development Plan and other relevant planning policy
2.1.2. Any other material considerations. 
3. Application Site 
3.1. The site is a relatively flat area of rough grazing ground which extends to just under 0.6
hectares in size.   
The site lies to the south of Phases 1 and 2 of the existing development which were
developed under the provisions of the previous LDP as Housing Allocation (HA) 5/19 
Phase 1 comprised 10 affordable units with Phase 2 comprising 10 mainstream units, all
of which are completed and occupied. 
At the time when the current application was submitted and validated, the site formed part
of HA 5/19 with the proposal effectively completing the development within the HA. 
However, LDP2 has now been adopted and has merged former HA 5/19 (27 units) and
adjacent PDA 5/105 (low density housing) to form Housing Allocation H4017 for the
development of 50 units with a 25% affordable requirement. 
The Supporting Statement submitted with the application details that it is the applicant’s
intention is to phase the development of the remainder of H4017 with the proposal the
subject of the current application representing Phase 3 with the application showing an
area for the future development of Phase 4.   
In respect of the affordability component of the development and its context within the
wider Housing Allocation and the planning history of the site, it is noted that the current
planning application was submitted before the adoption of LDP2 at a time when the
total required provision of affordable units was 7.  The existing and built Phase 1 and
Phase 2 provided 10 affordable units, an over-provision of 3.  During the determination
period of the current application, however, the new LDP2 now requires a total
affordability component of 25%.  The current application proposes 6 new units, none
of them affordable.  The previous Phase 1 and Phase 2 permissions provided 20 units

Page 19

LDP2 format template March 4th 2024
Report of Handling Template for PPSL and Delegated Planning Applications – Updated 10.11.2023 
in total which, added to the 6 units the subject of the current application gives an
affordability requirement of just over 6 units (25% of 26 = 6.5). Therefore the existing
affordability provision of 10 units is still above the current requirement of 25% although
it is accepted that this is a pro-rata calculation and that any future additional
development within the housing allocation may require the provision of further
affordable units, with a potential need for three additional affordable dwellings should
the total capacity of the housing allocation (50 units) be reached. 
4. Proposed Development 
4.1 The application is seeking to secure permission for 6 detached dwellinghouses which
comprise two different but very similar designs comprising two storey, pitched roof
structures finished in a mixture of white render and horizontal weatherboard cladding to
the walls with grey upvc doors and windows and a grey concrete roof tile. 
The design and finishing materials of the proposed dwellinghouses are very similar to
those within the adjacent completed development of Phase 2. 
The dwellinghouses are situated within spacious plots, arranged adjacent to the proposed
private access track which will serve them which is taken from the proposed future
adoptable road that runs through Inverbhreac Cottages (Phase 2).  Three of the
dwellinghouses are accessed via one spur off and the remaining three served by another
spur. 
The proposed private road provides an access point into the future phase of the housing
allocation. 
Whilst the site plan shows area of landscaping within the site, the finer details of the
proposed landscaping, boundary treatment and biodiversity enhancement measures
within the development will be sought by planning condition with such details requiring to
be submitted and agreed with the Planning Authority prior to works starting on site. 
5. Compliance with National and Local Development Plan 2 Policy 
Argyll and Bute ‘Local Development Plan 2’ (LDP2) was adopted on 28 February 2024
which, together with NPF4 which was adopted on 13 February 2023, represent the
Development Plan providing the policy background against which proposed developments
are assessed. 
The proposal is assessed against the relevant NPF4 Policies below which include details
of the associated LDP2 policies. 
5.1. NPF4 Policy 1 – Tackling the Climate and Nature Crises 
NPF4 Policy 1 seeks to prioritise the climate and nature crises in all decisions; it requires
to be applied together with other policies in NPF4. 
Guidance from the Scottish Government advises that it is for the decision maker to
determine whether the significant weight to be applied tips the balance in favour for, or
against a proposal on the basis of its positive or negative contribution to climate and
nature crises.   
5.2. NPF4 Policy 2 – Climate, Mitigation and Adaption

Page 20

LDP2 format template March 4th 2024
Report of Handling Template for PPSL and Delegated Planning Applications – Updated 10.11.2023 
NPF4 Policy 2 seeks to ensure that new development proposals will be sited to minimise
lifecycle greenhouse gas emissions as far as possible, and that proposals will be sited
and designed to adapt to current and future risks from climate change. 
Guidance from the Scottish Government confirms that at present there is no single
accepted methodology for calculating and / or minimising emissions. The emphasis is on
minimising emissions as far as possible, rather than eliminating emissions. The Spatial
Settlement Strategy set out within LDP2  seeks to deliver sustainable levels of growth by
steering the majority of development to our existing settlements as these are where the
most of our current infrastructure, services, employment opportunities, housing and
community facilities are to be found, however LDP2 recognises that there are instances
where a different approach to significant development has to be taken particularly where
existing infrastructure or services are at capacity and where a more sustainable option
would be to provide new facilities elsewhere. 
5.3. NPF4 Policy 3 – Biodiversity 
NPF4 Policy 3 seeks to protect biodiversity, reverse biodiversity loss and deliver positive
effects from development and strengthen nature networks. 
With regards to the need in NPF4 Policy 3 to secure biodiversity improvements, it is not
considered that there are any issues of compliance with Policy 3.  Whilst the Supporting
Statement details that habitat improvements have been incorporated into the site design
including the provision of native species planting, swift boxes and a SUDS pond area, it
is considered appropriate to impose a condition on the grant of permission to secure the
finer detail of these proposals as part of the wider landscaping and boundary treatment
measures for the site. 
With a condition to secure the finer details of the biodiversity enhancement and
protection measures within the development, as part of the wider landscaping and
boundary scheme for the site, the proposal aligns with the broad aims of NPF4
Policy 3 and is consistent with the requirements of LDP2  Policy 73, Development
Impact on Habitats, Species and Biodiversity. 
5.4. NPF4 Policy 4 – Natural Places 
NPF4 Policy 4 seeks to protect, restore and enhance natural assets making best use of
nature-based solutions. 
The development proposed by the current planning application is considered appropriate
in terms of its type, location and scale such that it will have no unacceptable impact on
the natural environment. The proposed development is not within any designated
European site of natural environment conservation or protection, it is not located within a
National Park, a National Scenic Area a SSSI or RAMSAR site, or a National Nature
Reserve. Neither is it located within a site designated as a local nature conservation site
or within an area identified as wild land.   
Whilst the site is located within the North Argyll LLA, the application proposes a small
scale residential development, within an area identified for housing development in LDP2,
where it will be viewed in the context of an area of existing housing development, therefore
it is the considered opinion of the Planning Authority that the proposal will not result in
any significant adverse effects on the integrity of the area or the qualities for which it has
been identified.

Page 21

LDP2 format template March 4th 2024
Report of Handling Template for PPSL and Delegated Planning Applications – Updated 10.11.2023 
The proposed development is considered to be consistent with NPF4 Policy 4 and
does not conflict LDP2 Policy 71, Development Impact on Local Landscape Areas.   
5.5. NPF4 Policy 9 – Brownfield, Vacant and Derelict Land and Empty Buildings 
NPF4 Policy 9 seeks to encourage, promote and facilitate the reuse of brownfield, vacant
and derelict land and empty buildings, and to help reduce the need for greenfield
development. 
Part (b) of Policy 9 states that proposals on greenfield sites will not be supported unless
the site has been allocated for development or the proposal is explicitly supported by
policies in the LDP.   
The site has been allocated as Housing Allocation H4017 in LDP2 and therefore
there is no conflict between NPF4 Policy 9 and the settlement strategy set out in
LDP2. 
5.6. NPF4 Policy 11 – Energy 
NPF4 Policy 11 seeks to encourage, promote and facilitate all forms of renewable energy
development, including energy generation, storage, and new and replacement
transmission and distribution infrastructure. 
NPF4 Policy 11(a) states that development proposals for all forms of renewable, low-
carbon and zero emissions technologies will be supported. The proposed development,
through the provision of air source heat pumps to the rear of the dwellinghouses, would
contribute to the expansion of low-carbon and zero emission technologies. 
The proposed development is supported by NPF4 Policy 11 and there is no conflict
with LDP2 Policy 09, Sustainable Design, which seeks proposed developments to
consider renewable sources of energy. 
5.7. NPF4 Policy 12 – Zero Waste 
NPF4 Policy 12 seeks to encourage, promote and facilitate development that is consistent
with the waste hierarchy as defined within the policy document. 
The development the subject of this planning application seeks to secure permission for
6 dwellinghouses.  Whilst this is a development likely to generate waste when operational,
it will already benefit from regular waste uplifts by the Council and will be expected to
comply with our adopted and enforced recycling and reuse strategy.  The application
shows an area within the grounds of each dwellinghouse for the placement of refuse bins
with the Roads Authority seeking to secure an area adjacent to the proposed private
access track for the placement of these bins for uplift by the Council’s Refuse Collection
Vehicle. 
The proposed development is considered to be in compliance with NPF4 Policy 12
and does not conflict with the requirements of LDP2 Policy 63, Waste Related
Development and Waste Management which seek to ensure that effective provision
for waste/recycling is provided within developments and the current proposal
would raise no issue of conflict should permission be granted. 
5.8. NPF4 Policy 13 – Sustainable Transport

Page 22

LDP2 format template March 4th 2024
Report of Handling Template for PPSL and Delegated Planning Applications – Updated 10.11.2023 
NPF4 Policy 13 seeks to encourage, promote and facilitate developments that prioritise
walking, wheeling, cycling and public transport for everyday travel and reduce the need
to travel unsustainably. 
The development is not considered to be a significant travel generating use or a proposal
where it is considered important to monitor travel patterns resulting from the development. 
A new private access is proposed into the site from the future adoptable road spurring
from the B845 public road which runs through Inverbhreac Cottages (Phase 2).  Three of
the dwellinghouses are to be accessed via one spur off of the new private access track
with the remaining three served by a further spur.   
The proposed private access provides an access point into the future phase of the
housing allocation. 
The Supporting Statement submitted with the application details that the application site
is readily accessible with links to existing path and public road networks, the existing
public bus network and National Cycle Network Route 78 thereby providing suitable
vehicular and pedestrian connectivity to the wider network and existing community. 
The applicant has worked closely with the Roads Authority to agree the proposed access
regime to serve the development which includes an upgrade of the existing access point
at the junction with the B845 public road and the provision of a 2 metre wide footway; the
provision of speed calming measures along the extent of the internal road spurring from
the junction with the B845; the provision of a passing place along the new private access
track; the provision of a 2 metre level service strip to provide pedestrian refuge along the
new private access track; the provision of a turning head within the new private access
track; and the provision of a bin storage area adjacent to the new private access track. 
The Roads Authority also sought a condition to secure three parking spaces for each
dwellinghouse, however as this is shown on the site plan there is no need for such a
condition.   
With conditions to secure the requirements of the Roads Authority the proposed
development is considered to be consistent with the broad aims of NPF4 Policy 13
and is consistent with the requirements of LDP2 Policies 36 , New Private
Accesses, Policy 37, Development Utilising an Existing Private Access or Existing
Private Road, Policy 39, Construction Standards for Private Accesses, Policy 40,
Vehicle Parking Provision and Policy 41, Off Site Highway Improvements which
collectively seek to ensure that proposed developments are served by a suitable
and safe access regime and provide appropriate parking provision commensurate
with the scale of the development proposed and the current proposal would raise
no issue of conflict should permission be granted. 
5.9. NPF4 Policy 14 – Design, Quality and Place 
NPF4 Policy 14 seeks to encourage, promote and facilitate well designed development
that makes successful places by taking a design-led approach and applying the ‘Place
Principle’. 
NPF4 Policy 14(a) details that development proposals should be designed to improve the
quality of an area whether in urban or rural locations, regardless of scale with Part (b)
affording support to developments where they are consistent with the six qualities of
successful places: Healthy, Pleasant, Connected, Distinctive, Sustainable and Adaptable.

Page 23

LDP2 format template March 4th 2024
Report of Handling Template for PPSL and Delegated Planning Applications – Updated 10.11.2023 
A statement addressing the six qualities of place has been submitted with the application
as follows. 
“Healthy - Pedestrian routes provide for overlooking by neighbouring properties,
providing a sense of community and supporting women’s safety. With links to National
Cycle Network Route 78 the proposals support improving physical health and the
associated benefits to mental health. Enhanced natural features on site and within the
local area support the mental health of the surrounding community. 
Pleasant - The overall layout for the proposed development has been designed to
respond to the existing site constraints and surrounding context including a robust
landscape strategy which will ensure the proposals sit well within the existing area. The
development retains key landscape features following the natural contours of the site.
Existing neighbouring woodland to the Southern border and a backdrop of significant hills
and munros creates an attractive setting for the proposals. 
Connected - The site is placed within walking distance of local primary education
facilities, community facilities, local public transport links and National Cycle Network
Route 78. The layout will be clear and easy to navigate around and will provide excellent
pedestrian connectivity to the wider network and existing community. 
Distinctive - To take advantage of this setting, high quality house design is proposed with
the low housing density consistent with the neighbouring properties. Dwellings within a
more generous plot size are considered to be more appropriate for this setting and will
allow for a more sympathetic approach when considering the integration of housing in this
area. Additional structured landscaping and woodland planting is proposed to the edge of
the site to ensure the proposed development is well integrated into the landscape
reinforcing the links with the surrounding countryside. 
Adaptable - The applicant is committed to providing dwellings designed to be flexible
through incorporation of the lifetime homes standard as defined within Section three of
the Scottish Building Regulations. This standard is a series of design criteria intended to
make homes more easily adaptable for lifetime use at minimal cost. The concept was
initially developed by the Joseph Rowntree Foundation. The dwellings shall be fully
accessible to wheelchair users and ambulant disabled persons. 
Sustainable - The site has been designed to accommodate six low energy family homes.
By building to this standard this will ensure that the buildings are climatically resilient. 
For any development to be sustainable, it needs to create a sense of place and
community. A development is required to provide a socially inclusive, attractive
environment which meets the current needs of the residents. The development is also
required to be adaptable to social and economic change while still meeting the long term
needs of the residents. 
In order to achieve this, the site layout needs to include; access to greenspace, access
to surrounding community services and facilities and be an environment conducive to
bringing people together. The location of the site lies within the settlement boundaries of
the settlement of Barcaldine, the pedestrian linkages and the close proximity of the site
to open spaces, local business, and the Primary School are considered critical in
achieving these aims”. 
The development the subject of this planning application is considered to be in
accordance with the broad aims of NPF4 Policy 14 and the sustainable siting and
design policies of LDP2 namely Policy 5, Design and Placemaking, Policy 08,

Page 24

LDP2 format template March 4th 2024
Report of Handling Template for PPSL and Delegated Planning Applications – Updated 10.11.2023 
Sustainable Siting, Policy 09, Sustainable Design and Policy 10, Design: All
Development which, in summary, collectively seek to ensure that developments are
compatible with surrounding land uses, are sited sensitively within the landscape
making use of existing infrastructure, are of an appropriate scale, sustainable
design and finishes for their site; and ensure that no adverse visual or amenity
impacts arise. 
5.10. NPF4 Policy 15 – Local Living and 20 Minute Neighbourhoods 
NPF4 Policy 15(a) seeks development proposals to contribute to local living including,
where relevant, 20 minute neighbourhoods. To establish this, consideration will be given
to existing settlement pattern, and the level and quality of interconnectivity of the proposed
development with the surrounding area, including local access to a number of facilities. 
The LDP2 settlement strategy seeks to deliver sustainable levels of growth by steering
the majority of development to our existing settlements where the most of our current
infrastructure, services, employment opportunities, housing and community facilities are
to be found and thereby making best use of these resources is a sustainable approach to
development. 
In this instance, the site, by virtue of being allocated as Housing Allocation H4017, would
reasonably comply with NPF4 Policy 15 given the scale of the environment within which
the development is to be located, and given its compliance with the existing settlement
pattern and the level and quality of interconnectivity of the proposed development with
the surrounding area where people can reasonably meet the majority of their daily needs
within a reasonable distance of their home. 
The proposed development aligns with NPF4 Policy 15 and there is no conflict with
LDP2 Policy 01, Settlement Areas and the current proposal would raise no issue of
conflict should permission be granted. 
5.11. NPF4 Policy 16 – Quality Homes 
NPF4 Policy 16 seeks to encourage, promote and facilitate the delivery of more high
quality, affordable and sustainable homes in the right locations and providing choice of
tenure to meet diverse housing needs. 
Policy 16(a) supports development proposals for new homes on land allocated for
housing in LDPs.  The site of the proposed residential development is within Housing
Allocation H4017, allocated within LDP2 for residential development. 
Policy 16(e) supports proposals for new homes where they make provision for affordable
homes to meet an identified need. Proposals for market homes will only be supported
where the contribution to the provision of affordable homes on a site will be at least 25%
of the total number of homes, unless the LDP sets out locations or circumstances where:
i. a higher contribution is justified by evidence of need, or
ii. a lower contribution is justified, for example, by evidence of impact on viability,
where proposals are small in scale, or to incentivise particular types of homes
that are needed to diversify the supply, such as self-build or wheelchair
accessible homes.
The contribution is to be provided in accordance with local policy or guidance.

Page 25

LDP2 format template March 4th 2024
Report of Handling Template for PPSL and Delegated Planning Applications – Updated 10.11.2023 
With regards to the affordability component of the development, as detailed above, the
site and its context within the wider Housing Allocation and the planning history of the
site, it is noted that the current planning application was submitted before the adoption of
LDP2 at a time when the total required provision of affordable units was 7.  The existing
and built Phase 1 and Phase 2 provided 10 affordable units, an over-provision of 3. 
During the determination period of the current application, however, the new LDP2 now
requires a total affordability component of 25%.  The current application proposes 6 new
units, none of them affordable.  The previous Phase 1 and Phase 2 permissions provided
20 units in total which, added to the 6 units the subject of the current application gives an
affordability requirement of just over 6 units (25% of 26 = 6.5). Therefore the existing
affordability provision of 10 units is still above the current requirement of 25% although it
is accepted that this is a pro-rata calculation and that any future additional development
within the housing allocation may require the provision of further affordable units, with a
potential need for three additional affordable dwellings should the total capacity of the
housing allocation (50 units) be reached. 
The proposed development is deemed to be consistent with NPF4 Policy 16 and
there is no conflict with LDP 2 Policy 01, Settlement Area with the current proposal
raising no issue of conflict. 
5.12. NPF4 Policy 17 – Rural Homes 
NPF4 Policy 17 seeks to encourage, promote and facilitate the delivery of more high
quality, affordable and sustainable rural homes in the right locations. 
Policy 17(a) supports development proposals for new homes in rural areas where the
development is suitably scaled, sited and designed to be in keeping with the character of
the area and (i) is on a site allocated for housing in the LDP. 
Policy 17(b) requires proposals for new homes in rural areas to consider how the
development will contribute towards local living and take into account identified local
housing needs.  It is has already been seen at NPF4 Policy 15 above that the proposed
development is consistent with our adopted settlement strategy policies and that it would
have no materially harmful access or environmental impact. The proposed development
seeks the introduction of 6 dwellinghouses which would accord with the Council’s key
planning policy aims of supporting and sustaining fragile rural communities by contributing
to actions to reverse our falling rural populations and supporting the local economy. In
this regard, the proposed development would directly support the local and national
‘housing emergency’. 
Policy 17(c) offers support to new homes in remote rural areas where such proposals (i)
support and sustain existing fragile communities; (ii) support identified local housing
outcomes; and (iii) are suitable in terms of location, access and environmental impact. 
The development proposed accords with the broad aims of NPF4 Policy 17 and
does not conflict with LDP2 Policy 09, Sustainable Development, Policy 10, Design
all Development, and Policy 67, Provision of Housing to Meet Local Needs. 
5.13. NPF4 Policy 18 – Infrastructure First 
NPF4 Policy 18 seeks to encourage, promote and facilitate an infrastructure first approach
to land use planning, which puts infrastructure considerations at the heart of placemaking.

Page 26

LDP2 format template March 4th 2024
Report of Handling Template for PPSL and Delegated Planning Applications – Updated 10.11.2023 
The application indicates water supply via connection to the public network with private
drainage arrangements comprising two septic tanks and soakaways due to the lack of
public drainage infrastructure within the vicinity of the site.   
Scottish Water raised no objection to the proposed development which would be serviced
from the Tullich Water Treatment Works but advised that further investigations may be
required once a formal application for connection to their infrastructure is submitted for
consideration.   
The Council’s Building Standards Service will apply sufficient control over the detailed
arrangements over the proposed private drainage arrangements at Building Warrant
stage. 
The proposed development aligns with NPF4 Policy 18 and is in accordance with
LDP2 Policy 04, Sustainable Development and Policy 60, Private Sewage Treatment
Plants and Wastewater Drainage Systems which seek to ensure that suitable
infrastructure is available to serve proposed developments and give support to
private drainage arrangements where connection to the public system is not
available and the current proposal would raise no issue of conflict should
permission be granted. 
5.14. NPF4 Policy 22 – Flood Risk and Water Management 
NPF4 Policy 22 seeks to strengthen resilience to flood risk and to ensure that water
resources are used efficiently and sustainably. 
As detailed above the development proposes connection to the public water supply to
which Scottish Water has not objected to.   
The site is within proximity of an area identified as having potential surface water flooding
issues and accordingly consultation was undertaken with the Council’s flooding advisors
JBA Consulting Ltd (JBA). 
JBA deferred their decision until evidence was provided that the surface water drainage
system has been designed in accordance with CIRIA C753 and Sewers for Scotland 4th
Edition, including: 
• Detailed drainage plan and drainage calculations, demonstrating that the post
development runoff rate does not exceed the greenfield runoff rate. 
• Evidence that the drainage network is designed to accommodate the 1:30 year
rainfall event plus climate change and a 10% allowance for future build out, and
that the 200 year plus climate change event does not flood existing or proposed
buildings. 
• Expected overland flow routes should the system be overtopped. 
The request from JBA resulted in ongoing correspondence between the agent and JBA
to agree a suitable scheme for the treatment of surface water within the development.  A
suitable system was agreed to which JBA has confirmed their acceptance to. 
With a condition to ensure that the surface water drainage system for the proposed
development is installed in accordance with the scheme agreed with JBA the
proposal aligns with NPF4 Policy 22 and LDP2 Policy 61, Sustainable Drainage
Systems and the current proposal would raise no issue of conflict should
permission be granted.

Page 27

LDP2 format template March 4th 2024
Report of Handling Template for PPSL and Delegated Planning Applications – Updated 10.11.2023 
6. Public Representation 
6.1.  At the time of writing, representations had been received by the Planning Authority from
19 respondents in relation to this planning application. 18 respondents raise objection and
1 provide representation. 
It is not considered that the objections raise any complex or technical issues that have
not been addressed in the current Report of Handling. 
7. Conclusion 
The principle of residential development on this site has been established by virtue of the
site being within Housing Allocation H4017 as defined in LDP2. 
No objections have been received from consultees with regards to the proposed
infrastructure to serve the proposed development. 
The proposed development is considered to be consistent with the provisions of both the
adopted National and Local Policy with the issues raised by third parties not amounting to
material planning considerations that have not been addressed through the processing of
the planning application. 
Accordingly the application is recommended for approval subject to conditions.